Skip to content
Others · 4 buildings · 78 unitsRERA P51700031214 +1

Riviera

Deedo IDDP-THN-A3P1

Its promised completion date, Sep 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 69% of its units are booked.

Thane (M Corp.), Thane 400605 · by Shreeram Builders

Delivery1 yr 2 mo past duePromised Sep 2025 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales69% booked54 of 78 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Sep 2025, has passed and MahaRERA does not show it completed

  • P51700031214Registered 11 Oct 2021, completion promised 30 Sep 2024.
  • P51700046447Registered 28 Jul 2022, completion promised 30 Sep 2025, and still not shown completed today.

No extension certificate on record.

2 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

4 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations2
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170003121411 Oct 202130 Sep 202430 Sep 2024Shreeram BuildersProject page
P5170004644728 Jul 202230 Sep 202530 Sep 2025Shreeram BuildersProject page
Documents180

3 documents held by Deedo, 177 filings listed on MahaRERA's project page

Registration certificate (2)

  • Registration certificateP51700031214 · 11 Oct 2021ViewSource
  • Registration certificateP51700046447 · 7 Nov 2023ViewSource

Other

  • OtherP51700046447 · Date not statedView

Finance

  • PAN CardP51700031214 · SRB PAN .pdf · uploaded 13 Sep 2021Source
  • PAN CardP51700046447 · Pancard Shreeram.pdf · uploaded 1 Jul 2022Source

Legal

  • Declaration Form BP51700031214 · Form B.pdf · uploaded 13 Sep 2021Source
  • Legal Title reportP51700031214 · Title_MahaRERA_Shreeram_Builders_Riveria_Scanned.pdf · uploaded 4 Oct 2021Source
  • Declaration Form BP51700031214 · affidavit rera rivera.pdf · uploaded 20 Oct 2021Source
Show all 180 documentsShow fewer documents

Legal

  • Legal Title reportP51700046447 · download1.pdf · uploaded 1 Jul 2022Source
  • Declaration Form BP51700046447 · Form B Riveria.pdf · uploaded 1 Jul 2022Source

Migrated

  • 1 PAN CardP51700031214 · SRB PAN .pdf · uploaded 13 Sep 2021Source
  • 1 Details of encumbrancesP51700031214 · Encumberance Letter.pdf · uploaded 13 Sep 2021Source
  • 1 Copy of Layout Approval (in case of layout)P51700031214 · CC Plan Riviera -1.pdf · uploaded 13 Sep 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentP51700031214 · CC Plan Riviera _compressed-2-3.pdf · uploaded 13 Sep 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentP51700031214 · CC RIVIERA.pdf · uploaded 13 Sep 2021Source
  • 1 Declaration about Commencement CertificateP51700031214 · Circular 32.pdf · uploaded 13 Sep 2021Source
  • 1 Declaration in FORM BP51700031214 · Form B.pdf · uploaded 13 Sep 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700031214 · Form 3 Riviera Building No 1 - Signed.pdf · uploaded 15 Sep 2021Source
  • 1 Proforma of Allotment letterP51700031214 · Agreement For Sale_Riviera_Shree Ram Builder.pdf · uploaded 17 Sep 2021Source
  • 2 Proforma of Allotment letterP51700031214 · Allotment Letter.pdf · uploaded 17 Sep 2021Source
  • 1 Copy of the legal title reportP51700031214 · Title_MahaRERA_Shreeram_Builders_Riveria_Scanned.pdf · uploaded 4 Oct 2021Source
  • 2 Details of encumbrancesP51700031214 · encumbrance riviera.pdf · uploaded 20 Oct 2021Source
  • 2 Declaration in FORM BP51700031214 · affidavit rera rivera.pdf · uploaded 20 Oct 2021Source
  • 1 PAN CardP51700046447 · Pancard Shreeram.pdf · uploaded 1 Jul 2022Source
  • 1 Copy of the legal title reportP51700046447 · download1.pdf · uploaded 1 Jul 2022Source
  • 1 b Details of encumbrances concerned to LegalP51700046447 · Encumbrance -Litigations.pdf · uploaded 1 Jul 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentP51700046447 · CC RIVIERA.pdf · uploaded 1 Jul 2022Source
  • 1 Declaration about Commencement CertificateP51700046447 · CC Declaration Riveria.pdf · uploaded 1 Jul 2022Source
  • 1 Declaration in FORM BP51700046447 · Form B Riveria.pdf · uploaded 1 Jul 2022Source
  • 1 CERSAI detailsP51700046447 · CERSAI_Search_Report_200241230904_For_Asset_Based_Search_01_07_2022_17_34_02_728.pdf · uploaded 1 Jul 2022Source
  • 1 Deviation Report with respect to Allotment letterP51700046447 · Deviation -Allotment.pdf · uploaded 1 Jul 2022Source
  • 1 Deviation Report with respect to model copy of AgreementP51700046447 · Deviation Report -Agreement.pdf · uploaded 1 Jul 2022Source
  • 1 Copy of Layout Approval (in case of layout)P51700046447 · Plan Copy of Riviera Bldg 2 Page 1.pdf · uploaded 6 Jul 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentP51700046447 · Plan Copy of Riviera Bldg 2 Page 2 -4.pdf · uploaded 6 Jul 2022Source
  • 1 Proforma of Allotment letterP51700046447 · Model Agreement for Sale _ Riviera Building No 2.pdf · uploaded 6 Jul 2022Source
  • 2 Proforma of Allotment letterP51700046447 · New Allotment Letter.pdf · uploaded 6 Jul 2022Source
  • 1 a Details of encumbrances concerned to FinanceP51700046447 · Encumbrance Dues -Bldg 2 Shreeram.pdf · uploaded 16 Jul 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046447 · download (12)-1-8_merged.pdf · uploaded 16 Jul 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP51700046447 · Deviation Bank AC -Bldg 2 Shreeram.pdf · uploaded 16 Jul 2022Source
  • 2 a Details of encumbrances concerned to FinanceP51700046447 · Riviera Bldg no 2 -No Encumbrance dues.pdf · uploaded 12 Oct 2022Source
  • 1 CERSAI detailsP51700031214 · Riviera- Building No 1.pdf · uploaded 24 Dec 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700031214 · Form 1- Riviera Building 1.pdf · uploaded 6 Apr 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046447 · Form 1- Riviera Building No 2.pdf · uploaded 6 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P51700031214 · riviera bldg 1 21-22.pdf · uploaded 21 Apr 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700031214 · Riviera - Form 3 CA Dec 21 Bldg 1.pdf · uploaded 28 Apr 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700031214 · Riviera - Form 3 CA Mar 22 Bldg 1.pdf · uploaded 28 Apr 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700031214 · Riviera - Form 3 CA Jun 22 Bldg 1.pdf · uploaded 28 Apr 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700031214 · Riviera - Form 3 CA Sep 22 Bldg 1.pdf · uploaded 28 Apr 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700031214 · Riviera - Form 3 CA Dec 22 Bldg 1.pdf · uploaded 28 Apr 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700031214 · form 1 31-03-2022.pdf · uploaded 29 Apr 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700031214 · form 1 30-06-2022.pdf · uploaded 29 Apr 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700031214 · form 1 29-09-2022.pdf · uploaded 29 Apr 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700031214 · form 1 31-03-2023.pdf · uploaded 29 Apr 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700031214 · form 2 15-01-2022.pdf · uploaded 29 Apr 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700031214 · form 2 04-04-2022.pdf · uploaded 29 Apr 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700031214 · form 2 12-07-2022.pdf · uploaded 29 Apr 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700031214 · form 2 13-10-2022.pdf · uploaded 29 Apr 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700031214 · form 2 09-01-2023.pdf · uploaded 29 Apr 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700031214 · form 2 15-04-2023.pdf · uploaded 29 Apr 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046447 · form 1 30-09-2022.pdf · uploaded 29 Apr 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046447 · form 1 31-03-2023.pdf · uploaded 29 Apr 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046447 · form 2 13-10-2022.pdf · uploaded 29 Apr 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046447 · form 2 09-01-2023.pdf · uploaded 29 Apr 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046447 · form 2 13-04-2023.pdf · uploaded 29 Apr 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046447 · SEPT 22 FORM 3.pdf · uploaded 29 Apr 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046447 · DEC 22 FORM 3.pdf · uploaded 29 Apr 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP51700031214 · FORMAT A.pdf · uploaded 10 Aug 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700031214 · Riveria Building 1 March 23.pdf · uploaded 31 Aug 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700031214 · Riveria June 23 Building 1.pdf · uploaded 31 Aug 2023Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP51700031214 · S08_0088_18 OC.pdf · uploaded 31 Aug 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046447 · Riveria Building 2 March 23.pdf · uploaded 31 Aug 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046447 · Riveria June 23 Building 2.pdf · uploaded 31 Aug 2023Source
  • 3 a Details of encumbrances concerned to FinanceP51700031214 · TO WHOMSOEVER IT MAY CONCERN OF RIVIERA Bldg No 1 07-08-2023.pdf · uploaded 2 Sep 2023Source
  • 1 b Details of encumbrances concerned to LegalP51700031214 · TO WHOMSOEVER IT MAY CONCERN OF RIVIERA Bldg No 1 07-08-2023.pdf · uploaded 2 Sep 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700031214 · Form 2 of Riviera Bldg No 1 18-07-2023.pdf · uploaded 2 Sep 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP51700031214 · ANNEXURE A OF SHREE RAM BUILDERS 09-08-2023.pdf · uploaded 2 Sep 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsP51700031214 · ANNEXURE A OF RAMESH AMRUTLAL MEHTA MEHTA 09-08-2023.pdf · uploaded 2 Sep 2023Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsP51700031214 · ANNEXURE A OF DEEPAK REAMESH MEHTA 09-08-2023.pdf · uploaded 2 Sep 2023Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsP51700031214 · ANNEXURE A OF ALPA KETAN MEHTA 09-08-2023.pdf · uploaded 2 Sep 2023Source
  • 5 Disclosure of Interest in Other Real Estate OrganizationsP51700031214 · ANNEXURE A OF RUCHIT KETAN MEHTA 09-08-2023.pdf · uploaded 2 Sep 2023Source
  • 6 Disclosure of Interest in Other Real Estate OrganizationsP51700031214 · ANNEXURE A OF JAY DEEPAK MEHTA 09-08-2023.pdf · uploaded 2 Sep 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046447 · Form 2 of Riviera Bldg No 2 18-07-2023.pdf · uploaded 2 Sep 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP51700046447 · ANNEXURE A OF SHREE RAM BUILDERS 09-08-2023.pdf · uploaded 2 Sep 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsP51700046447 · ANNEXURE A OF RAMESH AMRUTLAL MEHTA MEHTA 09-08-2023.pdf · uploaded 2 Sep 2023Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsP51700046447 · ANNEXURE A OF DEEPAK RAMESH MEHTA 09-08-2023.pdf · uploaded 2 Sep 2023Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsP51700046447 · ANNEXURE A OF ALPA KETAN MEHTA 09-08-2023.pdf · uploaded 2 Sep 2023Source
  • 5 Disclosure of Interest in Other Real Estate OrganizationsP51700046447 · ANNEXURE A OF RUCHIT KETAN MEHTA 09-08-2023.pdf · uploaded 2 Sep 2023Source
  • 6 Disclosure of Interest in Other Real Estate OrganizationsP51700046447 · ANNEXURE A OF JAY DEEPAK MEHTA 09-08-2023.pdf · uploaded 2 Sep 2023Source
  • 4 a Details of encumbrances concerned to FinanceP51700031214 · TO WHOMSOEVER IT MAY CONSERN OF RIVIERA Bldg No 1 07-08-2023 (DUES).pdf · uploaded 8 Sep 2023Source
  • 2 b Details of encumbrances concerned to LegalP51700031214 · TO WHOMSOEVER IT MAY CONSERN OF RIVIERA Bldg No 1 07-08-2023 (DUES).pdf · uploaded 8 Sep 2023Source
  • 1 Proforma of Agreement for saleP51700031214 · 1 Proforma of Allotment letter.pdf · uploaded 8 Sep 2023Source
  • 1 Proforma of Agreement for saleP51700046447 · 1 Proforma of Allotment letter.pdf · uploaded 8 Sep 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046447 · FORM 1 RIVIERA Bldg No 2 DTD 30-06-2023.pdf · uploaded 4 Oct 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046447 · Riviera Bldg no-2 Form 1.pdf · uploaded 20 Oct 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046447 · Form 2 Riviera Bldg no 2.pdf · uploaded 20 Oct 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046447 · Riviera Building No 2 Form 3 Certificate.pdf · uploaded 20 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P51700031214 · Form 5 R-1.pdf · uploaded 21 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P51700046447 · Form 5 R-2.pdf · uploaded 21 Oct 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046447 · RIVIERA Bldg no 2 FORM 1 DEC.pdf · uploaded 19 Feb 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046447 · FORM 2 Riviera Bldg No 2.pdf · uploaded 19 Feb 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046447 · Form 3 of Riviera Bldg 2 19-01-2024.pdf · uploaded 19 Feb 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)P51700031214 · Form 4 of Riviera Bldg No 1 04-09-2023.pdf · uploaded 5 Mar 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046447 · Form 1 of Riviera Bldg No 2 30-03-2024.pdf · uploaded 27 Apr 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046447 · Riveria Bldg No 2 FORM 3.pdf · uploaded 9 May 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046447 · Riviera Building No 2 Form 2.pdf · uploaded 25 May 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046447 · Form 1 of Riviera Bldg No 2 05-07-2024.pdf · uploaded 8 Jul 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046447 · Form 3 of Riviera Bldg No 2 31-08-2024.pdf · uploaded 23 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046447 · FORM 2 Riviera 2 June 24.pdf · uploaded 23 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046447 · Form 1 of Riviera Bldg No 2 30-09-2024.pdf · uploaded 23 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046447 · Form 1 of Riviera Bldg No 2 30-09-2024.pdf · uploaded 25 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700046447 · Riviera 2 Form 5.pdf · uploaded 25 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700031214 · FORM 5 Shree Ram Builders Riviera Bldg 1.pdf · uploaded 27 Nov 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046447 · Riviera Bldg No 2 FORM 2 Sept 24.pdf · uploaded 28 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046447 · Riveria Building No 2 Form 3 Sept 24.pdf · uploaded 5 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046447 · Form 1 of Riviera Bldg No 2 30-12-2024.pdf · uploaded 31 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046447 · Engineer Certificates R 2 Dec 24.pdf · uploaded 31 May 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046447 · Engineer Certificates R 2 March 25.pdf · uploaded 31 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046447 · Riveria bldg 2 rera certificate.pdf · uploaded 5 Jun 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046447 · Riveria Dec 2024.pdf · uploaded 9 Jun 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046447 · Riveria March 2025.pdf · uploaded 9 Jun 2025Source
  • Form 1P51700046447 · form 1 30-09-2022.pdf · uploaded 19 Jun 2025Source
  • Form 2P51700046447 · Sept 22.pdf · uploaded 19 Jun 2025Source
  • Form 3P51700046447 · SEPT 22 FORM 3.pdf · uploaded 19 Jun 2025Source
  • Disclosure of Sold and Booked InventoryP51700046447 · Riviera Booked Inventory.pdf · uploaded 19 Jun 2025View
  • Form 1P51700046447 · form 1 22-11-2022.pdf · uploaded 19 Jun 2025Source
  • Form 2P51700046447 · Dec 22.pdf · uploaded 19 Jun 2025Source
  • Form 3P51700046447 · DEC 22 FORM 3.pdf · uploaded 19 Jun 2025Source
  • Disclosure of Sold and Booked InventoryP51700046447 · Riviera Booked Inventory.pdf · uploaded 19 Jun 2025View
  • Form 1P51700046447 · form 1 31-03-2023.pdf · uploaded 19 Jun 2025Source
  • Form 2P51700046447 · March 23.pdf · uploaded 19 Jun 2025Source
  • Form 3P51700046447 · Riveria Building 2 March 23.pdf · uploaded 19 Jun 2025Source
  • Disclosure of Sold and Booked InventoryP51700046447 · Riviera Booked Inventory.pdf · uploaded 19 Jun 2025View
  • Form 1P51700046447 · FORM 1 RIVIERA Bldg No 2 DTD 30-06-2023.pdf · uploaded 19 Jun 2025Source
  • Form 2P51700046447 · June 23.pdf · uploaded 19 Jun 2025Source
  • Form 3P51700046447 · Riveria June 23 Building 2.pdf · uploaded 19 Jun 2025Source
  • Disclosure of Sold and Booked InventoryP51700046447 · Riviera Booked Inventory.pdf · uploaded 19 Jun 2025View
  • Form 1P51700046447 · sept 23.pdf · uploaded 19 Jun 2025Source
  • Form 2P51700046447 · Sept 23.pdf · uploaded 19 Jun 2025Source
  • Form 3P51700046447 · Sept 23.pdf · uploaded 19 Jun 2025Source
  • Disclosure of Sold and Booked InventoryP51700046447 · Riviera Booked Inventory.pdf · uploaded 19 Jun 2025View
  • Form 1P51700046447 · RIVIERA Bldg no 2 FORM 1 DEC 23.pdf · uploaded 19 Jun 2025Source
  • Form 2P51700046447 · Dec 23.pdf · uploaded 19 Jun 2025Source
  • Form 3P51700046447 · Dec 23.pdf · uploaded 19 Jun 2025Source
  • Disclosure of Sold and Booked InventoryP51700046447 · Riviera Booked Inventory.pdf · uploaded 19 Jun 2025View
  • Form 1P51700046447 · Form 1 of Riviera Bldg No 2 30-03-2024.pdf · uploaded 19 Jun 2025Source
  • Form 2P51700046447 · Riviera Building No 2 Form 2 March 24.pdf · uploaded 19 Jun 2025Source
  • Form 3P51700046447 · Riveria Bldg No 2 FORM 3 March 24.pdf · uploaded 19 Jun 2025Source
  • Disclosure of Sold and Booked InventoryP51700046447 · Riviera Booked Inventory.pdf · uploaded 19 Jun 2025View
  • Form 1P51700046447 · Form 1 of Riviera Bldg No 2 30-06-2024.pdf · uploaded 19 Jun 2025Source
  • Form 2P51700046447 · FORM 2 Riviera 2 June 24.pdf · uploaded 19 Jun 2025Source
  • Form 3P51700046447 · Form 3 of Riviera Bldg No 2 31-08-2024.pdf · uploaded 19 Jun 2025Source
  • Disclosure of Sold and Booked InventoryP51700046447 · Riviera Booked Inventory.pdf · uploaded 19 Jun 2025View
  • Form 1P51700046447 · Form 1 of Riviera Bldg No 2 30-09-2024.pdf · uploaded 19 Jun 2025Source
  • Form 2P51700046447 · Riviera Bldg No 2 FORM 2 Sept 24.pdf · uploaded 19 Jun 2025Source
  • Form 3P51700046447 · Riveria Building No 2 Form 3 Sept 24.pdf · uploaded 19 Jun 2025Source
  • Disclosure of Sold and Booked InventoryP51700046447 · Riviera Booked Inventory.pdf · uploaded 19 Jun 2025View
  • Form 1P51700046447 · Dec 24.pdf · uploaded 19 Jun 2025Source
  • Form 2P51700046447 · Dec 24.pdf · uploaded 19 Jun 2025Source
  • Form 3P51700046447 · Dec 24.pdf · uploaded 19 Jun 2025Source
  • Disclosure of Sold and Booked InventoryP51700046447 · Riviera Booked Inventory.pdf · uploaded 19 Jun 2025View
  • Form 1P51700046447 · March 25.pdf · uploaded 19 Jun 2025Source
  • Form 2P51700046447 · March 25.pdf · uploaded 19 Jun 2025Source
  • Form 3P51700046447 · March 25.pdf · uploaded 19 Jun 2025Source
  • Disclosure of Sold and Booked InventoryP51700046447 · Riviera Booked Inventory.pdf · uploaded 19 Jun 2025View

Technical

  • DocumentP51700031214 · CC Plan Riviera -1.pdf · uploaded 13 Sep 2021Source
  • DocumentP51700031214 · CC Plan Riviera _compressed-2-3.pdf · uploaded 13 Sep 2021Source
  • DocumentP51700046447 · Plan Copy of Riviera Bldg 2 Page 1.pdf · uploaded 6 Jul 2022Source
  • DocumentP51700046447 · Plan Copy of Riviera Bldg 2 Page 2 -4.pdf · uploaded 6 Jul 2022Source

Technical (Architect)

  • DocumentP51700031214 · form 1 31-03-2023.pdf · uploaded 29 Apr 2023Source
  • DocumentP51700046447 · Form 1 of Riviera Bldg No 2 30-06-2024.pdf · uploaded 23 Sep 2024Source
  • DocumentP51700046447 · Form 1 of Riviera Bldg No 2 30-09-2024.pdf · uploaded 25 Nov 2024Source
  • DocumentP51700046447 · Form 1 of Riviera Bldg No 2 30-12-2024.pdf · uploaded 31 May 2025Source
  • DocumentP51700046447 · Riveria bldg 2 rera certificate.pdf · uploaded 5 Jun 2025Source

Technical (Engineer)

  • DocumentP51700031214 · Form 2 of Riviera Bldg No 1 18-07-2023.pdf · uploaded 2 Sep 2023Source
  • DocumentP51700046447 · Form 1 of Riviera Bldg No 2 30-06-2024.pdf · uploaded 23 Sep 2024Source
  • DocumentP51700046447 · FORM 2 Riviera 2 June 24.pdf · uploaded 23 Oct 2024Source
  • DocumentP51700046447 · Form 1 of Riviera Bldg No 2 30-09-2024.pdf · uploaded 23 Oct 2024Source
  • DocumentP51700046447 · Riviera Bldg No 2 FORM 2 Sept 24.pdf · uploaded 28 Nov 2024Source
  • DocumentP51700046447 · Engineer Certificates R 2 Dec 24.pdf · uploaded 31 May 2025Source
  • DocumentP51700046447 · Engineer Certificates R 2 March 25.pdf · uploaded 31 May 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel CTS No. 396, Gut No. 61/4

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Phases
2
Unit types
1BHK, 1RK, 2BHK, Office space, Shop78 units in all
Address
CTS No. 396, Gut No. 61/4, Parsik Road, KharegaonPIN 400605
Village
Thane (M Corp.), Thane taluka
Land area for this project
1,061 sq m (11,415 sq ft)
Permissible built-up area
2,837 sq m (30,535 sq ft)
Sanctioned built-up area
2,837 sq m (30,535 sq ft)
Designated bank account
220
Developed in phases
No
Also registered as
Riviera - Building No.1, Riviera - Building No.2

Survey, CTS, gat or plot numbers

CTS No. 396Gut No. 61/4

Land as published on MahaRERA's project page

CTS No. 396, Gut No. 61/4

Boundaries

North
Property of Mukund Keny
South
Hotel Amit Garden
East
45 Mtr D P Road
West
Property of Natha Patil

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking78 units

54 of 78 units booked (69%), as the promoter reported to MahaRERA

1BHK · 33 units1RK · 11 units2BHK · 10 unitsOffice space · 7 unitsShop · 17 units
RERABuildingTypeCarpet areaUnitsBooked
P51700031214Building No 11BHK40.32 sq m · 434 sq ft103
P51700031214Building No 11BHK41.16 sq m · 443 sq ft54
P51700031214Building No 11RK26.76 sq m · 288 sq ft11
P51700031214Building No 11RK32.14 sq m · 346 sq ft44
P51700031214Building No 12BHK58.53 sq m · 630 sq ft107
P51700031214Building No 1Office space132.39 sq m · 1,425 sq ft20
P51700031214Building No 1Office space162.86 sq m · 1,753 sq ft21
P51700031214Building No 1Shop11.52 sq m · 124 sq ft22
Show all 27 unit rowsShow fewer unit rows
RERABuildingTypeCarpet areaUnitsBooked
P51700031214Building No 1Shop15.24 sq m · 164 sq ft22
P51700031214Building No 1Shop30.66 sq m · 330 sq ft11
P51700031214Building No 1Shop33.17 sq m · 357 sq ft10
P51700031214Building No 1Shop35.67 sq m · 384 sq ft10
P51700031214Building No 1Shop37.16 sq m · 400 sq ft10
P51700031214Building No 1Shop40.51 sq m · 436 sq ft10
P51700046447Building No-21BHK41.53 sq m · 447 sq ft64
P51700046447Building No-21BHK44.59 sq m · 480 sq ft66
P51700046447Building No-21BHK45.62 sq m · 491 sq ft66
P51700046447Building No-21RK25.08 sq m · 270 sq ft65
P51700046447Building No-2Office space17.74 sq m · 191 sq ft10
P51700046447Building No-2Office space23.97 sq m · 258 sq ft10
P51700046447Building No-2Office space64.01 sq m · 689 sq ft10
P51700046447Building No-2Shop7.25 sq m · 78 sq ft11
P51700046447Building No-2Shop7.9 sq m · 85 sq ft11
P51700046447Building No-2Shop10.31 sq m · 111 sq ft22
P51700046447Building No-2Shop14.03 sq m · 151 sq ft11
P51700046447Building No-2Shop15.24 sq m · 164 sq ft11
P51700046447Building No-2Shop15.33 sq m · 165 sq ft22

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Other projects in Thane (M Corp.)

All 898 projects in Thane (M Corp.) · Compare Riviera with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology