RERA projects in Thane (M Corp.)

1,176 projects under 1,298 MahaRERA registrations, registered 2017–2026. 47% have a completion date extended beyond the one promised.

Locality
1,176RERA projects
1,298Registrationssome projects hold several
567Completion still due731 past their completion date, 16 marked completed
4 monthsMedian extension beyond promised date47% of registrations extended
128Regulatory caseson 38 projects
1,952Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
2017443
2018116
2019118
202072
202151
2022102
2023114
2024109
2025129
202644

Projects in Thane (M Corp.)

1,176 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
JVM's CentrumJVM Spectrum LLPPR13300025016855 Dec 202531 Dec 202830 Apr 2029Extended 4 mo0
Poonam Chhaya CHSLVastu Vaibhav Creations LLPPR13300025016312 Dec 202531 Dec 202930 Apr 2030Extended 4 mo0
Sankalp HeightsJ K RealconPM133000250151118 Nov 202531 Dec 202730 Apr 2028Extended 4 mo0
Shree Sai Charan ChslMandar Constructions And Developers LLPPR133000250143811 Nov 202531 May 202930 Sep 2029Extended 4 mo0
Al-Taiba TowerRayyan ConstructionsPM133000250143010 Nov 202531 Dec 202930 Apr 2030Extended 4 mo0
Anupam Chs. Ltd.Shree Mangalmurti EnterprisesPR133000250142210 Nov 202525 Dec 202925 Apr 2030Extended 4 mo0
Om Vishnu Smruti Co-Operative Housing Society LimitedOm Vishnu Smruti Co-Operative Housing Society LimitedPR13300025014047 Nov 202530 Sep 202730 Jan 2028Extended 4 mo0
Leela PrasadPataskar Developers Private LimitedP5170008103331 Oct 202531 Dec 202630 Apr 2027Extended 4 mo0
Moksh TowerSuresh Shalik MhatrePM133000250137631 Oct 202531 May 202930 Sep 2029Extended 4 mo0
Madhav BlissShreeji Madhav Infra LLPPM133000250134028 Oct 202531 May 203030 Sep 2030Extended 4 mo0
Sandeep ApartmentYogesh Shashikant KadamPR133000250127520 Oct 202530 Sep 202730 Jan 2028Extended 4 mo0
Shree KrupaMagnum BuildersPR133000250127720 Oct 202531 Dec 202730 Apr 2028Extended 4 mo0
Star LivingsShivam SheltersP5170008102420 Oct 202531 Oct 202928 Feb 2030Extended 4 mo0
Nav OmkarAvighna Redevelopers Nav OmkarPM133000250124416 Oct 202531 Dec 202830 Apr 2029Extended 4 mo0
Stella-Tower BLodha Developers LimitedPM133000250122514 Oct 202531 Dec 203030 Apr 2031Extended 4 mo0
AdwaitShree Swami Samartha AssociatesP517000810069 Oct 202531 Dec 202830 Apr 2029Extended 4 mo0
Satej Premises Co-operative Society LimitedOjass Govind Infra LLPPM13300025011649 Oct 202531 Dec 202730 Apr 2028Extended 4 mo0
Rosa Manhattan Phase 3Sai Uma Construction Private LimitedPM13320225011067 Oct 202530 Jun 203230 Oct 2032Extended 4 mo0
New DwarkaMangal Siddhi RealtyPR13300025010731 Oct 202531 Mar 202731 Jul 2027Extended 4 mo0
One EastAashman EnterprisesPR13300025010381 Oct 202531 Dec 202930 Apr 2030Extended 4 mo0
Rosa SephoraAakash Darshan Buildcorp LLPP5170008099129 Sep 202531 Dec 202930 Apr 2030Extended 4 mo0
Maher Premises Co Op Hsg Soc LtdShrusti CasaPR133000250097926 Sep 202528 Aug 202828 Dec 2028Extended 4 mo0
Metro ImperialPragati CombinesPM133000250093924 Sep 202531 Dec 202830 Apr 2029Extended 4 mo0
Deepjyoti Co. Op. Housing SocietyAditya AssociatesPR133000250087022 Sep 202531 Jan 202831 May 2028Extended 4 mo0
One ArthasyaTop Floor Realty LLPPC133000250089222 Sep 202531 Dec 203130 Apr 2032Extended 4 mo0

Other localities in Thane

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Roma Builders Private Limited24 projects
  2. Macrotech Developers Limited23 projects
  3. Aditya Associates12 projects
  4. Dosti Enterprises12 projects
  5. Lodha Developers Limited12 projects
  6. Raymond Realty Limited10 projects
  7. Sai Shrushti Enterprises10 projects
  8. Unnathi Associates9 projects
  9. Agile Real Estate Pvt. Ltd.8 projects
  10. Mahesh Shriram Borkar8 projects
Data through23 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology