RERA projects in Yavatmal
65 projects under 67 MahaRERA registrations across 16 localities, registered 2017–2026. 12% have a completion date extended beyond the one promised.
65RERA projectsin 16 localities
67Registrationssome projects hold several
8Completion still due41 past their completion date, 15 marked completed
27 monthsMedian extension beyond promised date12% of registrations extended
9Regulatory caseson 8 projects
115Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 16 |
| 2018 | 5 |
| 2019 | 2 |
| 2020 | 5 |
| 2021 | 6 |
| 2022 | 6 |
| 2023 | 2 |
| 2024 | 1 |
| 2025 | 2 |
| 2026 | 4 |
Localities in Yavatmal
By number of registered projects. Talukas and localities as MahaRERA names them.
Projects in Yavatmal
65 projects registered with MahaRERA in this district and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Gopal ResidencyKg Dikundwar | PM1360002601765 | 3 Sep 2026 | 31 May 2031 | — | Not yet due | 0 |
| Mauli ApartmentsMahek Constructions | PM1360002600155 | 17 Apr 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Samruddhi Heights 1Aarpm Trading Enterprises Private Limited | P51000081106 | 12 Mar 2026 | 31 Dec 2028 | — | Not yet due | 0 |
| Vakratund ResidencyM/s. Khandve Developers | PR1360002502285 | 6 Feb 2026 | 31 Dec 2028 | — | Not yet due | 0 |
| Gokuldham GreensSwastik Infra | PR1360002501794 | 15 Dec 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Gold SukhRadhay Infra | PM1360002501434 | 11 Nov 2025 | 1 May 2027 | — | Not yet due | 0 |
| Lok8 GrandeurLok8 Infra Private Limited | P51000077074 | 23 Jul 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Ishwar NagarDeepak Mandokar And Mahesh Batra | P51000050903 | 15 May 2023 | 31 Mar 2026 | — | Promised date passed | 0 |
| Aamer TownshipZameer Khan Maheboob Khan Khan | P51000048632 | 10 Jan 2023 | 31 Oct 2025 | — | Promised date passed | 0 |
| Shri ResidencyShri Associate | P51000047846 | 28 Nov 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Jayale Elites ApartmentHarshad Arun Jayale | P51000045838 | 15 Jun 2022 | 30 Nov 2023 | — | Promised date passed | 1 |
| New Mata NagarMahesh K. Batra & 1 Other | P51000034481 | 11 Apr 2022 | 31 Mar 2025 | — | Promised date passed | 0 |
| Hari Om NagarDhanraj Ramkrushnaji Bhalerao & 3 Others | P51000033784 | 8 Mar 2022 | 31 Mar 2023 | — | Promised date passed | 0 |
| Vrundawan TownPawansut Land Developer | P51000032949 | 2 Feb 2022 | 31 Mar 2025 | — | Promised date passed | 0 |
| Smd TowerSmd Infrastructure | P51000032465 | 4 Jan 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| Mauli ParkVinod P Dhoble , Sunil P Dhoble and Dhanraj R Bhalerao | P51000032121 | 14 Dec 2021 | 31 Mar 2024 | — | Promised date passed | 0 |
| Shukratara ApartmentP & G Developers | P51000031806 | 12 Nov 2021 | 31 Mar 2023 | — | Promised date passed | 0 |
| Suvarna EnclaveSuhas Suresh Gatalwar | P51000029701 | 26 Jun 2021 | 31 May 2024 | — | Promised date passed | 0 |
| P and G PARKP & G Developers | P51000029375 | 29 May 2021 | 31 Mar 2023 | — | Promised date passed | 0 |
| Ishwar NagarMahesh Keshardasji Batra And Firoz Faruk Husain | P51000028227 | 18 Feb 2021 | 30 Sep 2023 | — | Promised date passed | 0 |
| Shri Ram CityPravin Gunvantrao Ghurde | P51000027983 | 24 Jan 2021 | 31 Jul 2026 | — | Promised date passed | 0 |
| Nalini Krishna RenaissanceShri Krishna Promoters | P51000027090 | 13 Nov 2020 | 30 Jun 2022 | 30 Jun 2023 | Extended 12 mo | 0 |
| Vighnaharta Nagar Unit 1Vishal Langade Savita Cahfle Jyoti Sharma Sudhir Chafle And Tushar Lonkar | P51000026073 | 15 Aug 2020 | 30 Mar 2022 | — | Promised date passed | 0 |
| Vighnaharta Nagar Unit 2Sunil Langde Savita Chafle Sanjay Sharma Sudhir Chafle And Tushar Lonkar | P51000026087 | 15 Aug 2020 | 30 Mar 2022 | — | Promised date passed | 0 |
| Vedant ResidencyAtul Nagesh Deshpande | P51000024504 | 18 Feb 2020 | 30 Dec 2024 | — | Promised date passed | 0 |
| dwarka cityM/s 3 M INFRA | P51000023704 | 2 Jan 2020 | 30 Mar 2023 | — | Promised date passed | 0 |
| WestendCotton City Infrabuild Pvt. Ltd. | P51000021155 | 14 Jun 2019 | 30 Mar 2026 | — | Promised date passed | 0 |
| Chintamani NagriRajendra Swarupchand Kothari | P51000019150 | 9 Jan 2019 | 31 Mar 2019 | — | Promised date passed | 0 |
| Gokuldham ResidencyAbhishek Ghanshyamji Bagdi | P51000017532 | 24 Aug 2018 | 15 Dec 2022 | — | Promised date passed | 0 |
| Viraj CityRashmi Sanjay Bang | P51000015777 | 26 Mar 2018 | 31 Dec 2018 | — | Completed | 0 |
| Mahalaxmi AppartmentShalik Mahadeorao Urkude | P51000015251 | 8 Feb 2018 | 31 May 2019 | — | Completed | 0 |
| Aamer Tower IIJamir Mahaboob Khan | P51000015004 | 22 Jan 2018 | 30 Dec 2021 | 24 Jul 2024 | Extended 31 mo | 0 |
| Shrihari ResidencyVijaya Infraventures | P51000014550 | 12 Dec 2017 | 31 Dec 2018 | — | Completed | 0 |
| Tirumala PridePrachi Avinash Pampattiwar | P51000014307 | 20 Nov 2017 | 1 Nov 2020 | — | Completed | 0 |
| Tirupati-2Shri Tirupati Corporations | P51000013954 | 2 Nov 2017 | 10 Oct 2019 | — | Completed | 0 |
| Sai Shopping ComplexSai Developers | P51000013171 | 15 Sep 2017 | 1 Aug 2020 | — | Completed | 0 |
| Aai PrasadVasant Nivrutti Narwade | P51000011716 | 31 Aug 2017 | 25 Mar 2018 | — | Completed | 0 |
| Madhulata ResidencyManish Madhusudan Agrawal | P51000011182 | 31 Aug 2017 | 30 Jun 2023 | — | Completed | 0 |
| Vidarbhapremier Nagri YavatmalPrakash Narayanrao Raole | P51000011689 | 31 Aug 2017 | 31 Dec 2019 | 30 Dec 2021 | Completed | 0 |
| Ram Shewalkar ParisarShewalkar Developers Limited | P51000009928 | 22 Aug 2017 | 15 Apr 2026 | — | Promised date passed | 1 |
| R M Dhariwal Greens YavatmalDhariwal And Chhoriya Developers LLP | P51000009219, P51000012173, P51000015553 | 22 Aug 2017 | 30 Jun 2021 | 31 Dec 2023 | Completed | 2 |
| Maniganesh TowerKishorkumar Bajranglalji Chokhani | P51000008147 | 18 Aug 2017 | 31 Dec 2017 | — | Completed | 0 |
| Prabhukunj AppartmentTuljai Developers | P51000007459 | 17 Aug 2017 | 31 Dec 2019 | — | Completed | 0 |
| Ranwara AppartmentPuri Enginneing Marvels | P51000005291 | 11 Aug 2017 | 31 Dec 2019 | — | Completed | 0 |
| Sheetal PlazaSachin Suresh Jirapure | P51000004005 | 7 Aug 2017 | 31 Dec 2018 | — | Completed | 0 |
| Tirupati ImperialsShri Tirupati Corporations | P51000001829 | 29 Jul 2017 | 4 Apr 2021 | — | Promised date passed | 0 |
| Viraj Shopping MallViraj Shopping Mall | P51000001945 | 29 Jul 2017 | 28 Apr 2019 | — | Completed | 0 |
| Anand Sagar Residency I | P51000019763 | — | — | — | — | 0 |
| Ayodhya Nagari | P51000034536 | — | — | — | — | 0 |
| Balaji Nagri | P51000024028 | — | — | — | — | 0 |
| Bhauraoji Shete NagarBhushan Bhaurao Shete | P51000029621 | — | — | — | — | 1 |
| jyoti savitri vihar | P51000010707 | — | — | — | — | 0 |
| Late Ramsaran Ji Juneja Nagri | P51000045207 | — | — | — | — | 0 |
| Late Ramsaran Ji Juneja Nagri | P51000045249 | — | — | — | — | 0 |
| Morya Residency | P51000006044 | — | — | — | — | 0 |
| Om Varco Regency Phase-1 | P51000003720 | — | — | — | — | 0 |
| Oracle LuxuriaRavindra Balkrishna Phadke | P51000002580 | — | — | — | — | 1 |
| Prathmesh Sankul | P51000011179 | — | — | — | — | 0 |
| Ram NagarSudhakar Narayanrao Argulwar | P51000029294 | — | — | — | — | 1 |
| ram tower | P51000013268 | — | — | — | — | 0 |
| R M Dhariwal Greens Yavatmal Phase 4 - Oakwood Residency | P51000024031 | — | — | — | — | 0 |
| Rupmati Shete NagarRajiv and Sanjay Shete | P51000026436 | — | — | — | — | 1 |
| Shamsh NagarDilshad Shamshuddin Gilani | P51000032407 | — | — | — | — | 1 |
| Shree Uddhav Baba Nagari | P51000030726 | — | — | — | — | 0 |
| Sweet Home Residency | P51000006064 | — | — | — | — | 0 |
Other districts
- Pune13,424 projects
- Thane7,170 projects
- Mumbai Suburban6,592 projects
- Raigarh5,728 projects
- Nashik4,171 projects
- Palghar3,084 projects
- Nagpur2,793 projects
- Aurangabad1,469 projects
- Mumbai City1,380 projects
- Satara1,181 projects
- Ratnagiri1,138 projects
- Kolhapur863 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- P & G Developers2 projects
- Shri Tirupati Corporations2 projects
- Aarpm Trading Enterprises Private Limited1 project
- Abhishek Ghanshyamji Bagdi1 project
- Atul Nagesh Deshpande1 project
- Bhushan Bhaurao Shete1 project
- Cotton City Infrabuild Pvt. Ltd.1 project
- Deepak Mandokar And Mahesh Batra1 project
- Dhanraj Ramkrushnaji Bhalerao & 3 Others1 project
- Dhariwal And Chhoriya Developers LLP1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology