RERA projects in Bhandara (M Cl)

18 projects under 18 MahaRERA registrations, registered 2017–2023. 39% have a completion date extended beyond the one promised.

Locality
18RERA projects
18Registrations
1Completion still due17 past their completion date, 5 marked completed
9 monthsMedian extension beyond promised date39% of registrations extended
0Regulatory casesnone on MahaRERA's lists
50Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20178
20180
20190
20203
20213
20222
20232

Projects in Bhandara (M Cl)

18 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Singh TowerSandhya Virendra SinghP5060005052521 Apr 202331 Mar 202631 Jul 2026Extended 4 mo0
Vijay HibiscusVijay NikharP5060005051217 Apr 202331 Dec 202531 Dec 2025Promised date passed0
Neelkanth ApartmentGm BuildconP5060004661325 Aug 202231 May 202730 Sep 2027Extended 4 mo0
Doma EstatesShrawan Domaji SakoreP5060004607815 Jun 202231 Mar 202631 Jul 2026Extended 4 mo0
Vijay CommercialV Y Nikhar & AssociatesP5060003236329 Dec 202131 Dec 202331 Dec 2023Promised date passed0
Urban CommercialsNeewas Infraspaces Private LimitedP5060003181712 Nov 202131 Mar 202231 Dec 2022Extended 9 mo0
Galaxy Apartment----IIGalaxy Builders & DevelopersP5060002790214 Jan 202130 Jun 202430 Jun 2024Promised date passed0
Excel TowerExcel TowerP5060002749814 Dec 202030 Apr 202430 Apr 2024Promised date passed0
Gaurav KalashGaurav BuildersP506000256751 Jul 202030 Jun 202330 Jun 2023Promised date passed0
Krishna Nagari Phase IISunny ConstructionsP506000256721 Jul 202030 Sep 202330 Jun 2025Extended 21 mo0
Gopal TowerAswale InfraP506000129717 Sep 201731 Mar 201831 Mar 2018Promised date passed0
Gp TowerGp DevelopersP506000127277 Sep 201731 Dec 201930 Dec 2021Extended 24 mo0
Rajbhav PalaceSuresh Bhanwarlal Munot JainP506000129227 Sep 201731 Dec 201931 Dec 2019Promised date passed0
construction of 26 shops and 03 halls at khat road BhandaraMHADA(Nagpur Board)P506000126406 Sep 201728 Feb 2018—Completed0
Surya Tower-IIIBirendra Kamdeo SinghP5060001121331 Aug 201731 Jan 201931 Jan 2020Completed0
Vijay SunstoneV Y Nikhar & AssociatesP5060000837518 Aug 201730 Dec 2022—Completed0
Vijay SilicaV Y Nikhar & AssociatesP5060000774917 Aug 201730 Dec 2022—Completed0
Anand ResidencyAnurag DevelopersP506000027784 Aug 201731 Oct 2018—Completed0

Other localities in Bhandara

Most active promoters

By projects registered here, as named on MahaRERA.

  1. V Y Nikhar & Associates3 projects
  2. Anurag Developers1 project
  3. Aswale Infra1 project
  4. Birendra Kamdeo Singh1 project
  5. Excel Tower1 project
  6. Galaxy Builders & Developers1 project
  7. Gaurav Builders1 project
  8. Gm Buildcon1 project
  9. Gp Developers1 project
  10. MHADA(Nagpur Board)1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology