Skip to content
Residential / Group Housing · 3 buildings · 58 unitsRERA P51700010184

Quality Heights I

Deedo IDDP-THN-MC6K

MahaRERA shows it completed, after its date was pushed back 1 year; no MahaRERA orders on record; 100% of its units are booked.

Thane (M Corp.), Thane 400612 · by Quality Construction Co

DeliveryCompletedAs MahaRERA shows · after a 1 yr extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked58 of 58 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 1 year

  • This projectRegistered 24 Aug 2017, completion promised 31 Dec 2018, revised to 31 Dec 2019.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700010184
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170001018424 Aug 201731 Dec 201831 Dec 2019Quality Construction CoProject page
Documents47

23 documents held by Deedo, 24 filings listed on MahaRERA's project page

Title report

Encumbrance details

Commencement certificate

Form B

Form 1

Form 2

Allotment letter (2)

Show all 47 documentsShow fewer documents

Registration certificate

Extension certificate

Form 5 (3)

Occupancy / completion certificate

  • Occupancy / completion certificate10 Aug 2021ViewSource

Other (6)

Form 4

Layout plan

Building plan

Document library

  • Declaration in FORM Bform b quality.pdf · uploaded 3 Aug 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)architecture.pdf · uploaded 3 Aug 2017View
  • Commencement Certificates / NA Order for plotted developmentcc.pdf · uploaded 3 Aug 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engin.pdf · uploaded 3 Aug 2017View
  • Copy of the legal title reportTitle Certificate.pdf · uploaded 3 Aug 2017View
  • Copy of Layout Approval (in case of layout)lAYOUT.pdf · uploaded 3 Aug 2017View
  • Building Plan Approval (IOD)bUILDING b pLANNING.pdf · uploaded 3 Aug 2017View
  • Proforma of Allotment letterDRAFT AGREEMENT OF QUALITY CONSTRUCTION.pdf · uploaded 3 Aug 2017View
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 3 Aug 2017View
  • Details of encumbrancesencumbrances.pdf · uploaded 3 Aug 2017View
  • Certificates of CA (Form 5)FORM 5.pdf · uploaded 29 Sep 2018View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5.pdf · uploaded 21 Dec 2019View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)20210430_164111_.pdf · uploaded 30 Apr 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)UDIN(1).pdf · uploaded 1 May 2021View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentB WING OC.pdf · uploaded 10 Aug 2021View
  • Status of Formation of Legal Entity (Society/Co Op etc.)New Doc 2021-01-22_1.pdf · uploaded 10 Aug 2021View
  • Architect’s Certificate on Completion of Project (Form 4)Form 4 phase I.pdf · uploaded 23 Aug 2021View
  • Disclosure of sold/ booked inventoryBooking status phase 1.pdf · uploaded 24 Aug 2021View
  • Disclosure of sold/ booked inventoryphase I.pdf · uploaded 12 Mar 2022View

Promoter documents

  • Declaration Form Bform b quality.pdf · uploaded 3 Aug 2017View
  • Legal Title reportTitle Certificate.pdf · uploaded 3 Aug 2017View

Technical documents

  • Building Plan ApprovalbUILDING b pLANNING.pdfView
  • Layout ApprovallAYOUT.pdfView

Proforma allotment letter

  • Proforma allotment letterDRAFT AGREEMENT OF QUALITY CONSTRUCTION.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel SURVEY NO 190 HISSA NO 1/B

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Address
Survey No 190 Hissa No 1/BPIN 400612
Village
Thane (M Corp.), Thane taluka
Land area for this project
259 sq m (2,789 sq ft)
Permissible built-up area
2,852 sq m (30,696 sq ft)
Sanctioned built-up area
2,852 sq m (30,696 sq ft)
Designated bank account
Dcb Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

SURVEY NO 190 HISSA NO 1/B

Land as published on MahaRERA's project page

SURVEY NO 190 HISSA NO 1/B

Boundaries

North
S No 201 Part
South
60 Mtr Mumbai Pune Road
East
S No 190 H No 1a
West
S No 190 H No 2

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking53 parking spaces

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000053
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress2 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

B Wing

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyDONE100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)DONE100%
  • Storm Water DrainsDONE100%
  • Landscaping & Tree PlantingDONE100%
  • Street Lightingwill be done prior to O.CNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvesting100%
  • Energy managemcntONLY RAIN WATER HARVESTINGNot applicable
  • Fire protection and fire safety requirements100%
  • Electrical meter room, sub-station, receiving stationDONE100%
  • Aggregate area of recreational Open SpaceDONE100%
  • Open Parkingwill be done prior to O.CNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectJoshi Deshaware & Associates—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology