Skip to content
Extended 4 mo8 floorsRERA P51700077446

Main building, Rajoba Solitaire

Deedo IDDP-THN-1WJQ-RS

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

Median saleNot on recordneeds 3 or more sales
Booked0%0 of 62 · MahaRERA
Completion30 Oct 202630 Jun 2026 · revised
Units & parking in Main building
TypeCarpet areaUnitsBooked
Anciliary 1 Rehab34.2 m² (368 sq.ft)10
Anciliary 2 Rehab40.9 m² (440 sq.ft)10
Multipurpose Room 129.9 m² (322 sq.ft)40
Multipurpose Room 225 m² (269 sq.ft)40
Multipurpose Room 324.2 m² (261 sq.ft)40
Multipurpose Room 427.3 m² (294 sq.ft)40
Multipurpose Room 527.4 m² (295 sq.ft)40
Multipurpose Room 623.8 m² (256 sq.ft)40
Multipurpose room 735.9 m² (387 sq.ft)40
Multipurpose Room 823.3 m² (251 sq.ft)30
Multipurp Rm 1 Owner29.9 m² (322 sq.ft)20
Multipurp Rm 2 Owner25 m² (269 sq.ft)20
Multipurp Rm 3 Owner24.2 m² (261 sq.ft)20
Multipurp Rm 4 Owner27.3 m² (294 sq.ft)20
Multipurp RM 5 Owner27.4 m² (295 sq.ft)20
Multipurp Rm 6 Owner23.8 m² (256 sq.ft)20
Multipurp Rm 7 Owner35.9 m² (387 sq.ft)20
Multipurp Rm 8 Owner23.3 m² (251 sq.ft)20
Multipurp Rm 8 Rehab23.3 m² (251 sq.ft)10
Office No. 1 Rehab33 m² (355 sq.ft)10
Office No. 2 Rehab32.8 m² (353 sq.ft)10
Office No. 3 Rehab21.9 m² (236 sq.ft)10
Office No.4 Rehab45.1 m² (486 sq.ft)10
Office No. 5 Rehab37.9 m² (408 sq.ft)10
OTLA 4 Rehab2.3 m² (25 sq.ft)10
Shop No. 1 Rehab37.4 m² (403 sq.ft)10
Shop No. 2 Rehab26.2 m² (282 sq.ft)10
Shop No. 3 Rehab26.7 m² (287 sq.ft)10
Shop No. 5 Rehab34.2 m² (368 sq.ft)10
Shop No. 6 Rehab28.4 m² (305 sq.ft)10
Shop No. 7 Rehab15.6 m² (168 sq.ft)10
As registered with MahaRERA
RERA registration
P51700077446 · registered 16 Aug 2024
Promised completion
30 Jun 2026
Revised completion
30 Oct 2026
Sanctioned habitable floors
8
Building
RAJOBA SOLITAIRE
Sanctioned floors (incl. basement, stilt, podium)
8
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
DP-THN-1WJQ-RS
Questions about Main building

When is Main building due for completion?

The MahaRERA registration promises 30 Jun 2026, revised to 30 Oct 2026.

How many floors does Main building have?

8 sanctioned habitable floors, as registered with MahaRERA.

Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology