Nagar, Ahmednagar
Deedo IDDL-AHM-NAGAR8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects228
Registrations228
Completion still due54146 past their date
Median extension4 months24% of registrations extended
Regulatory cases2on 2 projects
8 in 10 registrations run late here
228 MahaRERA registrations in Nagar and the places within it
18 not yet due36 extended, not yet due146 past even the latest date28 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Nagar
228 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Shiv-Pushpa SerenitySpace Buildcon | Due Apr 2028, extended 4 mo | — | — |
| Ashwamedh Capital1Ashwamedh Spaces Private Limited | Completed | — | — |
| Swapn PurtiShubh Vastu Realty | Completed | — | — |
| Royal Palms II WingCharudatta Moreshwar Mulay | Completed | — | — |
| Darshan ParkBajaj And Chhabriya Associates | 5 yrs 10 mo late | — | — |
| Riddhi Siddhi HeightsRiddhi Siddhi Builders And Promoters | Completed | — | — |
| Samruddhi Row BunglowSubhash Laxman Kale | 3 yrs 8 mo late | — | — |
| Amin TowerShaan Associates | Completed | — | 57% |
| Construction of 96 Ts EWS, 6 Ts MIG, 40 shops and 1 MHADA office on F P No 109 110 savedi AhmednagaNashik Housing & Area Development Board | Completed | — | — |
| Sukhkarta ResidencyM S Kiran R Waghe | Completed | — | — |
| Sai Anand ResidencySai Anand Realty | Completed, extended 1 yr 6 mo | — | — |
| Shambhavi ApartmentRatnakar Marutirao Kulkarni | Completed | — | — |
| Utkarsha Phase - IIIMakarand Madhav Kulkarni | Completed | — | 35% |
| Siya Ram ResidencyMakarand Madhav Kulkarni | Completed | — | 31% |
| Parth HeightsRajendra Ramchandra Pawar | Completed | — | — |
| Amrutkalash Phase-03Madhumalti Costruction Pvt Ltd | Completed | — | 65% |
| Kamath GlitteratiKamath Associates | Completed | — | — |
| Adikailas Wing A03Madhumalti Costruction Pvt Ltd | Completed | — | 50% |
| Shoora ResidencyDinesh Sadashiv Kshirsagar | Completed | — | 35% |
| Veda HomesSawan Developers | Completed | — | — |
| Dk ResidencyDk Developers | Completed | — | — |
| Vedant Park IIIPrasad Babanrao Andhale | Completed | — | 100% |
| Gulmohor ParkPrasad Babanrao Andhale | Completed | — | 88% |
| Siddhi ResidencyPrasad Babanrao Andhale | Completed | — | 37% |
| Sant Wamanbhau ResidencyGurukrupa Associates | Completed | — | — |
Nearby: other talukas in Ahmednagar
Most active promoters
- Madhumalti Costruction Pvt Ltd7 projects
- Makarand Madhav Kulkarni6 projects
- Prasad Babanrao Andhale6 projects
- Kamath Associates5 projects
- Akash Construction4 projects
- Marc Developers4 projects
- Rajendra Ramchandra Pawar3 projects
- Suresh Namdev Lagad3 projects
- Ambadas Bhagwat Kadam2 projects
- Amit Ashok Mutha2 projects
Nagar, in questions
How many projects in Nagar run late?
8 in 10 MahaRERA registrations (182 of 228): their completion date was extended or has passed, data through 14 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nagar by Deedo. Medians on fewer than 3 deeds are not shown.
Data through14 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology