Wardhekar Complex

Completed

Amravati (M Corp.), Amravati 444601 |Promoter: Sindh Asssociate

14 Aug 2017Registered with MahaRERA
31 Mar 2018Promised completion
1Building
33Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Buildings
1
Unit types
Residential cum comm33 units in all
Land area for this project
374 sq m (4,030 sq ft)
Permissible built-up area
1,193 sq m (12,845 sq ft)
Sanctioned built-up area
1,193 sq m (12,845 sq ft)
Address
72PIN 444601
Designated bank account
State Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 21.02160, 77.82386
Wardhekar Complex is at latitude 21.02160, longitude 77.82386.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Mar 2018

The latest completion date on record passed 8 years and 7 months ago.

Registered
14 Aug 2017
Promised
31 Mar 2018

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5030000661214 Aug 201731 Mar 2018—Sindh AsssociateProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Wardhekar Complex533

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

33 units registered

Residential cum comm · 33 units
TypeCarpet areaUnits
Residential cum comm784.3 sq m · 8,442 sq ft33

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00001

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Wardhekar Complex

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyAS PER MAP100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)AS PER MAP100%
  • Storm Water DrainsAS PER MAP100%
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterAS PER MAP100%
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAS PER MAP100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationAS PER MAP100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

20 documents held by Deedo, 19 filings listed on MahaRERA's project page

Title

Encumbrance

Commencement certificate

Form b

Form 1s

Form 2s

Allotment letters

Registration certificate

Form 4

Completion

Others

Layout plan

Building plan

Document library

  • Copy of the legal title reportLEGAL TITLE REPORT CONBINE WARDHEKAR.pdf · uploaded 31 Jul 2017View
  • Details of encumbrancesSINDH NON ENCUMBRANCE CERTIFICATS.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)LAYOUT COPY WARDHEKAR COMPLEX.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment lettersindh associate allotment letter.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterDECLAIRATION FORM SINDH ASSOCIATES.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM Bform b sindh associatess.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)WARDHEKAR COMPLEX ARCHITECH CERTIFICATE.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)WARDHEKAR COMPLEX ENGG CERTIFICATE.pdf · uploaded 31 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentSANTION LATTER-ilovepdf-compressed.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)SANTION MAP-ilovepdf-compressed.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 4)4.pdf · uploaded 15 Apr 2019View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)1.pdf · uploaded 15 Apr 2019View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)2.pdf · uploaded 15 Apr 2019View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentSANKALP HEIGHT OC.pdf · uploaded 2 Aug 2021View

Promoter documents

  • Legal Title reportLEGAL TITLE REPORT CONBINE WARDHEKAR.pdf · uploaded 31 Jul 2017View
  • Declaration Form Bform b sindh associatess.pdf · uploaded 31 Jul 2017View

Technical documents

  • Layout ApprovalLAYOUT COPY WARDHEKAR COMPLEX.pdfView
  • Building Plan ApprovalSANTION MAP-ilovepdf-compressed.pdfView

Proforma allotment letter

  • Proforma allotment lettersindh associate allotment letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Amravati (M Corp.), Amravati taluka

Survey, CTS, gat or plot numbers

72

As published on MahaRERA's project page

72

Boundaries

North
30 Ft Road
South
Plot No 71
East
Shegaon Road
West
Service Lane

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRahul Farkade—
EngineerPankaj Deshmukh—
EngineerPravin Purankar—
OtherPravin Kasambe—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology