Deedo IDDP-THN-7WKXCompletion was pushed back 4 months, to Mar 2030; no MahaRERA orders on record; 23% of its units are booked.
Sonale, Thane 421302 · by Skybound Heights India Private Limited
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Mar 2030
- This projectRegistered 13 Feb 2020, completion promised 13 Nov 2029, revised to 13 Mar 2030.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- Type1Size not on record0% booked
- Type-2 A WingSize not on record22% booked
- Type-2 B WingSize not on record100% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700024463
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700024463 | 13 Feb 2020 | 13 Nov 2029 | 13 Mar 2030 | Skybound Heights India Private Limited | Project page |
Documents170
2 documents held by Deedo, 168 filings listed on MahaRERA's project page
Legal
Show all 170 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentPLAN AND BANDKAM_compressed.pdf · uploaded 6 Feb 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentBANDH KAAM AND PLAN_compressed.pdf · uploaded 6 Feb 2020Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 6 Feb 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER'S CERTIFICATE (1)_compressed.pdf · uploaded 6 Feb 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE.pdf · uploaded 6 Feb 2020Source
- 1 Proforma of Allotment letterDraft Agreement (Bhiwandi).pdf · uploaded 6 Feb 2020Source
- 2 Proforma of Allotment letterFlat No.pdf · uploaded 20 Jan 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentBHADWAD REVISED CC COPY.pdf · uploaded 3 Apr 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE TYPE 2 B WING.pdf · uploaded 3 Apr 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE TYPE 2 B WING.pdf · uploaded 3 Apr 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE TYPE 1.pdf · uploaded 3 Apr 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate FORM -2.pdf · uploaded 3 Apr 2023Source
- 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf · uploaded 25 Apr 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsANNEXURE A (1).pdf · uploaded 25 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Skybound Heights India Pvt Ltd FY 2020 -21-Sign.pdf · uploaded 1 Jun 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Skybound Heights India Pvt Ltd FY 2021-22-Sign.pdf · uploaded 1 Jun 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Skybound Form 3 Signed.pdf · uploaded 4 Apr 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Certificate Form 5 2022-23.pdf · uploaded 17 Apr 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Certificate form 5 2023-2024.pdf · uploaded 17 Apr 2025Source
- Form 5 (FY 2024-2025)RERA Audit Report_24-25.pdf · uploaded 2 Jun 2025Source
- Form 5 (FY 2019-2020)RERA Audit Report_19-20.pdf · uploaded 3 Jun 2025Source
- Form 1Form 1 - Q1 June 24 (System Generated)-Signed.pdf · uploaded 17 Jun 2025Source
- Form 2Form 2 - Q1 Jun 24 (System Generated) - Signed.pdf · uploaded 17 Jun 2025Source
- Form 3Form 3 Q1 24-25-signed.pdf · uploaded 17 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Booked- Q1 June 24.pdf · uploaded 17 Jun 2025Source
- Form 1Form 1 - Q2 Sep 24 (System Generated)-Signed.pdf · uploaded 17 Jun 2025Source
- Form 2Form 2 - Q2 Sep 24 (System Generated) - Signed.pdf · uploaded 17 Jun 2025Source
- Form 3Form 3 Q2 24-25-signed.pdf · uploaded 17 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Booked- Q2 Sep 24.pdf · uploaded 17 Jun 2025Source
- Form 1Form 1 - Q3 Dec 24 (System Generated)-Signed.pdf · uploaded 17 Jun 2025Source
- Form 2Form 2 - Q3 Dec 24 (System Generated) - Signed.pdf · uploaded 17 Jun 2025Source
- Form 3Form 3 Q3 24-25-signed.pdf · uploaded 17 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Booked- Q3 Dec 24.pdf · uploaded 17 Jun 2025Source
- Form 1Form 1 - Q4 Mar 25 (System Generated)-Signed.pdf · uploaded 17 Jun 2025Source
- Form 2Form 2 - Q4 Mar 25 (System Generated).pdf · uploaded 17 Jun 2025Source
- Form 3Form 3 Q4 Mar 25-(System Generated).pdf · uploaded 17 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Booked- Q4 Mar 25.pdf · uploaded 17 Jun 2025Source
- Form 1Form 1 - Q1-Signed.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2 - Q1 - Signed.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q1 23-24-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q1 23-24-signed.pdf · uploaded 23 Jun 2025Source
- Form 1Form 1 - Q2-Signed.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2 - Q2 - Signed.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q2 23-24-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q2 23-24-signed.pdf · uploaded 23 Jun 2025Source
- Form 1Form 1 - Q3-Signed.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2 - Q3 - Signed.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q3 23-24-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q3 23-24-signed.pdf · uploaded 23 Jun 2025Source
- Form 1Form 1 - Q4-Signed.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2 - Q4 - Signed.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q4 23-24-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q4 23-24-signed.pdf · uploaded 23 Jun 2025Source
- Form 1Form 1 - Q1-Signed.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2 - Q1 - Signed.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q1 22-23-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q1 22-23-signed.pdf · uploaded 23 Jun 2025Source
- Form 1Form 1 - Q2-Signed.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2 - Q2 - Signed.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q2 22-23-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q2 22-23-signed.pdf · uploaded 23 Jun 2025Source
- Form 1Form 1 - Q3-Signed.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2 - Q3 - Signed.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q3 22-23-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q3 22-23-signed.pdf · uploaded 23 Jun 2025Source
- Form 1Form 1 - Q4-Signed.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2 - Q4 - Signed.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q4 22-23-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q4 22-23-signed.pdf · uploaded 23 Jun 2025Source
- Form 1Form 1 - Q1-Signed.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2 - Q1 - Signed.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q1 21-22-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q1 21-22-signed.pdf · uploaded 23 Jun 2025Source
- Form 1Form 1 - Q2-Signed.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2 - Q2 - Signed.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q2 21-22-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q2 21-22-signed.pdf · uploaded 23 Jun 2025Source
- Form 1Form 1 - Q3-Signed.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2 - Q3 - Signed.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q3 21-22-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q3 21-22-signed.pdf · uploaded 23 Jun 2025Source
- Form 1Form 1 - Q4-Signed.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2 - Q4 - Signed.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q4 21-22-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q4 21-22-signed.pdf · uploaded 23 Jun 2025Source
- Form 1Sold Book-Q1 19-20-signed.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2- Q4-19-20.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q1 19-20-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q1 19-20-signed.pdf · uploaded 23 Jun 2025Source
- Form 1Form 1- Q1-20-21.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2 - Q1- Signed.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q1 20-21-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q1 20-21-signed.pdf · uploaded 23 Jun 2025Source
- Form 1Form 1- Q2-20-21.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2 - Q2- Signed.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q2 20-21-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q2 20-21-signed.pdf · uploaded 23 Jun 2025Source
- Form 1Form 1- Q3-20-21.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2 - Q3- Signed.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q3 20-21-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q3 20-21-signed.pdf · uploaded 23 Jun 2025Source
- Form 1Form 1- Q4-20-21.pdf · uploaded 23 Jun 2025Source
- Form 2Form 2 - Q4 - Signed.pdf · uploaded 23 Jun 2025Source
- Form 3Form 3 Q4 20-21-signed.pdf · uploaded 23 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Book-Q4 20-21-signed.pdf · uploaded 23 Jun 2025Source
- Withdrawal Update Form 1Skybound Form 1 Q1 25 26.pdf · uploaded 11 Aug 2025Source
- Withdrawal Update Form 1Skybound Form 1 Q1 25 26.pdf · uploaded 11 Aug 2025Source
- Withdrawal Update Form 2Skybound Form 2 Q1 25 26.pdf · uploaded 11 Aug 2025Source
- Withdrawal Update Form 2Skybound Form 2 Q1 25 26.pdf · uploaded 11 Aug 2025Source
- Withdrawal Update Form 3Skybound Form 3 Q1 25 26 Signed.pdf · uploaded 11 Aug 2025Source
- Withdrawal Update Form 3Skybound Form 3 Q1 25 26 Signed.pdf · uploaded 11 Aug 2025Source
- Withdrawal Update Form 1Skybound Form 1 Q1 25 26.pdf · uploaded 12 Aug 2025Source
- Withdrawal Update Form 1Skybound Form 1 Q1 25 26.pdf · uploaded 12 Aug 2025Source
- Withdrawal Update Form 2Skybound Form 2 Q1 25 26.pdf · uploaded 12 Aug 2025Source
- Withdrawal Update Form 2Skybound Form 2 Q1 25 26.pdf · uploaded 12 Aug 2025Source
- Withdrawal Update Form 3Skybound Form 3 Q1 25 26 Signed.pdf · uploaded 12 Aug 2025Source
- Withdrawal Update Form 3Skybound Form 3 Q1 25 26 Signed.pdf · uploaded 12 Aug 2025Source
- Withdrawal Update Form 1Skybound Form 1 Q1 25 26.pdf · uploaded 30 Sep 2025Source
- Withdrawal Update Form 2Skybound Form 2 Q1 25 26.pdf · uploaded 30 Sep 2025Source
- Withdrawal Update Form 3Skybound Form 3 Q1 25 26 Signed.pdf · uploaded 30 Sep 2025Source
- Form 5 (FY 2020-2021)RERA Audit Report_20-21.pdf · uploaded 30 Sep 2025Source
- Form 5 (FY 2021-2022)RERA Audit Report_21-22.pdf · uploaded 30 Sep 2025Source
- Form 5 (FY 2022-2023)RERA Audit Report_22-23.pdf · uploaded 30 Sep 2025Source
- Form 5 (FY 2023-2024)RERA Audit Report_23-24.pdf · uploaded 30 Sep 2025Source
- Form 2A (FY 2019-2020)Form 2A_March 20.pdf · uploaded 8 Oct 2025Source
- Form 2A (FY 2020-2021)Form 2A_March 21.pdf · uploaded 8 Oct 2025Source
- Form 2A (FY 2021-2022)Form 2A_March 22.pdf · uploaded 8 Oct 2025Source
- Form 2A (FY 2022-2023)Form 2A_March 23.pdf · uploaded 8 Oct 2025Source
- Form 2A (FY 2023-2024)Form 2A_March 24.pdf · uploaded 8 Oct 2025Source
- Form 2A (FY 2024-2025)Form 2A_March 25.pdf · uploaded 8 Oct 2025Source
- Withdrawal Update Form 1Architect Certificate Sep 25.pdf · uploaded 3 Dec 2025Source
- Withdrawal Update Form 2Engineer Certificate Sep 25.pdf · uploaded 3 Dec 2025Source
- Withdrawal Update Form 3CA Certificate_Sept 2025.pdf · uploaded 3 Dec 2025Source
- Withdrawal Update Form 1Architect Certificate Dec 25.pdf · uploaded 9 Feb 2026Source
- Withdrawal Update Form 2Engineer Certificate Dec 25.pdf · uploaded 9 Feb 2026Source
- Withdrawal Update Form 3CA Certificate Dec 25.pdf · uploaded 9 Feb 2026Source
- Withdrawal Update Form 1Architect Certificate_Mar 26.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 1Architect Certificate_Mar 26.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 1Architect Certificate_Mar 26.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 1Architect Certificate_Mar 26.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 2Engineer Certificate_Mar 26.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 2Engineer Certificate_Mar 26.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 2Engineer Certificate_Mar 26.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 2Engineer Certificate_Mar 26.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 3CA Certificate_Mar 26.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 3CA Certificate_Mar 26.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 3CA Certificate_Mar 26.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 3CA Certificate_Mar 26.pdf · uploaded 27 May 2026Source
- Withdrawal Update Form 1Form 1_Jun 26.pdf · uploaded 22 Jul 2026Source
- Withdrawal Update Form 2Form 2_Jun 26.pdf · uploaded 22 Jul 2026Source
- Withdrawal Update Form 3CA Certificate_Jun 2026.pdf · uploaded 22 Jul 2026Source
Technical
- DocumentPLAN AND BANDKAM_compressed.pdf · uploaded 6 Feb 2020Source
- DocumentPLAN AND BANDKAM_compressed.pdf · uploaded 6 Feb 2020Source
- DocumentRevised Layout Plan.pdf · uploaded 23 Dec 2025Source
- DocumentRevised Plan-Sheet No 01.pdf · uploaded 23 Dec 2025Source
- DocumentRevised Plan-Sheet No 02.PDF · uploaded 23 Dec 2025Source
- DocumentRevised Plan-Sheet No 03.pdf · uploaded 23 Dec 2025Source
- DocumentRevised Plan-Sheet No 04.pdf · uploaded 23 Dec 2025Source
- DocumentRevised Plan-Sheet No 05.pdf · uploaded 23 Dec 2025Source
- DocumentRevised Plan-Sheet No 06.pdf · uploaded 23 Dec 2025Source
- DocumentRevised Plan-Sheet No 07.pdf · uploaded 23 Dec 2025Source
- DocumentRevised Plan-Sheet No 08.pdf · uploaded 23 Dec 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Survey No 5 Hissa No 1
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Village
- Sonale
- Location
- 19.28982, 73.08344
- Designated bank account
- 82
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Source: registration certificates and MahaRERA's project page, as stated there.