Quality Construction Co

Company or firm · 2 projects · 2 MahaRERA registrations · 1 reported completed

2Projects2 RERA registrations
1Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Quality Heights IP51700010184Thane (M Corp.)2017Completed31 Dec 201831 Dec 2019+12 months
Quality Heights IIP51700015599Thane (M Corp.)2018Not reported30 Dec 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Quality Heights I+12 mo
  • Quality Heights IIOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Quality Heights I (P51700010184).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology