Prathamesh Tower · Prathamesh Towers

Thane (M Corp.) · RERA P51700008600

IDBLD_01176320 floorsCompleted
20Sanctioned habitable floorsregistration certificate
31 Mar 2018Promised completion

Floors

20 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51700008600 · registered 19 Aug 2017
Promised completion
31 Mar 2018
Sanctioned habitable floors
20

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1 BHK A40.2 m² (432 sq.ft)18not published
1 BHK B38.6 m² (415 sq.ft)29not published
1 BHK D37.6 m² (404 sq.ft)4not published
2 BHK66.6 m² (717 sq.ft)18not published
Total69

Parking

Spaces as declared on MahaRERA's project page.

TypeTwo-wheelerFour-wheelerVisitorTotal
Closed/Covered00010
Open Space00020

Construction progress

Work completed on this building, as the promoter reported it to MahaRERA (Form 1).

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
  • Sanitary Fittings within the flats / premises95%
Show all 11 activitiesShow fewer activities
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Data through11 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology