RERA projects in Supa

11 projects under 12 MahaRERA registrations, registered 2017–2026. None has an extended completion date on record.

11RERA projects
12Registrationssome projects hold several
4Completion still due8 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
1Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20173
20181
20191
20202
20212
20220
20232
20240
20250
20261

Projects in Supa

11 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Arihant HillsMadan Nemichand BafanaPR10100026018379 Sep 202615 Aug 2028—Not yet due0
Kartiki ViharUttam Baban RepaleP5220005219027 Jul 202331 Dec 2026—Not yet due0
Arihant PearlMadan Nemichand BafanaP5220005214624 Jul 202315 Aug 2027—Not yet due0
Arihant Park Phase 8Madan Nemichand BafanaP5220002794321 Jan 202130 Dec 2022—Promised date passed0
Mauli Green ParkMauli DevelopersP52200026981, P522000322857 Nov 202030 Jun 2028—Not yet due0
Arihant Park Phase 7Madan Nemichand BafanaP5220002469028 Feb 202030 Jun 2022—Promised date passed0
Arihantpark Phase-6Madan Nemichand BafanaP522000191499 Jan 201930 Dec 2020—Promised date passed0
Mauli PrasadPratibha Anand ShindeP522000162582 May 201811 Nov 2019—Promised date passed0
Arihant Park Phase - 4Madan Nemichand BafanaP5220001456915 Dec 201730 Sep 2019—Promised date passed0
Dream CityAbhijit Dadasaheb PathareP522000140517 Nov 20171 Apr 2023—Promised date passed0
Supa HightsSai Builders And DevelopersP5220001305814 Sep 201716 Dec 2019—Promised date passed0

Other localities in Parner

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Madan Nemichand Bafana6 projects
  2. Abhijit Dadasaheb Pathare1 project
  3. Mauli Developers1 project
  4. Pratibha Anand Shinde1 project
  5. Sai Builders And Developers1 project
  6. Uttam Baban Repale1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology