Nagar, Ahmednagar
Deedo IDDL-AHM-NAGAR8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects228
Registrations228
Completion still due54146 past their date
Median extension4 months24% of registrations extended
Regulatory cases2on 2 projects
8 in 10 registrations run late here
228 MahaRERA registrations in Nagar and the places within it
18 not yet due36 extended, not yet due146 past even the latest date28 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Nagar
228 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Adit Heritage | No date on record | — | — |
| Ashtavinayak | No date on record | — | — |
| Chatrapati Villa | No date on record | — | — |
| Chhatrapati Tower | No date on record | — | — |
| Ganraj Towers | No date on record | — | — |
| Gayatri Apartment | No date on record | — | — |
| Gsp Imperium | No date on record | — | — |
| J P Gulmohar | No date on record | — | — |
| Kalika Apartment | No date on record | — | — |
| Krushna Ganga Residency | No date on record | — | — |
| Naman Galaxy | No date on record | — | — |
| Nayantara | No date on record | — | — |
| P52200029074 | No date on record | — | — |
| P52200052826 | No date on record | — | — |
| P52200081107 | No date on record | — | — |
| Parshwanath Co-Operative Housing Society Limited | No date on record | — | — |
| Ronak Residency | No date on record | — | — |
| Sadgururesidency | No date on record | — | — |
| Sai Galaxy | No date on record | — | — |
| Sai Heritage | No date on record | — | — |
| Sai Rachana | No date on record | — | — |
| Shiv-Samrudhhi Heritage | No date on record | — | — |
| Shri Balbhimrao Doke Corner | No date on record | — | — |
| Shri Hari Row-Bunglows | No date on record | — | — |
| Torna Heights | No date on record | — | — |
Nearby: other talukas in Ahmednagar
Most active promoters
- Madhumalti Costruction Pvt Ltd7 projects
- Makarand Madhav Kulkarni6 projects
- Prasad Babanrao Andhale6 projects
- Kamath Associates5 projects
- Akash Construction4 projects
- Marc Developers4 projects
- Rajendra Ramchandra Pawar3 projects
- Suresh Namdev Lagad3 projects
- Ambadas Bhagwat Kadam2 projects
- Amit Ashok Mutha2 projects
Nagar, in questions
How many projects in Nagar run late?
8 in 10 MahaRERA registrations (182 of 228): their completion date was extended or has passed, data through 14 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nagar by Deedo. Medians on fewer than 3 deeds are not shown.
Data through14 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology