MahaRERA shows it completed; no MahaRERA orders on record; 100% of its units are booked.

Usatane, Thane 421502 · by Krushan Dham Builders & Developers

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked48 of 48 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 15 Feb 2018, completion promised 30 Dec 2022.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700015294
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170001529415 Feb 201830 Dec 202230 Dec 2022Krushan Dham Builders & DevelopersProject page
Documents36

2 documents held by Deedo, 34 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN CARD - KRUSHAN DHAM BUILDERS.pdf · uploaded 31 Jan 2018Source

Legal

  • Legal Title reportLEGAL TITLE REPORT - KRUSHAN DHAM BUILDERS (1).pdf · uploaded 1 Feb 2018Source
  • Declaration Form BFORM B - KRUSHAN DHAM BUILDERS (1).pdf · uploaded 1 Feb 2018Source
  • Other – LegalREQUEST TO WAIVE COMPLIANCE OF OC - P51700015294.pdf · uploaded 12 Jan 2024Source

Migrated

  • 1 PAN CardPAN CARD - KRUSHAN DHAM BUILDERS.pdf · uploaded 31 Jan 2018Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN - KRUSHAN DHAM BUIILDERS.pdf · uploaded 31 Jan 2018Source
Show all 36 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval (IOD)COMMENCEMENT CERTIFICATE - KRUSHAN DHAM BUILDERS.pdf · uploaded 31 Jan 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE - KRUSHAN DHAM BUILDERS.pdf · uploaded 31 Jan 2018Source
  • 1 Copy of the legal title reportLEGAL TITLE REPORT - KRUSHAN DHAM BUILDERS (1).pdf · uploaded 1 Feb 2018Source
  • 1 Details of encumbrancesDETAILS OF ENCUMBRANCES - KRUSHAN DHAM BUILDERS.pdf · uploaded 1 Feb 2018Source
  • 1 Declaration in FORM BFORM B - KRUSHAN DHAM BUILDERS (1).pdf · uploaded 1 Feb 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE - KRUSHAN DHAM BUILDERS.pdf · uploaded 1 Feb 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE - KRUSHAN DHAM BUILDERS.pdf · uploaded 1 Feb 2018Source
  • 1 Certificates of CA (Form 3)CA CERTIFICATE - KRUSHAN DHAM BUILDERS.pdf · uploaded 1 Feb 2018Source
  • 1 Proforma of Allotment letterProforma of the allotment letter and agreement for sale - KRUSHNA DHAM BUILDERS.pdf · uploaded 1 Feb 2018Source
  • 1 Certificates of CA (Form 5)Certificates of CA (Form 5) - KRUSHAN DHAM BUILDERS AND DEVELOPERS.pdf · uploaded 28 Sep 2018Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 RERA.pdf · uploaded 31 Dec 2021Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE.pdf · uploaded 24 May 2023Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 - KRUSHAN DHAM BUILDERS AND DEVELOPERS.pdf · uploaded 24 May 2023Source
  • 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD AND BOOKED INVENTORY.pdf · uploaded 24 May 2023View
  • 2 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 24 May 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5 - 18-19.pdf · uploaded 24 May 2023Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOCCUPANCY CERTIFICATE - KRUSHAN DHAM BUILDERS AND DEVELOPERS.pdf · uploaded 24 May 2023Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Registration - KRUSHAN DHAM BUILDERS AND DEVELOPERS.pdf · uploaded 24 May 2023Source
  • 1 Status of ConveyanceCONVEYANCE DEED - KRUSHAN DHAM BUILDERS AND DEVELOPERS.pdf · uploaded 24 May 2023Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE.pdf · uploaded 31 May 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM - 5 - 2021-2022.pdf · uploaded 22 Jun 2023Source
  • 1 Other – LegalREQUEST TO WAIVE COMPLIANCE OF OC - P51700015294.pdf · uploaded 12 Jan 2024Source
  • 4 Architect’s Certificate on Completion of Project (Form 4)REQUEST FOR WAIVE OF OC.pdf · uploaded 10 Feb 2024Source
  • 5 Architect’s Certificate on Completion of Project (Form 4)FORM 4 - KRUSHAN DHAM BUILDERS AND DEVELOPERS.pdf · uploaded 10 Feb 2024Source

Technical

  • DocumentLAYOUT PLAN - KRUSHAN DHAM BUIILDERS.pdf · uploaded 31 Jan 2018Source
  • DocumentCOMMENCEMENT CERTIFICATE - KRUSHAN DHAM BUILDERS.pdf · uploaded 31 Jan 2018Source

Technical (Architect)

  • DocumentARCHITECT CERTIFICATE.pdf · uploaded 24 May 2023Source

Technical (Engineer)

  • DocumentENGINEER CERTIFICATE.pdf · uploaded 31 May 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel PLOT NO. 193/1/2 PART

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1 BHK, 1 RK48 units in all
Address
Plot No. 193/1/2 Part, Usatane, UsatanePIN 421502
Village
Usatane, Ambarnath taluka
Land area for this project
2,000 sq m (21,528 sq ft)
Permissible built-up area
1,889 sq m (20,335 sq ft)
Sanctioned built-up area
1,889 sq m (20,335 sq ft)
Recreational open space
253 sq m (2,723 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

PLOT NO. 193/1/2 PART

Land as published on MahaRERA's project page

PLOT NO. 193/1/2 PART

Boundaries

North
Survey No 193-1
South
Survey No 193-3 And Gaonthan
East
Survey No 193-4
West
Survey No 2

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking48 units

48 of 48 units booked (100%), as the promoter reported to MahaRERA

1 BHK · 15 units1 RK · 33 units
TypeCarpet areaUnitsBooked
1 BHK28.34 sq m · 305 sq ft66
1 BHK36.98 sq m · 398 sq ft33
1 BHK37.65 sq m · 405 sq ft66
1 RK25.85 sq m · 278 sq ft2121
1 RK29.77 sq m · 320 sq ft99
1 RK29.83 sq m · 321 sq ft33

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectJeetendra Parmar—
EngineerYateesh Tare—

Source: MahaRERA project page. Contact details are not shown.