RERA projects in Wani (M Cl)
7 projects under 7 MahaRERA registrations, registered 2017–2026. 14% have a completion date extended beyond the one promised.
Locality
7RERA projects
7Registrations
1Completion still due6 past their completion date, 2 marked completed
31 monthsMedian extension beyond promised date14% of registrations extended
1Regulatory caseson 1 project
19Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 2 |
| 2019 | 0 |
| 2020 | 1 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 1 |
| 2024 | 0 |
| 2025 | 0 |
| 2026 | 1 |
Projects in Wani (M Cl)
7 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Gopal ResidencyKg Dikundwar | PM1360002601765 | 3 Sep 2026 | 31 May 2031 | — | Not yet due | 0 |
| Ishwar NagarDeepak Mandokar And Mahesh Batra | P51000050903 | 15 May 2023 | 31 Mar 2026 | — | Promised date passed | 0 |
| dwarka cityM/s 3 M INFRA | P51000023704 | 2 Jan 2020 | 30 Mar 2023 | — | Promised date passed | 0 |
| Mahalaxmi AppartmentShalik Mahadeorao Urkude | P51000015251 | 8 Feb 2018 | 31 May 2019 | — | Completed | 0 |
| Aamer Tower IIJamir Mahaboob Khan | P51000015004 | 22 Jan 2018 | 30 Dec 2021 | 24 Jul 2024 | Extended 31 mo | 0 |
| Shrihari ResidencyVijaya Infraventures | P51000014550 | 12 Dec 2017 | 31 Dec 2018 | — | Completed | 0 |
| Ram Shewalkar ParisarShewalkar Developers Limited | P51000009928 | 22 Aug 2017 | 15 Apr 2026 | — | Promised date passed | 1 |
Other localities in Wani
- Ganeshpur2 projects
- Chikhalgaon1 project
Most active promoters
By projects registered here, as named on MahaRERA.
- Deepak Mandokar And Mahesh Batra1 project
- Jamir Mahaboob Khan1 project
- Kg Dikundwar1 project
- M/s 3 M INFRA1 project
- Shalik Mahadeorao Urkude1 project
- Shewalkar Developers Limited1 project
- Vijaya Infraventures1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology