Invictus By Gs
Deedo IDDP-THN-FKY0Completion was pushed back 4 months, to Feb 2029; no MahaRERA orders on record; 60% of its units are booked.
Thane (M Corp.), Thane 400606 · by Raymond Realty Limited
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Feb 2029
- This projectRegistered 19 Jul 2023, completion promised 5 Oct 2028, revised to 5 Feb 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700052012
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700052012 | 19 Jul 2023 | 5 Oct 2028 | 5 Feb 2029 | Raymond Realty Limited | Project page |
Documents162
1 document held by Deedo, 161 filings listed on MahaRERA's project page
Finance
Legal
Show all 162 documentsShow fewer documents
Migrated
- 1 b Details of encumbrances concerned to Legallegal encumbrances.pdf · uploaded 3 Jul 2023Source
- 1 Declaration in FORM BForm B.pdf · uploaded 3 Jul 2023Source
- 1 Proforma of Allotment letterALLOTMENT LETTER WORD.pdf · uploaded 3 Jul 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samedeclaration about seprate bank account.pdf · uploaded 3 Jul 2023Source
- 2 a Details of encumbrances concerned to Financefianacial encumbrance.pdf · uploaded 4 Jul 2023Source
- 2 b Details of encumbrances concerned to Legalfianacial encumbrance.pdf · uploaded 4 Jul 2023Source
- 1 CERSAI detailsCR.pdf · uploaded 4 Jul 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Invictus by GS.pdf · uploaded 4 Jul 2023Source
- 1 Copy of the legal title reportTitle Report.pdf · uploaded 5 Jul 2023Source
- 1 Proforma of Agreement for saleFINAL AFS.pdf · uploaded 5 Jul 2023Source
- 1 Deviation Report with respect to model copy of AgreementPart 1.pdf · uploaded 5 Jul 2023Source
- 2 Deviation Report with respect to model copy of AgreementPart 2.pdf · uploaded 5 Jul 2023Source
- 3 Deviation Report with respect to model copy of AgreementPart 3.pdf · uploaded 5 Jul 2023Source
- 4 Deviation Report with respect to model copy of AgreementPart 4.pdf · uploaded 5 Jul 2023Source
- 1 Copy of Layout Approval (in case of layout)Wing 1-Layout Plan.pdf · uploaded 7 Jul 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentWing 1 -2,7,12,17,21,26,31 floor plan.pdf · uploaded 7 Jul 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentWing 1 -3,8,13,18,22,27,32_compressed.pdf · uploaded 7 Jul 2023Source
- 3 Building Plan Approval / NA Order for plotted developmentWing 1 -4,5,6,9,10,11,14,15,16,19,20,22,23,24,25,28,29,30 flr plan.pdf · uploaded 7 Jul 2023Source
- 4 Building Plan Approval / NA Order for plotted development2nd Podium floor plan.pdf · uploaded 7 Jul 2023Source
- 5 Building Plan Approval / NA Order for plotted development4th Podium floor plan.pdf · uploaded 7 Jul 2023Source
- 6 Building Plan Approval / NA Order for plotted developmentBasement floor Plan.pdf · uploaded 7 Jul 2023Source
- 7 Building Plan Approval / NA Order for plotted developmentLower Ground floor plan.pdf · uploaded 7 Jul 2023Source
- 8 Building Plan Approval / NA Order for plotted developmentPodium Top-Stilt floor plan.pdf · uploaded 7 Jul 2023Source
- 9 Building Plan Approval / NA Order for plotted developmentUpper Grnd Flr,1st Podium_compressed.pdf · uploaded 7 Jul 2023Source
- 10 Building Plan Approval / NA Order for plotted developmentWing 1 - Terrace floor plan.pdf · uploaded 7 Jul 2023Source
- 11 Building Plan Approval / NA Order for plotted developmentWing 1- Section AA.pdf · uploaded 7 Jul 2023Source
- 12 Building Plan Approval / NA Order for plotted developmentUpper Grnd Flr,1st Podium_compressed.pdf · uploaded 7 Jul 2023Source
- 13 Building Plan Approval / NA Order for plotted development3rd Podium floor plan.pdf · uploaded 7 Jul 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCC PERMISSION.pdf · uploaded 7 Jul 2023Source
- 1 Declaration about Commencement Certificatecc declaration.pdf · uploaded 7 Jul 2023Source
- 1 Deviation Report with respect to Allotment letterdeviation sheet allotment letter.pdf · uploaded 13 Jul 2023Source
- 1 Disclosure of Interest in Other Real Estate Organizations1.pdf · uploaded 14 Jul 2023Source
- 2 Disclosure of Interest in Other Real Estate Organizations2.pdf · uploaded 14 Jul 2023Source
- 3 Disclosure of Interest in Other Real Estate Organizations3.pdf · uploaded 14 Jul 2023Source
- 4 Disclosure of Interest in Other Real Estate Organizations4.pdf · uploaded 14 Jul 2023Source
- 5 Disclosure of Interest in Other Real Estate Organizations5.pdf · uploaded 14 Jul 2023Source
- 6 Disclosure of Interest in Other Real Estate Organizations6.pdf · uploaded 14 Jul 2023Source
- 7 Disclosure of Interest in Other Real Estate Organizations7.pdf · uploaded 14 Jul 2023Source
- 8 Disclosure of Interest in Other Real Estate Organizations8.pdf · uploaded 14 Jul 2023Source
- 1 Other – LegalPrashant Rathod- Resolution.pdf · uploaded 14 Jul 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Invictus by GS signed.pdf · uploaded 22 Aug 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 RERA Invictus.pdf · uploaded 22 Aug 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Invictus by GS.pdf · uploaded 22 Aug 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Invictus RERA Certificate.pdf · uploaded 26 Oct 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)INVICTUS BY GS.pdf · uploaded 26 Oct 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 RERA INVICTUS BY GS.pdf · uploaded 27 Oct 2023Source
- 2 CERSAI details1.pdf · uploaded 27 Oct 2023Source
- 1 Disclosure of sold/ booked inventoryINVICTUS BY GS.pdf · uploaded 1 Nov 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1Invictus by GS Tower_240109_150550.pdf · uploaded 12 Jan 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 RERA - Invictus 080124.pdf · uploaded 12 Jan 2024Source
- 1 Other – FinanceForm 3 Invictus.pdf · uploaded 12 Jan 2024Source
- 3 CERSAI detailsCERSAI_Search_Report_200293558244_For_Asset_Based_Search_15_01_2024_18_12_16_284.pdf · uploaded 16 Jan 2024Source
- 2 Disclosure of sold/ booked inventoryINVICTYS BY GS_240123_150623.pdf · uploaded 23 Jan 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Invictus by GS.pdf · uploaded 8 Apr 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 RERA - Invictus 030424.pdf · uploaded 8 Apr 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)INVICTUS.pdf · uploaded 15 Apr 2024Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)INVICTUS BY GS.pdf · uploaded 18 Apr 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Invictus.pdf · uploaded 18 Apr 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Invictus by GS.pdf · uploaded 18 Apr 2024Source
- 4 CERSAI detailsCERSAI_Search_Report_200304176658_For_Asset_Based_Search_18_04_2024_16_19_40_535.pdf · uploaded 19 Apr 2024Source
- 5 CERSAI detailsCERSAI_Search_Report_200304180320_For_Asset_Based_Search_18_04_2024_16_39_13_935.pdf · uploaded 19 Apr 2024Source
- 6 CERSAI detailsCERSAI_Search_Report_200304180455_For_Asset_Based_Search_18_04_2024_16_39_56_846.pdf · uploaded 19 Apr 2024Source
- 7 CERSAI detailsCERSAI_Search_Report_200304180506_For_Asset_Based_Search_18_04_2024_16_40_11_014.pdf · uploaded 19 Apr 2024Source
- 3 Disclosure of sold/ booked inventoryINVICTUS BY GS.pdf · uploaded 23 Apr 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 RERA - Invictus 010724.pdf · uploaded 9 Jul 2024Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM2A.pdf · uploaded 16 Jul 2024Source
- 4 Disclosure of sold/ booked inventorySOLD UNSOLD INVICTUS.pdf · uploaded 18 Jul 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Invictus.pdf · uploaded 19 Jul 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Annexure -14, INVICTUS BY GS.pdf · uploaded 7 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 Invictus.pdf · uploaded 14 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 RERA - Invictus 300924.pdf · uploaded 14 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed RERA Form 3 - Tower Invictus - Certificate Number 190.pdf · uploaded 15 Oct 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed RERA Form 3 - Tower Invictus - Certificate Number 190.pdf · uploaded 16 Oct 2024Source
- 2 Disclosure of sold/ booked inventoryInvictus By GS.pdf · uploaded 24 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 invictus by GS tower_250113_122920.pdf · uploaded 15 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA Form 3 - Tower Invictus - Certificate Number 285 signed.pdf · uploaded 15 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 RERA - Invictus 311224.pdf · uploaded 16 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryInvictus BY GS.pdf · uploaded 21 Jan 2025Source
- 1 Copy of Layout Approval (in case of layout)layout compress.pdf · uploaded 19 Feb 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 19 Feb 2025Source
- 4 Building Plan Approval / NA Order for plotted developmentTOWER 1pdf 5.pdf · uploaded 19 Feb 2025Source
- 11 Building Plan Approval / NA Order for plotted developmentTOWER 1pdf 12.pdf · uploaded 19 Feb 2025Source
- 10 Building Plan Approval / NA Order for plotted developmentTOWER 1pdf 11.pdf · uploaded 19 Feb 2025Source
- 9 Building Plan Approval / NA Order for plotted developmentTOWER 1pdf 10.pdf · uploaded 19 Feb 2025Source
- 8 Building Plan Approval / NA Order for plotted developmentTOWER 1pdf 9.pdf · uploaded 19 Feb 2025Source
- 7 Building Plan Approval / NA Order for plotted developmentTOWER 1pdf 8.pdf · uploaded 19 Feb 2025Source
- 6 Building Plan Approval / NA Order for plotted developmentTOWER 1pdf 7.pdf · uploaded 19 Feb 2025Source
- 5 Building Plan Approval / NA Order for plotted developmentTOWER 1pdf 6.pdf · uploaded 19 Feb 2025Source
- 3 Building Plan Approval / NA Order for plotted developmentTOWER 1pdf 4.pdf · uploaded 19 Feb 2025Source
- 2 Building Plan Approval / NA Order for plotted developmentTOWER 1pdf 3.pdf · uploaded 19 Feb 2025Source
- 1 Building Plan Approval / NA Order for plotted developmentTOWER 1- 2.pdf · uploaded 19 Feb 2025Source
- 1 Declaration about Commencement CertificateCC DECLARATION INVITUS BY GS.pdf · uploaded 19 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Invictus.pdf · uploaded 17 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA Form 3 - Tower Invictus - Certificate Number 29 signed.pdf · uploaded 19 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 RERA - Invictus 310325.pdf · uploaded 19 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryInvictus By GS.pdf · uploaded 24 Apr 2025Source
- Form 2A (FY 2024-2025)INVICTUS BY GS.pdf · uploaded 3 Jul 2025Source
- Form 1Form 1 _Invictus.pdf · uploaded 20 Jul 2025Source
- Form 3Form 3_invictus.pdf · uploaded 20 Jul 2025Source
- Form 2Form 2 RERA.pdf · uploaded 20 Jul 2025Source
- Disclosure of Sold and Booked Inventorysold list.pdf · uploaded 20 Jul 2025Source
- Form 1Form 1 Invictus.pdf · uploaded 20 Jul 2025Source
- Form 2Form 2 RERA - Invictus 310325.pdf · uploaded 20 Jul 2025Source
- Form 3RERA Form 3 - Tower Invictus - Certificate Number 29 signed.pdf · uploaded 20 Jul 2025Source
- Disclosure of Sold and Booked InventoryInvictus By GS.pdf · uploaded 20 Jul 2025Source
- Form 5 (FY 2024-2025)Invictus by GS_Statement and Certificate.pdf · uploaded 29 Sep 2025Source
- Withdrawal Update Form 1Invictus_Online.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 2Form 2_Invictus.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 3Form 3_Invictus.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 1Form 1_Invictus.pdf · uploaded 22 Jan 2026Source
- Withdrawal Update Form 2Form 2 _Invictus.pdf · uploaded 22 Jan 2026Source
- Withdrawal Update Form 3Form 3 Invictus _.pdf · uploaded 22 Jan 2026Source
- Withdrawal Update Form 1Form 1_Invictus by GS.pdf · uploaded 23 Apr 2026Source
- Withdrawal Update Form 2Form 2_Invictus by GS.pdf · uploaded 23 Apr 2026Source
- Withdrawal Update Form 3Form 3_Invictus BY GS.pdf · uploaded 23 Apr 2026Source
- Form 2A (FY 2025-2026)INVIXTUS BY GS.pdf · uploaded 26 Jun 2026Source
- Withdrawal Update Form 1Form 1-Ivictus by GS.pdf · uploaded 10 Jul 2026Source
- Withdrawal Update Form 2Form 2_Invictus by GS.pdf · uploaded 10 Jul 2026Source
- Withdrawal Update Form 3Form 3_ Invictus BY GS.pdf · uploaded 10 Jul 2026Source
- Form 5 (FY 2025-2026)Invictus BY GS RERA Certificates and statement.pdf · uploaded 29 Sep 2026Source
Technical
- DocumentWing 1-Layout Plan.pdf · uploaded 7 Jul 2023Source
- DocumentWing 1 -2,7,12,17,21,26,31 floor plan.pdf · uploaded 7 Jul 2023Source
- DocumentWing 1 -3,8,13,18,22,27,32_compressed.pdf · uploaded 7 Jul 2023Source
- DocumentWing 1 -4,5,6,9,10,11,14,15,16,19,20,22,23,24,25,28,29,30 flr plan.pdf · uploaded 7 Jul 2023Source
- Document2nd Podium floor plan.pdf · uploaded 7 Jul 2023Source
- Document4th Podium floor plan.pdf · uploaded 7 Jul 2023Source
- DocumentBasement floor Plan.pdf · uploaded 7 Jul 2023Source
- DocumentLower Ground floor plan.pdf · uploaded 7 Jul 2023Source
- DocumentPodium Top-Stilt floor plan.pdf · uploaded 7 Jul 2023Source
- DocumentUpper Grnd Flr,1st Podium_compressed.pdf · uploaded 7 Jul 2023Source
- DocumentWing 1 - Terrace floor plan.pdf · uploaded 7 Jul 2023Source
- DocumentWing 1- Section AA.pdf · uploaded 7 Jul 2023Source
- DocumentUpper Grnd Flr,1st Podium_compressed.pdf · uploaded 7 Jul 2023Source
- Document3rd Podium floor plan.pdf · uploaded 7 Jul 2023Source
- Documentlayout compress.pdf · uploaded 19 Feb 2025Source
- DocumentTOWER 1- 2.pdf · uploaded 19 Feb 2025Source
- DocumentTOWER 1pdf 3.pdf · uploaded 19 Feb 2025Source
- DocumentTOWER 1pdf 4.pdf · uploaded 19 Feb 2025Source
- DocumentTOWER 1pdf 5.pdf · uploaded 19 Feb 2025Source
- DocumentTOWER 1pdf 6.pdf · uploaded 19 Feb 2025Source
- DocumentTOWER 1pdf 7.pdf · uploaded 19 Feb 2025Source
- DocumentTOWER 1pdf 8.pdf · uploaded 19 Feb 2025Source
- DocumentTOWER 1pdf 9.pdf · uploaded 19 Feb 2025Source
- DocumentTOWER 1pdf 10.pdf · uploaded 19 Feb 2025Source
- DocumentTOWER 1pdf 11.pdf · uploaded 19 Feb 2025Source
- DocumentTOWER 1pdf 12.pdf · uploaded 19 Feb 2025Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 65 132/2
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 4BHK102 units in all
- Address
- 65 132/2, Pokhran Road No 1, Village PanchpakhadiPIN 400606
- Village
- Thane (M Corp.), Thane taluka
- Land area for this project
- 1,064 sq m (11,448 sq ft)
- Permissible built-up area
- 34,385 sq m (3,70,113 sq ft)
- Sanctioned built-up area
- 34,385 sq m (3,70,113 sq ft)
- Recreational open space
- 7,445 sq m (80,139 sq ft)
- Designated bank account
- 171
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
65 132/2
Boundaries
- North
- 132 2
- South
- 66 132 2
- East
- 132 2
- West
- 131 B 30 M Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking102 units
61 of 102 units booked (60%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 4BHK | 206.77 sq m · 2,226 sq ft | 54 | 25 |
| 4BHK | 207 sq m · 2,228 sq ft | 14 | 9 |
| 4BHK | 218.97 sq m · 2,357 sq ft | 34 | 27 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Engineer | Rajesh Mishra | — |
Source: MahaRERA project page. Contact details are not shown.