RERA projects in Bhandara
36 projects under 36 MahaRERA registrations across 6 localities, registered 2017–2024. 15% have a completion date extended beyond the one promised.
36RERA projectsin 6 localities
36Registrations
5Completion still due22 past their completion date, 7 marked completed
16 monthsMedian extension beyond promised date15% of registrations extended
4Regulatory caseson 4 projects
8Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 11 |
| 2018 | 1 |
| 2019 | 0 |
| 2020 | 4 |
| 2021 | 3 |
| 2022 | 3 |
| 2023 | 4 |
| 2024 | 1 |
Localities in Bhandara
By number of registered projects. Talukas and localities as MahaRERA names them.
Projects in Bhandara
36 projects registered with MahaRERA in this district and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Construction of 584 EWS flat under PMAY on kh no. 395, 396, 397, 398, 399 and 400 mouza BhandaraMHADA (Nagpur board) | P50600055513 | 2 Apr 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Saibaba ComplexKeshav Premlal Chindhalore (Huf) | P50600052219 | 31 Jul 2023 | 31 May 2026 | — | Promised date passed | 0 |
| Namdev ComplexPriti Mahaveer Nikhade | P50600050576 | 21 Apr 2023 | 31 Dec 2028 | — | Not yet due | 0 |
| Singh TowerSandhya Virendra Singh | P50600050525 | 21 Apr 2023 | 31 Mar 2026 | — | Promised date passed | 0 |
| Vijay HibiscusVijay Nikhar | P50600050512 | 17 Apr 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Neelkanth ApartmentGm Buildcon | P50600046613 | 25 Aug 2022 | 31 May 2027 | — | Not yet due | 0 |
| Arya AppartmentLaxman Tejram Babhare | P50600046314 | 22 Jun 2022 | 31 Mar 2027 | — | Not yet due | 0 |
| Doma EstatesShrawan Domaji Sakore | P50600046078 | 15 Jun 2022 | 31 Mar 2026 | — | Promised date passed | 0 |
| Vijay CommercialV Y Nikhar & Associates | P50600032363 | 29 Dec 2021 | 31 Dec 2023 | — | Promised date passed | 0 |
| Urban CommercialsNeewas Infraspaces Private Limited | P50600031817 | 12 Nov 2021 | 31 Mar 2022 | 31 Dec 2022 | Extended 9 mo | 0 |
| Galaxy Apartment----IIGalaxy Builders & Developers | P50600027902 | 14 Jan 2021 | 30 Jun 2024 | — | Promised date passed | 0 |
| Excel TowerExcel Tower | P50600027498 | 14 Dec 2020 | 30 Apr 2024 | — | Promised date passed | 0 |
| Gaurav KalashGaurav Builders | P50600025675 | 1 Jul 2020 | 30 Jun 2023 | — | Promised date passed | 0 |
| Krishna Nagari Phase IISunny Constructions | P50600025672 | 1 Jul 2020 | 30 Sep 2023 | 30 Jun 2025 | Extended 21 mo | 0 |
| J. K. HeightsSky Developers And Promoters India Pvt. Ltd. | P50600023850 | 7 Jan 2020 | 31 Dec 2026 | — | Not yet due | 0 |
| Meera HeightsAkhilesh Sheshnarayan Gupta | P50600014887 | 9 Jan 2018 | 31 Mar 2019 | — | Promised date passed | 0 |
| Gopal TowerAswale Infra | P50600012971 | 7 Sep 2017 | 31 Mar 2018 | — | Promised date passed | 0 |
| Gp TowerGp Developers | P50600012727 | 7 Sep 2017 | 31 Dec 2019 | 30 Dec 2021 | Extended 24 mo | 0 |
| Rajbhav PalaceSuresh Bhanwarlal Munot Jain | P50600012922 | 7 Sep 2017 | 31 Dec 2019 | — | Promised date passed | 0 |
| construction of 26 shops and 03 halls at khat road BhandaraMHADA(Nagpur Board) | P50600012640 | 6 Sep 2017 | 28 Feb 2018 | — | Completed | 0 |
| Surya Towers - IIBirendra Kamdeo Singh | P50600012597 | 4 Sep 2017 | 30 Dec 2020 | — | Promised date passed | 0 |
| Surya Tower-IIIBirendra Kamdeo Singh | P50600011213 | 31 Aug 2017 | 31 Jan 2019 | 31 Jan 2020 | Completed | 0 |
| Dream City Project- Phase IDarshan Erectors Private Limited | P50600010003 | 23 Aug 2017 | 31 Dec 2018 | — | Completed | 0 |
| Surya Tower 1Balaji Builders And Developers | P50600009251 | 22 Aug 2017 | 31 Jan 2019 | — | Completed | 0 |
| Vijay SunstoneV Y Nikhar & Associates | P50600008375 | 18 Aug 2017 | 30 Dec 2022 | — | Completed | 0 |
| Vijay SilicaV Y Nikhar & Associates | P50600007749 | 17 Aug 2017 | 30 Dec 2022 | — | Completed | 0 |
| Anand ResidencyAnurag Developers | P50600002778 | 4 Aug 2017 | 31 Oct 2018 | — | Completed | 0 |
| Bela Gat No 200 | P50600003666 | — | — | — | — | 0 |
| Ln HomesL.n.infraventures | P50600045833 | — | — | — | — | 1 |
| ParadiseDivyansh Infraventure | P50600033369 | — | — | — | — | 1 |
| Sariputta Exotica Nagari | P50600019900 | — | — | — | — | 0 |
| Silver Spring | P50600009160 | — | — | — | — | 0 |
| Sunrise Apartments | P50600018093 | — | — | — | — | 0 |
| Sunshine TowerChandrashekhar Manik Motghare | P50600033969 | — | — | — | — | 1 |
| Venus MallAvani Infrastructure | P50600030778 | — | — | — | — | 1 |
| Yashoda Green | P50600016358 | — | — | — | — | 0 |
Other districts
- Pune13,424 projects
- Thane7,170 projects
- Mumbai Suburban6,592 projects
- Raigarh5,728 projects
- Nashik4,171 projects
- Palghar3,084 projects
- Nagpur2,793 projects
- Aurangabad1,469 projects
- Mumbai City1,380 projects
- Satara1,181 projects
- Ratnagiri1,138 projects
- Kolhapur863 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- V Y Nikhar & Associates3 projects
- Birendra Kamdeo Singh2 projects
- MHADA (Nagpur board)2 projects
- Akhilesh Sheshnarayan Gupta1 project
- Anurag Developers1 project
- Aswale Infra1 project
- Avani Infrastructure1 project
- Balaji Builders And Developers1 project
- Chandrashekhar Manik Motghare1 project
- Darshan Erectors Private Limited1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology