Main building, Shantai
Deedo IDDP-THN-49C7-SHANTA13 flats have a sale on record, 0 are booked without a sale deed yet and 3 are unsold.
Every flat, floor by floor
Tap a flat to see its record.
- Sale registered
- Unsold
- Reserved, rehab or other
Other units on these floors (no stack in the number):
Flat number not read (14): no floor on record and the number doesn't say one.
Sale status from MahaRERA's disclosure; deeds from IGR Index II, placed on a flat only when the deed names this tower and flat. “Listed by developer” comes from the developer and is labelled as such.
Flat 3201
365 sq ft · floor 1
- Deeds
- 0
- Last activity
- None on record
- Last sale
- None registered
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| RESIDENTIAL | 578.8 m² (6,231 sq.ft) | 35 | Not on record |
| SHOP | 126.1 m² (1,358 sq.ft) | 9 | Not on record |
Parking: Closed/Covered 2 · Open Space 0 (as declared to MahaRERA)
Construction progress (declared)
Work completed, as the promoter reported it to MahaRERA (Form 1). Not verified on site.
- Excavation100%
- Basement (if any)100%
- Podiums (if any)0%
- Plinth100%
- Stilt Floor100%
- Slabs of Super Structure100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
- Sanitary Fittings within the flats / premises100%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
As registered with MahaRERA
- RERA registration
- P51700008654 · registered 19 Aug 2017
- Promised completion
- 31 Dec 2019
- Revised completion
- 30 Dec 2021
- Sanctioned habitable floors
- 2
- Also named
- Shantai
- Deedo ID
- DP-THN-49C7-SHANTA
Questions about Main building
How many flats in Main building are sold?
13 flats have a sale on record, 0 are booked without a sale deed yet and 3 are unsold.
When is Main building due for completion?
The MahaRERA registration promises 31 Dec 2019, revised to 30 Dec 2021.
How many floors does Main building have?
2 sanctioned habitable floors, as registered with MahaRERA.