Abbasali Ahtesham Husain Haji

Individual promoter · 2 projects · 2 MahaRERA registrations · 2 reported completed

Projects22 RERA registrations
Completed2as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+9 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Vimaco Residency IIP50300004204Amravati (M Corp.)2017Completed30 Jun 2023—On date
Vimaco Gulmohar CondominiumP50300006416Amravati (M Corp.)2017Completed31 Dec 202030 Jun 2022+18 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Vimaco Residency IIOn date
  • Vimaco Gulmohar Condominium+18 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 18 months, for Vimaco Gulmohar Condominium (P50300006416).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology