Completed10 floorsRERA P51700009018

Main building, Girivihar

Deedo IDDP-THN-CG67-GIRIVI

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

All of Girivihar
Median saleNot on recordneeds 3 or more sales
Completion31 May 2019as registered
Units & parking in Main building
TypeCarpet areaUnitsBooked
1BHK28.8 m² (310 sq.ft)1Not on record
1BHK29.1 m² (313 sq.ft)1Not on record
1BHK29.1 m² (314 sq.ft)1Not on record
1BHK29.8 m² (321 sq.ft)1Not on record
1RK29.2 m² (314 sq.ft)2Not on record
2BHK52.6 m² (566 sq.ft)5Not on record
2BHK54 m² (582 sq.ft)1Not on record
3BHK68.7 m² (739 sq.ft)5Not on record
SHOP68.8 m² (740 sq.ft)1Not on record
STORAGE70.6 m² (760 sq.ft)1Not on record
STUDIO APARTMENT15.3 m² (164 sq.ft)1Not on record

Parking: Closed/Covered 10 · Open Space 2 (as declared to MahaRERA)

Construction progress (declared)

Work completed, as the promoter reported it to MahaRERA (Form 1). Not verified on site.

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure70%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
As registered with MahaRERA
RERA registration
P51700009018 · registered 19 Aug 2017
Promised completion
31 May 2019
Sanctioned habitable floors
10
Also named
Girivihar
Deedo ID
DP-THN-CG67-GIRIVI
Questions about Main building

When is Main building due for completion?

The MahaRERA registration promises 31 May 2019.

How many floors does Main building have?

10 sanctioned habitable floors, as registered with MahaRERA.

Data through11 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology