Skip to content
Residential / Group Housing · 2 buildings · 82 unitsRERA PR1330002502502

Trinity Phase 2

Deedo IDDP-THN-H18B

Completion was pushed back 4 months, to Jul 2030; no MahaRERA orders on record; 0% of its units are booked.

Shil, Thane 400612 · by Trinity Builders

DeliveryExtended 4 moPromised Mar 2030 · now due Jul 2030RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 82 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jul 2030

  • This projectRegistered 26 Feb 2026, completion promised 31 Mar 2030, revised to 31 Jul 2030.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPR1330002502502
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR133000250250226 Feb 202631 Mar 203031 Jul 2030Trinity BuildersProject page
Documents45

1 document held by Deedo, 44 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPancard Trinity Builders .pdf · uploaded 3 Jun 2025Source
  • OthersEncumbrance Letter - Finance.pdf · uploaded 6 Jun 2025Source
  • OthersCersai Declaration Phase 2.pdf · uploaded 6 Jun 2025Source
  • OthersDeclaration - Trinity Phase 2.pdf · uploaded 5 Nov 2025Source

Legal

  • Declaration Form BSale Deed S No 29.pdf · uploaded 3 Jun 2025Source
  • Declaration Form BForm B- Affidavit cum Declaration.pdf · uploaded 6 Jun 2025Source
  • OthersEncumbrance Letter-Legal.pdf · uploaded 22 Jul 2025Source
Show all 45 documentsShow fewer documents

Legal

  • OthersForm B -Affidavit cum Declaration.pdf · uploaded 22 Jul 2025Source
  • OthersAnnexure A- Disclosure Mr Sijo.pdf · uploaded 22 Jul 2025Source
  • Othersannexure A disclosure Sunny Sir.pdf · uploaded 22 Jul 2025Source
  • Declaration Form BTitle Report.pdf · uploaded 25 Sep 2025Source

Migrated

  • Withdrawal Update Form 1Form 1 - Trinity Phase 2 as on March 2026.pdf · uploaded 20 May 2026Source
  • Withdrawal Update Form 2Form 2 - Trinity Phase 2.pdf · uploaded 20 May 2026Source
  • Withdrawal Update Form 3Form 3 - Trinity Phase 2 as on 31-03-2026.pdf · uploaded 20 May 2026Source
  • Form 2A (FY 2025-2026)Form 2A Trinity Phase 2 FY 2025-26.pdf · uploaded 1 Jul 2026Source
  • Withdrawal Update Form 1Form 1 - Trinity Phase 2 as on June 2026.pdf · uploaded 17 Jul 2026Source
  • Withdrawal Update Form 2Form 2 - Trinity Phase 2 as on June 2026.pdf · uploaded 17 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - Trinity Phase 2 as on June 2026.pdf · uploaded 17 Jul 2026Source
  • Form 5 (FY 2025-2026)Form 5 Trinity Phase 2 FY 2025-26.pdf · uploaded 29 Sep 2026Source

Technical

  • DocumentCommencement Certificate A4 & A5.PDF · uploaded 3 Jun 2025Source
  • DocumentSheet 1 of 12.pdf · uploaded 3 Jun 2025Source
  • DocumentSheet 2 of 12.pdf · uploaded 3 Jun 2025Source
  • DocumentSheet 3 of 12.pdf · uploaded 3 Jun 2025Source
  • DocumentSheet 4 of 12.pdf · uploaded 3 Jun 2025Source
  • DocumentSheet 5 of 12.pdf · uploaded 3 Jun 2025Source
  • DocumentSheet 6 of 12.pdf · uploaded 3 Jun 2025Source
  • DocumentSheet 7 of 12.pdf · uploaded 3 Jun 2025Source
  • DocumentSheet 8 of 12.pdf · uploaded 3 Jun 2025Source
  • DocumentSheet 9 of 12.pdf · uploaded 3 Jun 2025Source
  • DocumentSheet 10 of 12.pdf · uploaded 3 Jun 2025Source
  • DocumentSheet 11 of 12.pdf · uploaded 3 Jun 2025Source
  • DocumentSheet 12 of 12.pdf · uploaded 3 Jun 2025Source
  • OthersAnnexure A- Disclosure Mr Sijo.pdf · uploaded 3 Jun 2025Source
  • Othersannexure A disclosure Sunny Sir.pdf · uploaded 3 Jun 2025Source
  • OthersFORM 2.pdf · uploaded 3 Jun 2025Source
  • OthersEmail to RERA.pdf · uploaded 5 Jun 2025Source
  • OthersCC Declaration.pdf · uploaded 6 Jun 2025Source
  • DocumentAnnexure A.pdf · uploaded 14 Oct 2025Source
  • OthersForm 2 Trinity Phase 2 New.pdf · uploaded 3 Dec 2025Source
  • OthersForm 1 Trinity Phase 2.pdf · uploaded 28 Jan 2026Source
  • OthersEmail to RERA NEW.pdf · uploaded 28 Jan 2026Source
  • OthersEmail to RERA New.pdf · uploaded 10 Feb 2026Source

Technical (Architect)

  • DocumentForm 1 - Trinity Phase 2 as on June 2026.pdf · uploaded 17 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2 - Trinity Phase 2 as on June 2026.pdf · uploaded 17 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 37/2 Sector 11, Survey No 29

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—82 units in all
Address
Shill ThanePIN 400612
Village
Shil, Thane taluka
Land area for this project
5,560 sq m (59,847 sq ft)
Approved layout area
20,460 sq m (2,20,229 sq ft)
Permissible built-up area
28,568 sq m (3,07,500 sq ft)
Sanctioned built-up area
6,806 sq m (73,256 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
179
Developed in phases
Yes

Survey, CTS, gat or plot numbers

37/2 Sector 11Survey No 29

Land as published on MahaRERA's project page

Survey No 29 & 37/2 Sector 11 Village Shill

Boundaries

North
Survey No 30
South
60-meter-wide D.P. Road
East
Survey No 27
West
Survey No 36

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking82 units

82 units registered

— · 82 units
BuildingTypeCarpet areaUnits
Building A4——41
Building A5——41

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSameer S Lotke and Associates Lotke—
Chartered accountantParth Gada—
Chartered accountantPeenaz Jokhi—
EngineerBhagwan Bagwe—
EngineerSscons—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Shil