Promised date passed11 floorsRERA P51700012072
Main building, Vakratund
Deedo IDDP-THN-46D6-VAKRATMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked31%4 of 13 · MahaRERA
Completion31 Jul 2018as registered
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 32.3 m² (348 sq.ft) | 4 | 1 |
| 1BHK | 25.8 m² (277 sq.ft) | 5 | 3 |
| 1RK | 23.8 m² (256 sq.ft) | 1 | 0 |
| OFFICE | 65.7 m² (707 sq.ft) | 1 | 0 |
| SHOP | 10.7 m² (115 sq.ft) | 1 | 0 |
| SHOP | 17.4 m² (187 sq.ft) | 1 | 0 |
As registered with MahaRERA
- RERA registration
- P51700012072 · registered 1 Sep 2017
- Promised completion
- 31 Jul 2018
- Revised completion
- 31 Jul 2018
- Sanctioned habitable floors
- 11
- Building
- VAKRATUND
- Sanctioned floors (incl. basement, stilt, podium)
- 11
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-THN-46D6-VAKRAT
Questions about Main building
When is Main building due for completion?
The MahaRERA registration promises 31 Jul 2018.
How many floors does Main building have?
11 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology