Nagar, Ahmednagar

Deedo IDDL-AHM-NAGAR

8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects228
Registrations228
Completion still due54146 past their date
Median extension4 months24% of registrations extended
Regulatory cases2on 2 projects

8 in 10 registrations run late here

228 MahaRERA registrations in Nagar and the places within it

18 not yet due36 extended, not yet due146 past even the latest date28 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nagar

228 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Shiv-Pushpa SerenitySpace BuildconDue Apr 2028, extended 4 mo——
Ashwamedh Capital1Ashwamedh Spaces Private LimitedCompleted——
Swapn PurtiShubh Vastu RealtyCompleted——
Royal Palms II WingCharudatta Moreshwar MulayCompleted——
Darshan ParkBajaj And Chhabriya Associates5 yrs 10 mo late——
Riddhi Siddhi HeightsRiddhi Siddhi Builders And PromotersCompleted——
Samruddhi Row BunglowSubhash Laxman Kale3 yrs 8 mo late——
Amin TowerShaan AssociatesCompleted—57%
Construction of 96 Ts EWS, 6 Ts MIG, 40 shops and 1 MHADA office on F P No 109 110 savedi AhmednagaNashik Housing & Area Development BoardCompleted——
Sukhkarta ResidencyM S Kiran R WagheCompleted——
Sai Anand ResidencySai Anand RealtyCompleted, extended 1 yr 6 mo——
Shambhavi ApartmentRatnakar Marutirao KulkarniCompleted——
Utkarsha Phase - IIIMakarand Madhav KulkarniCompleted—35%
Siya Ram ResidencyMakarand Madhav KulkarniCompleted—31%
Parth HeightsRajendra Ramchandra PawarCompleted——
Amrutkalash Phase-03Madhumalti Costruction Pvt LtdCompleted—65%
Kamath GlitteratiKamath AssociatesCompleted——
Adikailas Wing A03Madhumalti Costruction Pvt LtdCompleted—50%
Shoora ResidencyDinesh Sadashiv KshirsagarCompleted—35%
Veda HomesSawan DevelopersCompleted——
Dk ResidencyDk DevelopersCompleted——
Vedant Park IIIPrasad Babanrao AndhaleCompleted—100%
Gulmohor ParkPrasad Babanrao AndhaleCompleted—88%
Siddhi ResidencyPrasad Babanrao AndhaleCompleted—37%
Sant Wamanbhau ResidencyGurukrupa AssociatesCompleted——
Nagar market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Madhumalti Costruction Pvt Ltd7 projects
  2. Makarand Madhav Kulkarni6 projects
  3. Prasad Babanrao Andhale6 projects
  4. Kamath Associates5 projects
  5. Akash Construction4 projects
  6. Marc Developers4 projects
  7. Rajendra Ramchandra Pawar3 projects
  8. Suresh Namdev Lagad3 projects
  9. Ambadas Bhagwat Kadam2 projects
  10. Amit Ashok Mutha2 projects

Nagar, in questions

How many projects in Nagar run late?

8 in 10 MahaRERA registrations (182 of 228): their completion date was extended or has passed, data through 14 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nagar by Deedo. Medians on fewer than 3 deeds are not shown.

Data through14 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology