Skip to content
Residential / Group Housing · 1 building · 69 unitsRERA P51700008600

Prathamesh Towers

Deedo IDDP-THN-J8M1

MahaRERA shows it completed; no MahaRERA orders on record.

Thane (M Corp.), Thane 400607 · by Shivam Developers

DeliveryCompletedAs MahaRERA showsRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 19 Aug 2017, completion promised 31 Mar 2018.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700008600
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170000860019 Aug 201731 Mar 2018—Shivam DevelopersProject page
Documents36

16 documents held by Deedo, 20 filings listed on MahaRERA's project page

Commencement certificate

Form 1

Title report

Allotment letter (2)

Encumbrance details (2)

Form B

Show all 36 documentsShow fewer documents

Form 2

Registration certificate

Form 5

Form 4

Other (2)

Layout plan

Building plan

Document library

  • Copy of Layout Approval (in case of layout)Layout Approval.pdf · uploaded 29 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 29 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCommence Certificate29072017.pdf · uploaded 29 Jul 2017View
  • Proforma of Allotment letterAllottment letter.pdf · uploaded 30 Jul 2017View
  • Proforma of Allotment letterSale Agreement of RERA.pdf · uploaded 30 Jul 2017View
  • Copy of the legal title reportLatest Title Report.PDF · uploaded 30 Jul 2017View
  • Declaration in FORM BFinal Form B-Shivam Developers.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 31 Jul 2017View
  • Details of encumbrancesDeclaration of No Encumbrances.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)Building Plan.pdf · uploaded 31 Jul 2017View
  • OtherPrathamesh Tower Project Note.pdf · uploaded 31 Jul 2017View
  • Details of encumbrancesRERA Updation- Letter of Emcumbrances.pdf · uploaded 15 Jun 2018View
  • Certificates of CA (Form 5)Form 5 - Prathamesh Tower.pdf · uploaded 15 Oct 2018View
  • Architect’s Certificate on Completion of Project (Form 4)Shivam Dev.pdf · uploaded 21 Jan 2020View

Promoter documents

  • Legal Title reportLatest Title Report.PDF · uploaded 30 Jul 2017View
  • Declaration Form BFinal Form B-Shivam Developers.pdf · uploaded 31 Jul 2017View

Technical documents

  • Layout ApprovalLayout Approval.pdfView
  • Building Plan ApprovalBuilding Plan.pdfView

Other legal documents

  • OtherPrathamesh Tower Project Note.pdfView

Proforma allotment letter

  • Proforma allotment letterSale Agreement of RERA.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 42/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Unit types
1 BHK A, 1 BHK B, 1 BHK D, 2 BHK69 units in all
Address
42/1PIN 400607
Village
Thane (M Corp.), Thane taluka
Land area for this project
1,620 sq m (17,438 sq ft)
Permissible built-up area
3,423 sq m (36,848 sq ft)
Sanctioned built-up area
3,423 sq m (36,848 sq ft)
Recreational open space
241 sq m (2,593 sq ft)
Designated bank account
Punjab National Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

42/1

Land as published on MahaRERA's project page

42/1

Boundaries

North
84
South
30 m w DP Road
East
42 3
West
Wadavali Shiv

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking69 units · 30 parking spaces

69 units registered

1 BHK A · 18 units1 BHK B · 29 units1 BHK D · 4 units2 BHK · 18 units
TypeCarpet areaUnits
1 BHK A40.15 sq m · 432 sq ft18
1 BHK B38.58 sq m · 415 sq ft29
1 BHK D37.56 sq m · 404 sq ft4
2 BHK66.58 sq m · 717 sq ft18

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000010
Open Space000020

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress2 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Prathamesh Tower

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
  • Sanitary Fittings within the flats / premises95%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyU.G./O.H. Tank Completed90%
  • Sewerage (Chamber, Lines, Septic Tank , STP)S.P. Tank Completed95%
  • Storm Water DrainsWork in progress85%
  • Landscaping & Tree PlantingWork in progress10%
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingWork in progress10%
  • Energy managemcntWork in progress10%
  • Fire protection and fire safety requirementsWork in progress85%
  • Electrical meter room, sub-station, receiving stationWork in progress10%
  • Aggregate area of recreational Open SpaceOpen Spaces & Gardens90%
  • Open ParkingOpen Parking90%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAkruti Consultant—
EngineerTechline—
OtherDonga & Associates—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology