Shubham Artesia
Deedo IDDP-THN-V3CYCompletion was pushed back 4 months, to Apr 2032; no MahaRERA orders on record; 4% of its units are booked.
Vashi, Thane 400703 · by Akshay Enterprises Realty LLP
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2032
- This projectRegistered 16 Jun 2026, completion promised 31 Dec 2031, revised to 30 Apr 2032.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- Wing-A21 floors · 82 units0% booked
- Wing-B22 floors · 85 units0% booked
- Wing-C27 floors · 128 units4% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPM1330002600815
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PM1330002600815 | 16 Jun 2026 | 31 Dec 2031 | 30 Apr 2032 | Akshay Enterprises Realty LLP | Project page |
Documents33
1 document held by Deedo, 32 filings listed on MahaRERA's project page
Finance
Legal
- Declaration Form BFORM B Final Promoter Notarised_compressed.pdf · uploaded 1 Jun 2026Source
- OthersDis of interest in Other Org DLS Signed.pdf · uploaded 2 Jun 2026Source
- OthersPast Experience duly Notarised.pdf · uploaded 2 Jun 2026Source
- Declaration Form BSHUBHAM Lease Deed.pdf · uploaded 2 Jun 2026Source
Show all 33 documentsShow fewer documents
Legal
Migrated
- Withdrawal Update Form 1AERLLP Architect Certificate_220726.pdf · uploaded 28 Jul 2026Source
- Withdrawal Update Form 2Engineer Certificate Akshay Enterprises Reality LLP.pdf · uploaded 28 Jul 2026Source
- Withdrawal Update Form 3AERLLP CA Certificate_270726_compressed (1).pdf · uploaded 28 Jul 2026Source
Planning Authority
- Document1777895093_NMMCC-25-102506_R0.html · uploaded 28 May 2026Source
- DocumentkgLnv5akJ98_SUPPLEMENTARY_LEASE_DEED.pdf · uploaded 28 May 2026Source
- Document1777895093_NMMCC-25-102506_R0.pdf_2_58DSE_Sign.pdfSign.pdf · uploaded 28 May 2026Source
- DocumentkgLnv5akJ97_POWER_OF_ATTORNEY.pdf · uploaded 28 May 2026Source
- DocumentCert_B_642021_447F0OokSign.pdf · uploaded 28 May 2026Source
Technical
- DocumentCopy of layout_compressed.pdf · uploaded 3 Jun 2026Source
- DocumentCC DRAWING SIGNED (1)-2.pdf · uploaded 3 Jun 2026Source
- DocumentCC DRAWING SIGNED (1)-3.pdf · uploaded 3 Jun 2026Source
- DocumentCC DRAWING SIGNED (1)-4.pdf · uploaded 3 Jun 2026Source
- DocumentCC DRAWING SIGNED (1)-5.pdf · uploaded 3 Jun 2026Source
- DocumentCC DRAWING SIGNED (1)-6.pdf · uploaded 3 Jun 2026Source
- DocumentCC DRAWING SIGNED (1)-7.pdf · uploaded 3 Jun 2026Source
- DocumentCC DRAWING SIGNED (1)-8.pdf · uploaded 3 Jun 2026Source
- DocumentCC DRAWING SIGNED (1)-9.pdf · uploaded 3 Jun 2026Source
- DocumentCC DRAWING SIGNED (1)-10.pdf · uploaded 3 Jun 2026Source
- DocumentCC DRAWING SIGNED (1)-11.pdf · uploaded 3 Jun 2026Source
- DocumentCC DRAWING SIGNED (1)-12.pdf · uploaded 3 Jun 2026Source
- DocumentANNEXURE A Order No 50_signed (2).pdf · uploaded 5 Jun 2026Source
Technical (Architect)
- DocumentAERLLP Architect Certificate_220726.pdf · uploaded 28 Jul 2026Source
Technical (Engineer)
- DocumentEngineer Certificate Akshay Enterprises Reality LLP.pdf · uploaded 28 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Plot no. 1 Gut no 16
As registered with MahaRERA and published on its project page
- Project type
- Mixed
- Status on MahaRERA
- Certificate Signed
- Unit types
- —295 units in all
- Address
- SECTOR-16, JuhuPIN 400703
- Village
- Vashi, Thane taluka
- Location
- 19.07708, 72.99922
- Land area for this project
- 5,471 sq m (58,884 sq ft)
- Permissible built-up area
- 30,795 sq m (3,31,473 sq ft)
- Sanctioned built-up area
- 30,792 sq m (3,31,440 sq ft)
- Recreational open space
- 801 sq m (8,620 sq ft)
- Designated bank account
- 85
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
plot_no 1 city_survey_gut_no 16 final_plot_no 1 sector_no 16 mauje VASHI road_street - society -
Boundaries
- North
- 9 Mtr Wide Existing Road
- South
- 14 Mtr Wide Existing Road
- East
- 11 Mtr Wide Existing Road
- West
- 32 Mtr Wide Existing Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking295 units
295 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Wing-A | — | — | 82 |
| Wing-B | — | — | 85 |
| Wing-C | — | — | 128 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Chartered accountant | Kailesh Ramesh Thakkar | — |
| Engineer | Aniket Suresh Kumbhar | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Vashi
- Chintamani PlanetRERA PM1330002602366
- Satyam VelouraRERA PR1330002601366
- Gami AyurRERA PR1330002600552
- Kamdhenu Center OneRERA PC1330002600253
- Satyam AshtavinayakRERA PR1330002600132
- Tulsi HeritageRERA PR1330002502652
- Akshar ElevateRERA PC1330002502427
- Kamdhenu ConquestRERA PC1330002502300
All 28 projects in Vashi · Compare Shubham Artesia with another project