Prathamesh Tower · Prathamesh Towers
Thane (M Corp.) · RERA P51700008600
IDBLD_01176320 floorsCompleted
20Sanctioned habitable floorsregistration certificate
31 Mar 2018Promised completion
Floors
20 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- Sanctioned habitable floors
- 20
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK A | 40.2 m² (432 sq.ft) | 18 | not published |
| 1 BHK B | 38.6 m² (415 sq.ft) | 29 | not published |
| 1 BHK D | 37.6 m² (404 sq.ft) | 4 | not published |
| 2 BHK | 66.6 m² (717 sq.ft) | 18 | not published |
| Total | 69 |
Parking
Spaces as declared on MahaRERA's project page.
| Type | Two-wheeler | Four-wheeler | Visitor | Total |
|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 10 |
| Open Space | 0 | 0 | 0 | 20 |
Construction progress
Work completed on this building, as the promoter reported it to MahaRERA (Form 1).
- Excavation100%
- Basement (if any)100%
- Podiums (if any)0%
- Plinth100%
- Stilt Floor100%
- Slabs of Super Structure100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
- Sanitary Fittings within the flats / premises95%
Show all 11 activitiesShow fewer activities
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Data through11 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology