Motala, Buldana
No MahaRERA registration here has an extended completion date on record.
RERA projects2
Registrations2
Completion still due02 past their date
Median extensionNot on record0% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
2 MahaRERA registrations in Motala
2 past even the latest date
Projects in Motala
2 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Sahara ComplexSahara Construction And Developers | 1 yr 11 mo late | — | — |
| Jayshree BuildingRajesh Gulabchand Rathi | 2 yrs 10 mo late | — | — |
Most active promoters
- Rajesh Gulabchand Rathi1 project
- Sahara Construction And Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology