Deedo IDDP-THN-F29ACompletion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 58% of its units are booked.
Thane (M Corp.), Thane 400607 · by Jvm Spectrum Llp
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 5 Dec 2025, completion promised 31 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
4 buildings
Open a building to see every flat, floor by floor.
- Building - 1 Wing A6 floors · 35 units
- Building - 1 Wing B6 floors · 29 units
- Wing A6 floors · 35 units67% booked
- Wing B6 floors · 29 units36% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPR1330002501685
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PR1330002501685 | 5 Dec 2025 | 31 Dec 2028 | 30 Apr 2029 | JVM Spectrum LLP | Project page |
Documents28
1 document held by Deedo, 27 filings listed on MahaRERA's project page
Finance
Legal
- OthersAnnexure A -Disclosure of Intrest -Firm and Partners Merged.pdf · uploaded 12 Nov 2025Source
- Declaration Form BRERA Title Certificate - LUV Kutir.pdf · uploaded 12 Nov 2025Source
- Declaration Form BRERA Title Certificate - Shatrudhan.pdf · uploaded 12 Nov 2025Source
- Declaration Form BForm-B - Affidavit cum Declaration - Promoter Notarized.pdf · uploaded 12 Nov 2025Source
- OthersJVM spectrum (LLP) Partnership Deed_.pdf · uploaded 18 Nov 2025Source
Show all 28 documentsShow fewer documents
Migrated
- Withdrawal Update Form 1Form 1 - JVMs Centrum as on Dec 2025.pdf · uploaded 14 May 2026Source
- Withdrawal Update Form 2Form 2 - JVMs Centrum as on Dec 2025.pdf · uploaded 14 May 2026Source
- Withdrawal Update Form 3Form 3 - JVMs Centrum as on Dec 2025.pdf · uploaded 14 May 2026Source
- Withdrawal Update Form 1Form 1 - JVMs Centrum as on March 2026.pdf · uploaded 18 May 2026Source
- Withdrawal Update Form 2Form 2 - JVMs Centrum as on March 2026.pdf · uploaded 18 May 2026Source
- Withdrawal Update Form 3Form 3 - JVMs Centrum as on March 2026.pdf · uploaded 18 May 2026Source
- Withdrawal Update Form 1JVM Centrum_Form -1.pdf · uploaded 18 Jul 2026Source
- Withdrawal Update Form 2Jvm_S_Centrum_Form2_Q1_2026-27_18-07-2026_11-24.pdf · uploaded 18 Jul 2026Source
- Withdrawal Update Form 3Jvm_S_Centrum_Form3_Q1_2026-27_18-07-2026_08-07_doc1.pdf · uploaded 18 Jul 2026Source
- Withdrawal Update Form 1JVM Centrum_Form -1.pdf · uploaded 31 Aug 2026Source
- Withdrawal Update Form 2Jvm_S_Centrum_Form2_Q1_2026-27_18-07-2026_11-24.pdf · uploaded 31 Aug 2026Source
- Withdrawal Update Form 3Jvm_S_Centrum_Form3_Q1_2026-27_18-07-2026_08-07_doc1.pdf · uploaded 31 Aug 2026Source
Technical
- DocumentLayout Plan Jvms centrum Final-1.pdf · uploaded 12 Nov 2025Source
- DocumentBuilding Plan Jvms centrum Final-2-3.pdf · uploaded 12 Nov 2025Source
- DocumentBuilding Plan Jvms centrum Final-4-5.pdf · uploaded 12 Nov 2025Source
- OthersC Verification Mail Screenshot (As per Order No 45).pdf · uploaded 12 Nov 2025Source
- DocumentAnnexure A - Order No 50 - Declaration - 04112025.pdf · uploaded 20 Nov 2025Source
- OthersDeclaration regarding clarification of unit allocation - 17112025.pdf · uploaded 20 Nov 2025Source
Technical (Architect)
- DocumentJVM Centrum_Form -1.pdf · uploaded 18 Jul 2026Source
Technical (Engineer)
- DocumentJvm_S_Centrum_Form2_Q1_2026-27_18-07-2026_11-24.pdf · uploaded 18 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel CTS No 369/5, CTS No - 369/6
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —64 units in all
- Address
- 9 Mtr Wide Road, Dhokali, Yashasvi NagarPIN 400607
- Village
- Thane (M Corp.), Thane taluka
- Location
- 19.22239, 72.98370
- Land area for this project
- 1,264 sq m (13,606 sq ft)
- Permissible built-up area
- 5,425 sq m (58,397 sq ft)
- Sanctioned built-up area
- 3,827 sq m (41,193 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 76
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Plot No 6, Plot No 5 , CTS No - 369/6, Survey No -76/B/6, CTS No 369/5, Survey No -76/B/5, Sector -5 Village Dhokali
Boundaries
- North
- CTS No - 363 & CTS No - 369/6
- South
- CTS No - 369/4 & CTS No - 369/5
- East
- CTS No -355
- West
- CTS No 439
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking64 units
64 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Wing A | — | — | 35 |
| Wing B | — | — | 29 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Other projects in Thane (M Corp.)
- Metro MilleniaRERA PM1330002602679
- Kalyani Krupa Co.op Hsg Soc LtdRERA PR1330002602399
- Shreeji's Laxmi Jyot CHSLRERA PR1330002602306
- RivantaRERA PM1330002601984
- Shree Gangadhar ChslRERA PM1330002601922
- The Lake CornerRERA PM1330002601899
- Shree AudumbarRERA PR1330002601484
- Shreyas Co-Op Hsg. Soc. Ltd.RERA PR1330002601418
All 898 projects in Thane (M Corp.) · Compare JVM's Centrum with another project