Residential / Group Housing · 1 building · 49 unitsRERA P51500016638

Nath Tower

Deedo IDDP-AUR-NSH8

MahaRERA shows it completed; no MahaRERA orders on record.

Satara (Ct), Aurangabad 431001 · by D N Developers

DeliveryCompletedAs MahaRERA showsRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 5 Jun 2018, completion promised 31 Dec 2019.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51500016638
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P515000166385 Jun 201831 Dec 2019—D N DevelopersProject page
Documents25

11 documents held by Deedo, 14 filings listed on MahaRERA's project page

Title report

Commencement certificate

Form B

Encumbrance details

Allotment letter (2)

Registration certificate

Form 4

Show all 25 documentsShow fewer documents

Other (2)

Layout plan

Document library

  • Declaration in FORM BFORM B.pdf · uploaded 29 May 2018View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 29 May 2018View
  • Copy of the legal title reportTitle Search Report.pdf · uploaded 29 May 2018View
  • Building Plan Approval (IOD)Building Plan Approval.pdf · uploaded 29 May 2018View
  • Copy of Layout Approval (in case of layout)Building Plan Approval.pdf · uploaded 29 May 2018View
  • Details of encumbrancesNo Encumbrances.pdf · uploaded 31 May 2018View
  • Proforma of Allotment letterProforma of Allotment Letter.pdf · uploaded 31 May 2018View
  • Proforma of Allotment letterAgreement For Sale.pdf · uploaded 31 May 2018View
  • Architect’s Certificate on Completion of Project (Form 4)form 4.pdf · uploaded 4 Nov 2020View

Promoter documents

  • Declaration Form BFORM B.pdf · uploaded 29 May 2018View
  • Legal Title reportTitle Search Report.pdf · uploaded 29 May 2018View

Technical documents

  • Building Plan ApprovalBuilding Plan Approval.pdfView
  • Layout ApprovalBuilding Plan Approval.pdfView

Proforma allotment letter

  • Proforma allotment letterProforma of Allotment Letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 39 to 44, 90/2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Unit types
2 BHK49 units in all
Address
39 to 44 and 90/2, Jalna Road, Jalna RoadPIN 431001
Village
Satara (CT), Aurangabad taluka
Land area for this project
1,062 sq m (11,433 sq ft)
Permissible built-up area
2,414 sq m (25,987 sq ft)
Sanctioned built-up area
2,414 sq m (25,987 sq ft)
Recreational open space
6,500 sq m (69,965 sq ft)
Designated bank account
RBL Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

39 to 4490/2

Land as published on MahaRERA's project page

39 to 44 and 90/2

Boundaries

North
36 MT Road
South
9 MT Road
East
8 MT Road
West
9 MT Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking49 units · 15 parking spaces

49 units registered

2 BHK · 49 units
TypeCarpet areaUnits
2 BHK43.5 sq m · 468 sq ft35
2 BHK48 sq m · 517 sq ft14

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space000014

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress2 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Nath Tower

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor50%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
  • Internal Roads & FootpathsNot applicable
  • Water SupplyRefer Form 150%
Show all 75 activitiesShow fewer activities
  • Water SupplyRefer Form 150%
  • Water SupplyRefer Form 150%
  • Water SupplyRefer Form 150%
  • Water SupplyRefer Form 150%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Refer Form 10%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Refer Form 10%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Refer Form 10%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Refer Form 10%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Refer Form 10%
  • Storm Water DrainsNot applicable
  • Storm Water DrainsNot applicable
  • Storm Water DrainsNot applicable
  • Storm Water DrainsNot applicable
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingRefer Form 10%
  • Landscaping & Tree PlantingRefer Form 10%
  • Landscaping & Tree PlantingRefer Form 10%
  • Landscaping & Tree PlantingRefer Form 10%
  • Landscaping & Tree PlantingRefer Form 10%
  • Street LightingNot applicable
  • Street LightingNot applicable
  • Street LightingNot applicable
  • Street LightingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Community BuildingsNot applicable
  • Community BuildingsNot applicable
  • Community BuildingsNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRefer Form 1100%
  • Water conservation /Rain water harvestingRefer Form 1100%
  • Water conservation /Rain water harvestingRefer Form 1100%
  • Water conservation /Rain water harvestingRefer Form 1100%
  • Water conservation /Rain water harvestingRefer Form 1100%
  • Energy managemcntNot applicable
  • Energy managemcntNot applicable
  • Energy managemcntNot applicable
  • Energy managemcntNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsRefer Form 10%
  • Fire protection and fire safety requirementsRefer Form 10%
  • Fire protection and fire safety requirementsRefer Form 10%
  • Fire protection and fire safety requirementsRefer Form 10%
  • Fire protection and fire safety requirementsRefer Form 10%
  • Electrical meter room, sub-station, receiving stationRefer Form 1100%
  • Electrical meter room, sub-station, receiving stationRefer Form 1100%
  • Electrical meter room, sub-station, receiving stationRefer Form 1100%
  • Electrical meter room, sub-station, receiving stationRefer Form 1100%
  • Electrical meter room, sub-station, receiving stationRefer Form 1100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingRefer Form 10%
  • Open ParkingRefer Form 10%
  • Open ParkingRefer Form 10%
  • Open ParkingRefer Form 10%
  • Open ParkingRefer Form 10%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDeva Group—

Source: MahaRERA project page. Contact details are not shown.