Promised date passed8 floorsRERA P51700005889

Main building, Shree Sadan

Deedo IDDP-THN-7DJW-SS

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

All of Shree Sadan
Median saleNot on recordneeds 3 or more sales
Booked17%1 of 6 · MahaRERA
Completion31 Jan 2020as registered
Units & parking in Main building
TypeCarpet areaUnitsBooked
2BHK GR Floor62.1 m² (668 sq.ft)10
5 BHK197.2 m² (2,122 sq.ft)31
5 BHK Duplex201.3 m² (2,167 sq.ft)10
5th Floor Duplex36 m² (388 sq.ft)10
As registered with MahaRERA
RERA registration
P51700005889 · registered 14 Aug 2017
Promised completion
31 Jan 2020
Revised completion
31 Jan 2020
Sanctioned habitable floors
8
Building
Shree Sadan
Sanctioned floors (incl. basement, stilt, podium)
8
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
DP-THN-7DJW-SS
Questions about Main building

When is Main building due for completion?

The MahaRERA registration promises 31 Jan 2020.

How many floors does Main building have?

8 sanctioned habitable floors, as registered with MahaRERA.

Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology