Raymond Realty Limited

Company or firm · 12 projects · 15 MahaRERA registrations

12Projects15 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 13 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
TEN X HABITAT Raymond Realty Tower FP51700034190Thane (M Corp.)2022Certificate Signed31 Aug 202631 Aug 2026On date
TEN X HABITAT Raymond Realty Tower GP51700047152Thane (M Corp.)2022Certificate Signed30 Jun 202630 Jun 2026On date
TEN X ERA Raymond Realty Tower CP51700049520Thane (M Corp.)2023Certificate Signed30 Jan 202930 May 2029+4 months
TEN X ERA Raymond Realty Tower BP51700049592Thane (M Corp.)2023Certificate Signed30 Jan 202930 May 2029+4 months
The Address By Gs Tower CP51700052008Thane2023Certificate Signed25 Dec 202825 Apr 2029+4 months
Invictus By GsP51700052012Thane (M Corp.)2023Certificate Signed5 Oct 20285 Feb 2029+4 months
The Address by GS Tower DP51700053947Thane (M Corp.)2023Certificate Signed31 Mar 202931 Jul 2029+4 months
Park AvenueP51700077214Thane (M Corp.)2024Certificate Signed31 Jul 202730 Nov 2027+4 months
The Address by GSP51700077861Thane (M Corp.)2024Certificate Signed31 Mar 203031 Jul 2030+4 months
Invictus by GS Tower BPR1335052500426Thane (M Corp.)2025Certificate Signed31 Aug 203131 Dec 2031+4 months
The Address by GSPR1335052500430Thane (M Corp.)2025Certificate Signed31 Oct 203129 Feb 2032+4 months
Tenx DistrictPM1331012502632Panchpakhadi2026Certificate Signed31 Dec 203130 Apr 2032+4 months
Tenx DistrictPM1331012502633Panchpakhadi2026Certificate Signed31 Dec 203130 Apr 2032+4 months
Tenx DistrictPM1331012502634Panchpakhadi2026Certificate Signed31 Jan 203231 May 2032+4 months
Raymond RetailPC1330002600856Panchpakhadi2026Certificate Signed30 Jun 203730 Oct 2037+4 months
Show all 15 registrationsShow fewer

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • TEN X HABITAT Raymond Realty Tower FOn date
  • TEN X HABITAT Raymond Realty Tower GOn date
  • TEN X ERA Raymond Realty Tower C+4 mo
  • TEN X ERA Raymond Realty Tower B+4 mo
  • The Address By Gs Tower C+4 mo
  • Invictus By Gs+4 mo
  • The Address by GS Tower D+4 mo
  • Park Avenue+4 mo
  • The Address by GS+4 mo
  • Invictus by GS Tower B+4 mo
Show all 15 registrations
  • The Address by GS+4 mo
  • Tenx District+4 mo
  • Tenx District+4 mo
  • Tenx District+4 mo
  • Raymond Retail+4 mo

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for TEN X ERA Raymond Realty Tower C (P51700049520).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology