Sector 5 - Wing A

Deedo IDDP-THN-VK7D

Completion was pushed back 3 years, to Dec 2030; no MahaRERA orders on record; 9% of its units are booked.

Thane (M Corp.), Thane 400607 · by Agile Real Estate Pvt. Ltd · 100% of its projects kept the RERA date

DeliveryExtended 3 yrsPromised Dec 2027 · now due Dec 2030RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales9% booked28 of 319 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 3 years, to Dec 2030

  • This projectRegistered 29 Mar 2019, completion promised 30 Dec 2027, revised to 30 Dec 2030.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700020201
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170002020129 Mar 201930 Dec 202730 Dec 2030Agile Real Estate Pvt. Ltd.Project page
Documents190

2 documents held by Deedo, 188 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardAgile Real Estate Pvt Ltd.pdf · uploaded 6 Jun 2024Source

Legal

  • OtherWing A.pdf · uploaded 27 Mar 2019Source
  • Legal Title reportTC Final.pdf · uploaded 27 Mar 2019Source
  • Legal Title reportTC 1.pdf · uploaded 27 Mar 2019Source
  • Declaration Form BWing A.pdf · uploaded 27 Mar 2019Source
  • Legal Title reportAddendum-2019.pdf · uploaded 6 Apr 2019Source
Show all 190 documentsShow fewer documents

Legal

  • Declaration Form BSector 5 Wing A.pdf · uploaded 22 May 2024Source

Migrated

  • 1 Copy of the legal title reportTC Final.pdf · uploaded 27 Mar 2019Source
  • 2 Copy of the legal title reportTC 1.pdf · uploaded 27 Mar 2019Source
  • 1 Details of encumbrancesEncumbrance Certificate.pdf · uploaded 27 Mar 2019Source
  • 2 Details of encumbrancesWing A.pdf · uploaded 27 Mar 2019Source
  • 1 Copy of Layout Approval (in case of layout)Layout-1.pdf · uploaded 27 Mar 2019Source
  • 1 Building Plan Approval (IOD)IOD.pdf · uploaded 27 Mar 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 27 Mar 2019Source
  • 1 Declaration in FORM BWing A.pdf · uploaded 27 Mar 2019Source
  • 1 Certificates of CA (Form 3)Wing A.pdf · uploaded 27 Mar 2019Source
  • 1 Proforma of Allotment letterWing A.pdf · uploaded 27 Mar 2019Source
  • 1 OtherWing A.pdf · uploaded 27 Mar 2019Source
  • 3 Copy of the legal title reportAddendum-2019.pdf · uploaded 6 Apr 2019Source
  • 3 Details of encumbrancesEncumbrance Certificate.pdf · uploaded 6 Apr 2019Source
  • 1 Form 2ASector 5 Wing A.pdf · uploaded 29 Jun 2019Source
  • 2 Form 2ASector 5 Wing A.pdf · uploaded 6 Aug 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5)Sector 5 A.pdf · uploaded 30 Sep 2019Source
  • 3 Form 2ASector 5 Wing A.pdf · uploaded 16 Oct 2019Source
  • 4 Form 2ASector 5 Wing A.pdf · uploaded 16 Jan 2020Source
  • 5 Form 2ASector 5 Wing A-March 2020.pdf · uploaded 14 Sep 2020Source
  • 6 Form 2ASector 5 Wing A-June 2020.pdf · uploaded 14 Sep 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Expansia A.pdf · uploaded 9 Oct 2020Source
  • 7 Form 2ASector 5 Wing A-Sept2020.pdf · uploaded 29 Oct 2020Source
  • 8 Form 2ASector 5 Wing A-Dec2020 signed.pdf · uploaded 10 Feb 2021Source
  • 9 Form 2ASector 5 Wing A-March21.pdf · uploaded 7 May 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Wing A.pdf · uploaded 20 Jul 2021Source
  • 1 Declaration about Commencement Certificatesector 5- a.pdf · uploaded 4 Oct 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Tower A Sector 5.pdf · uploaded 5 Oct 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Sector 5 Wing A .pdf · uploaded 7 Oct 2021Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Sector 5 A.pdf · uploaded 21 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Expansia Tower A_Agile.pdf · uploaded 30 Sep 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)1 Annual Audit Report of Statutory CA (Form 5) (2).pdf · uploaded 20 Jan 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 Wing A.pdf · uploaded 23 Feb 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 Wing A.pdf · uploaded 23 Feb 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Sector 5 A.pdf · uploaded 23 Jun 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Sector 5 A.pdf · uploaded 23 Jun 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 Wing A.pdf · uploaded 25 Jul 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 Wing A.pdf · uploaded 25 Jul 2023Source
  • 2 Certificates of CA (Form 3)Sector 5 Wing A.pdf · uploaded 25 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Expansia A.pdf · uploaded 30 Sep 2023Source
  • 3 Certificates of CA (Form 3)Sector 5 Wing A.pdf · uploaded 20 Oct 2023Source
  • 4 Certificates of CA (Form 3)Sector 5 Wing A.pdf · uploaded 19 Jan 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 wing A.pdf · uploaded 20 Jan 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 Wing A.pdf · uploaded 20 Jan 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5-Wing A.pdf · uploaded 20 Apr 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 - Wing A Sign.pdf · uploaded 20 Apr 2024Source
  • 5 Certificates of CA (Form 3)CA Certificate Srishti Sector 2A Wing A.pdf · uploaded 20 Apr 2024Source
  • 6 Certificates of CA (Form 3)Sector 5 Wing A.pdf · uploaded 20 Apr 2024Source
  • 2 Declaration in FORM BSector 5 Wing A.pdf · uploaded 22 May 2024Source
  • 1 PAN CardAgile Real Estate Pvt Ltd.pdf · uploaded 6 Jun 2024Source
  • 2 Copy of Layout Approval (in case of layout)1_UPLOAD.pdf · uploaded 6 Jun 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentBayer Amended Permission_C C dated.pdf · uploaded 6 Jun 2024Source
  • 2 Declaration about Commencement CertificateSector 5 wing A 1.pdf · uploaded 6 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Sector 5 Wing A.pdf · uploaded 6 Jun 2024Source
  • 1 Disclosure of sold/ booked inventorySector 5 Wing A Sold Unsold.pdf · uploaded 6 Jun 2024Source
  • 1 CERSAI detailsCERSAI_Search_Report_Asset_Id_Based_Search_23_03_2024_15_25_24_652.pdf · uploaded 6 Jun 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsSumti.pdf · uploaded 6 Jun 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsIIK.pdf · uploaded 6 Jun 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Declaration.pdf · uploaded 6 Jun 2024Source
  • 3 Copy of Layout Approval (in case of layout)1_UPLOAD.pdf · uploaded 12 Jun 2024Source
  • 2 Building Plan Approval (IOD)62_UPLOAD.pdf · uploaded 12 Jun 2024Source
  • 3 Building Plan Approval (IOD)63_UPLOAD.pdf · uploaded 12 Jun 2024Source
  • 4 Building Plan Approval (IOD)64_UPLOAD.pdf · uploaded 12 Jun 2024Source
  • 5 Building Plan Approval (IOD)65_UPLOAD.pdf · uploaded 12 Jun 2024Source
  • 6 Building Plan Approval (IOD)66_UPLOAD.pdf · uploaded 12 Jun 2024Source
  • 7 Building Plan Approval (IOD)63_UPLOAD.pdf · uploaded 20 Jun 2024Source
  • 1 Other – TechnicalCommencement of work Architect application for Ph 3 wing A B C G H J and K.pdf · uploaded 20 Jun 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5-Wing A.pdf · uploaded 20 Jul 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)wing A.pdf · uploaded 20 Jul 2024Source
  • 7 Certificates of CA (Form 3)Expansia A.pdf · uploaded 20 Jul 2024Source
  • 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 A.pdf · uploaded 20 Oct 2024Source
  • 17 Certificates of CA (Form 3)Sector 5 Tower A.pdf · uploaded 20 Oct 2024Source
  • 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 A.pdf · uploaded 20 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Sector 5 A.pdf · uploaded 21 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 A.pdf · uploaded 20 Jan 2025Source
  • 1 Certificates of CA (Form 3)Sector 5 Wing A.pdf · uploaded 20 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Wing A.pdf · uploaded 20 Jan 2025Source
  • 9 Certificates of CA (Form 3)CA Certificate - Expansia - Tower- A- RERA QE-jun21.pdf · uploaded 17 Feb 2025Source
  • 11 Certificates of CA (Form 3)CA certificate - Expansia-A RERA QE 31-12-2021.pdf · uploaded 17 Feb 2025Source
  • 10 Certificates of CA (Form 3)CA Certificate - Sep21 Tower A.pdf · uploaded 17 Feb 2025Source
  • 7 Certificates of CA (Form 3)CA Certificate - Sector 5 -Tower -A- Rera Qtr -Feb21.pdf · uploaded 17 Feb 2025Source
  • 6 Certificates of CA (Form 3)CA Certificate - Expansia -Tower A - 30-11-2020.pdf · uploaded 17 Feb 2025Source
  • 5 Certificates of CA (Form 3)Expansia A.pdf · uploaded 17 Feb 2025Source
  • 4 Certificates of CA (Form 3)CA Certificate Sector 5 J, K_Dec 19.pdf · uploaded 17 Feb 2025Source
  • 3 Certificates of CA (Form 3)CA Certificate_Sector 5-A.pdf · uploaded 17 Feb 2025Source
  • 2 Certificates of CA (Form 3)CA Certificate_Sector 5-A_June 2019.pdf · uploaded 17 Feb 2025Source
  • 8 Certificates of CA (Form 3)CA Certificate Expansia Tower A - 31May21.pdf · uploaded 17 Feb 2025Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 Wing A dec 21.pdf · uploaded 21 Feb 2025Source
  • 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 wing A.pdf · uploaded 21 Feb 2025Source
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 A.pdf · uploaded 21 Feb 2025Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector-5-Wing A sept21.pdf · uploaded 21 Feb 2025Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5-Wing A june21.pdf · uploaded 21 Feb 2025Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 Wing A may21.pdf · uploaded 21 Feb 2025Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sec 5 A nov2020.pdf · uploaded 21 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Wing A June19.pdf · uploaded 21 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 JK sept19.pdf · uploaded 21 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 A sept19.pdf · uploaded 21 Feb 2025Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)sector 5 -wing a dec19.pdf · uploaded 21 Feb 2025Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5-Wing A jan 2020.pdf · uploaded 21 Feb 2025Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)sector 5 wing A feb2020.pdf · uploaded 21 Feb 2025Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)SEctor 5 A feb21.pdf · uploaded 21 Feb 2025Source
  • 16 Certificates of CA (Form 3)Sector 5 Wing A.pdf · uploaded 21 Feb 2025Source
  • 15 Certificates of CA (Form 3)Sector 5 A Dec22.pdf · uploaded 21 Feb 2025Source
  • 14 Certificates of CA (Form 3)Tower A.pdf · uploaded 21 Feb 2025Source
  • 13 Certificates of CA (Form 3)Sector 5 Wing A June 22.pdf · uploaded 21 Feb 2025Source
  • 12 Certificates of CA (Form 3)Sector 5 Wing A March22.pdf · uploaded 21 Feb 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)A sept19.pdf · uploaded 21 Feb 2025Source
  • 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)A dec2021.pdf · uploaded 21 Feb 2025Source
  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)A Sept2021.pdf · uploaded 21 Feb 2025Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)A jun2021.pdf · uploaded 21 Feb 2025Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)A may2021.pdf · uploaded 21 Feb 2025Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)A Feb2021.pdf · uploaded 21 Feb 2025Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)A nov2020.pdf · uploaded 21 Feb 2025Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)A Jul2020.pdf · uploaded 21 Feb 2025Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)A Jan2020.pdf · uploaded 21 Feb 2025Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)A dec19.pdf · uploaded 21 Feb 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)A jun19.pdf · uploaded 21 Feb 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 A.pdf · uploaded 21 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 Wing A.pdf · uploaded 21 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 Wing A.pdf · uploaded 20 Apr 2025Source
  • 1 Certificates of CA (Form 3)EXPANSIA A.pdf · uploaded 20 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 Wing A EC.pdf · uploaded 20 Apr 2025Source
  • Form 1Sector 5 Wing A AC.pdf · uploaded 28 Apr 2026Source
  • Form 1Sector 5 Wing A AC.pdf · uploaded 28 Apr 2026Source
  • Form 2Sector 5 Wing A EC.pdf · uploaded 28 Apr 2026Source
  • Form 2Sector 5 Wing A EC.pdf · uploaded 28 Apr 2026Source
  • Form 3RERA certificate eternia tower A_260330_183743.pdf · uploaded 28 Apr 2026Source
  • Form 3Sector 5 Wing A CA.pdf · uploaded 28 Apr 2026Source
  • Disclosure of Sold and Booked InventorySector 5 A.pdf · uploaded 28 Apr 2026Source
  • Disclosure of Sold and Booked InventorySector 5 A.pdf · uploaded 28 Apr 2026Source
  • Form 2A (FY 2025-2026)Form 2A Sector 5 Wing A.pdf · uploaded 22 Jun 2026Source
  • Form 1Sector 5 A AC.pdf · uploaded 21 Jul 2026Source
  • Form 2Sector 5 A EC.pdf · uploaded 21 Jul 2026Source
  • Form 3Sector 5 Wing A.pdf · uploaded 21 Jul 2026Source
  • Disclosure of Sold and Booked InventorySector 5 Wing A.pdf · uploaded 21 Jul 2026Source
  • Form 5 (FY 2025-2026)Sector 5 A tower.pdf · uploaded 16 Sep 2026Source

Technical

  • DocumentLayout-1.pdf · uploaded 27 Mar 2019Source
  • DocumentIOD.pdf · uploaded 27 Mar 2019Source
  • Document1_UPLOAD.pdf · uploaded 6 Jun 2024Source
  • Document1_UPLOAD.pdf · uploaded 12 Jun 2024Source
  • Document62_UPLOAD.pdf · uploaded 12 Jun 2024Source
  • Document63_UPLOAD.pdf · uploaded 12 Jun 2024Source
  • Document64_UPLOAD.pdf · uploaded 12 Jun 2024Source
  • Document65_UPLOAD.pdf · uploaded 12 Jun 2024Source
  • Document66_UPLOAD.pdf · uploaded 12 Jun 2024Source
  • Document63_UPLOAD.pdf · uploaded 20 Jun 2024Source
  • Other – TechnicalCommencement of work Architect application for Ph 3 wing A B C G H J and K.pdf · uploaded 20 Jun 2024Source

Technical (Architect)

  • DocumentSector 5-Wing A.pdf · uploaded 30 Sep 2024Source
  • DocumentSector 5 A.pdf · uploaded 20 Oct 2024Source
  • DocumentSector 5 A.pdf · uploaded 20 Jan 2025Source
  • DocumentWing A June19.pdf · uploaded 21 Feb 2025Source
  • DocumentSector 5 JK sept19.pdf · uploaded 21 Feb 2025Source
  • DocumentSector 5 A sept19.pdf · uploaded 21 Feb 2025Source
  • Documentsector 5 -wing a dec19.pdf · uploaded 21 Feb 2025Source
  • DocumentSector 5-Wing A jan 2020.pdf · uploaded 21 Feb 2025Source
  • Documentsector 5 wing A feb2020.pdf · uploaded 21 Feb 2025Source
  • DocumentSec 5 A nov2020.pdf · uploaded 21 Feb 2025Source
  • DocumentSEctor 5 A feb21.pdf · uploaded 21 Feb 2025Source
  • DocumentSector 5 Wing A may21.pdf · uploaded 21 Feb 2025Source
  • DocumentSector 5-Wing A june21.pdf · uploaded 21 Feb 2025Source
  • DocumentSector-5-Wing A sept21.pdf · uploaded 21 Feb 2025Source
  • DocumentSector 5 Wing A dec 21.pdf · uploaded 21 Feb 2025Source
  • DocumentSector 5 A.pdf · uploaded 21 Feb 2025Source
  • DocumentSector 5 wing A.pdf · uploaded 21 Feb 2025Source
  • DocumentSector 5 Wing A.pdf · uploaded 20 Apr 2025Source

Technical (Engineer)

  • Documentwing A.pdf · uploaded 3 Oct 2024Source
  • DocumentSector 5 A.pdf · uploaded 20 Oct 2024Source
  • DocumentWing A.pdf · uploaded 20 Jan 2025Source
  • DocumentSector 5 Wing A.pdf · uploaded 21 Feb 2025Source
  • DocumentSector 5 A.pdf · uploaded 21 Feb 2025Source
  • DocumentA jun19.pdf · uploaded 21 Feb 2025Source
  • DocumentA sept19.pdf · uploaded 21 Feb 2025Source
  • DocumentA dec19.pdf · uploaded 21 Feb 2025Source
  • DocumentA Jan2020.pdf · uploaded 21 Feb 2025Source
  • DocumentA Jul2020.pdf · uploaded 21 Feb 2025Source
  • DocumentA nov2020.pdf · uploaded 21 Feb 2025Source
  • DocumentA Feb2021.pdf · uploaded 21 Feb 2025Source
  • DocumentA may2021.pdf · uploaded 21 Feb 2025Source
  • DocumentA jun2021.pdf · uploaded 21 Feb 2025Source
  • DocumentA Sept2021.pdf · uploaded 21 Feb 2025Source
  • DocumentA dec2021.pdf · uploaded 21 Feb 2025Source
  • DocumentSector 5 Wing A EC.pdf · uploaded 20 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 83/2A Part, 83/2B/1 Part

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK319 units in all
Address
New S No.79/9 Part, 83/2A Part, 83/2B/1 Part, 83/5 Part of Village Balkum, Kolshet Road, Village Balkum, ThanePIN 400607
Village
Thane (M Corp.), Thane taluka
Land area for this project
1,210 sq m (13,029 sq ft)
Permissible built-up area
21,102 sq m (2,27,138 sq ft)
Sanctioned built-up area
20,688 sq m (2,22,687 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

83/2A Part83/2B/1 Part83/5 Part ofNew S No.79/9 Part

Land as published on MahaRERA's project page

New S No.79/9 Part, 83/2A Part, 83/2B/1 Part, 83/5 Part of Village Balkum

Boundaries

North
New SNo 79-9 Pt 83-2A Pt 83-5 Pt of Village Balkum
South
New S No 83-2B-1 Part 83-5 part of village Balkum
East
New S No 83-5 Part of Village Balkum
West
New S No 83-2A Part 83-2B-1 Part of Village Balkum

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking319 units

28 of 319 units booked (9%), as the promoter reported to MahaRERA

2BHK · 179 units3BHK · 140 units
TypeCarpet areaUnitsBooked
2BHK11,618.47 sq m · 1,25,060 sq ft1797
3BHK15,650.53 sq m · 1,68,461 sq ft14021

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
EngineerZankar Borse—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology