RERA projects in Jategaon
1 project under 1 MahaRERA registration, registered 2020–2020. None has an extended completion date on record.
Locality
1RERA projects
1Registrations
0Completion still due1 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2020 | 1 |
Projects in Jategaon
1 project registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Nature ValleyRadhakrushna Madhukar Kale | P52200027579 | 16 Dec 2020 | 30 Jun 2024 | 30 Jun 2024 | Promised date passed | 0 |
Other localities in Parner
Most active promoters
By projects registered here, as named on MahaRERA.
- Radhakrushna Madhukar Kale1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology