Sector 5 - Wing A · Thane (M Corp.), Thane · Agile Real Estate Pvt. Ltd
Promised for 30 Dec 2027, extended once to 30 Dec 2030, which is still ahead.
The revised date is 3 years after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Dec 2027 to 30 Dec 2030 (1 extension certificate on record).
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51700020201
Is Sector 5 - Wing A delayed?
Its completion moved from 30 Dec 2027 to 30 Dec 2030; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 1 extension certificate for P51700020201. The completion date moved from 30 Dec 2027 to 30 Dec 2030.
Who is the promoter?
MahaRERA records Agile Real Estate Pvt. Ltd as the promoter of P51700020201.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51700020201.