Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52000017495

V Aashraya · Vadghar (Ct), Raigarh · Atharva Developers

Promised for 31 Jan 2021, extended once to 30 Jul 2022 — and that date has passed without the project marked complete on MahaRERA.

5 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Jan 2021 to 30 Jul 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Jul 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate18 May 2020View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000017495

Is V Aashraya delayed?

Yes. MahaRERA records a promised completion of 31 Jan 2021, revised to 30 Jul 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000017495. The completion date moved from 31 Jan 2021 to 30 Jul 2022.

Who is the promoter?

MahaRERA records Atharva Developers as the promoter of P52000017495.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000017495.

Answers are generated from the record.

Data through9 Nov 2026, 02:00SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology