Vimaco Gulmohar Condominium

Completed

Amravati (M Corp.), Amravati 444606 |Promoter: Abbasali Ahtesham Husain Haji

Residential / Group HousingRERAP50300006416
14 Aug 2017Registered with MahaRERA
31 Dec 2020Promised completion
30 Jun 2022Revised completionPushed back 1 year and 6 months
1Building
14Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
Commercial, Residential14 units in all
Land area for this project
445 sq m (4,787 sq ft)
Permissible built-up area
732 sq m (7,884 sq ft)
Sanctioned built-up area
732 sq m (7,884 sq ft)
Address
Sheeta No. 18-C, Nazul Plot No. 1PIN 444606
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.86760, 75.49855
Vimaco Gulmohar Condominium is at latitude 19.86760, longitude 75.49855.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year and 6 months

The latest completion date on record passed 4 years and 4 months ago.

Registered
14 Aug 2017
Promised
31 Dec 2020
Revised
30 Jun 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5030000641614 Aug 201731 Dec 202030 Jun 2022Abbasali Ahtesham Husain HajiProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Vimaco Gulmohar714

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

14 units registered

Commercial · 6 unitsResidential · 8 units
TypeCarpet areaUnits
Commercial118.46 sq m · 1,275 sq ft6
Residential523.12 sq m · 5,631 sq ft8

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Vimaco Gulmohar

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyNIL0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)NIL0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingCOMPLETED100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNIL0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

13 documents held by Deedo, 16 filings listed on MahaRERA's project page

Commencement certificate

Form b

Form 1

Form 2

Form 5

Registration certificate

Completion

Extension certificate

Others

Title

Layout plan

Building plan

Document library

  • Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM BForm B - Promoter.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 31 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 31 Jul 2017View
  • Copy of the legal title reportDeclaration.pdf · uploaded 31 Jul 2017View
  • Details of encumbrancesDeclaration.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterDeclaration.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)MAP.pdf · uploaded 31 Jul 2017View
  • Certificates of CA (Form 5)Form 5 - Gulmohar.pdf · uploaded 16 Jan 2019View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentvimaco gulmohar OC document.pdf · uploaded 3 Aug 2021View

Promoter documents

  • Declaration Form BForm B - Promoter.pdf · uploaded 31 Jul 2017View
  • Legal Title reportDeclaration.pdf · uploaded 31 Jul 2017View

Technical documents

  • Building Plan ApprovalMAP.pdfView
  • Layout ApprovalLayout Plan.pdfView

Proforma allotment letter

  • Proforma allotment letterDeclaration.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Amravati (M Corp.), Amravati taluka

Survey, CTS, gat or plot numbers

1NAZUL PLOT NO. 1SHEETA NO. 18CSHEETA NO. 18C

As published on MahaRERA's project page

SHEETA NO. 18-C, NAZUL PLOT NO. 1

Boundaries

North
Road
South
Service Line
East
Others House
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAdwait Saurkar—
EngineerAkash Dadhu—
OtherRitesh Laddha—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology