Kshipra
Deedo IDDP-THN-FKMCMahaRERA shows it completed; no MahaRERA orders on record; 100% of its units are booked.
Sanpada, Thane 400705 · by Sara Realty
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 22 Jan 2018, completion promised 30 Dec 2022.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700015011
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700015011 | 22 Jan 2018 | 30 Dec 2022 | 30 Dec 2022 | Sara Realty | Project page |
Documents62
2 documents held by Deedo, 60 filings listed on MahaRERA's project page
Show all 62 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)Sara.pdf · uploaded 15 Jan 2018Source
- 1 Building Plan Approval (IOD)Commencement Certificate.pdf · uploaded 15 Jan 2018Source
- 1 Declaration in FORM BForm B.pdf · uploaded 15 Jan 2018Source
- 1 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 15 Jan 2018Source
- 1 Proforma of Allotment letterSale Agreement.pdf · uploaded 15 Jan 2018Source
- 1 Commencement Certificates / NA Order for plotted developmentKshipra CC.pdf · uploaded 21 Apr 2018Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Kshipra ARC Certificate.pdf · uploaded 21 Apr 2018Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect certificate 130718 compressed.pdf · uploaded 21 Jul 2018Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Sara Eng Cert 250418.pdf · uploaded 21 Jul 2018Source
- 2 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 21 Jul 2018Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Eng Certificate 140718.PDF · uploaded 8 Aug 2018Source
- 3 Certificates of CA (Form 3)Certificate_Form 3_Sara_140718.pdf · uploaded 8 Aug 2018Source
- 1 Certificates of CA (Form 5)Form 5.pdf · uploaded 15 Oct 2018Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect certiicate 021118.pdf · uploaded 2 Nov 2018Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect certiicate 021118.pdf · uploaded 11 Jan 2019Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 SARA.pdf · uploaded 11 Jan 2019Source
- 4 Certificates of CA (Form 3)Form 3 Rera certificate.pdf · uploaded 11 Jan 2019Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate compressed.pdf · uploaded 11 Mar 2019Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Eng Certificate.pdf · uploaded 11 Mar 2019Source
- 5 Certificates of CA (Form 3)Form 3.pdf · uploaded 22 Apr 2019Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Architect certifictae.pdf · uploaded 23 May 2019Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Certificate.pdf · uploaded 23 May 2019Source
- 6 Certificates of CA (Form 3)C A CERTIFICATE.PDF · uploaded 13 Jul 2019Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate 310719.pdf · uploaded 17 Aug 2019Source
- 7 Certificates of CA (Form 3)Form 3.pdf · uploaded 27 Sep 2019Source
- 2 Certificates of CA (Form 5)Sara Realty Form 5 1819.pdf · uploaded 30 Sep 2019Source
- 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Kshipra Eng Certificate 251019.pdf · uploaded 21 Dec 2019Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 250120_compressed.pdf · uploaded 24 Aug 2020Source
- 8 Certificates of CA (Form 3)Form 3 SARA KSHIPRA 251019.pdf · uploaded 25 Nov 2020Source
- 9 Certificates of CA (Form 3)Form 3 SARA Realty.pdf · uploaded 25 Nov 2020Source
- 10 Certificates of CA (Form 3)Form 3 SARA Realty.pdf · uploaded 25 Nov 2020Source
- 3 Certificates of CA (Form 5)Form5 SARA KSHIPRA.pdf · uploaded 25 Nov 2020Source
- 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 250420 Architechs Certificate_compressed.pdf · uploaded 27 Nov 2020Source
- 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Architech Certificate 250720_compressed.pdf · uploaded 27 Nov 2020Source
- 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 02 Engineer Certificate 250420_compressed.pdf · uploaded 28 Nov 2020Source
- 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 02 Engineer Certificate 250720_compressed.pdf · uploaded 28 Nov 2020Source
- 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 01 25102020(Architect Certificate)_compressed.pdf · uploaded 27 Feb 2021Source
- 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 01 25012021(Architect Certificate)_compressed.pdf · uploaded 27 Feb 2021Source
- 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form No 02 Engineer Certificate 25102020.pdf · uploaded 27 Feb 2021Source
- 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form No 02 Engineer Certificate 25012021.pdf · uploaded 27 Feb 2021Source
- 1 Disclosure of sold/ booked inventorysold unsold inventory SARA_compressed.pdf · uploaded 27 May 2021View
- 11 Certificates of CA (Form 3)Form-3_Cert_25_25102020_compressed_compressed.pdf · uploaded 27 May 2021Source
- 12 Certificates of CA (Form 3)Form-3_Cert_26_25012021_compressed_compressed.pdf · uploaded 27 May 2021Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Formation Letter.pdf · uploaded 21 Jul 2021Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentKSHIPRA_Occupancy Certificate.pdf · uploaded 7 Jan 2022Source
- 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4 Work Completion Certificate.pdf · uploaded 11 Mar 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form-5 as on 31-03-2019.pdf · uploaded 31 Mar 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)SCAN_SIGNED_FORM-5 (FY 2020-21).pdf · uploaded 31 Mar 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)SCAN_SIGNED_FORM-5 (FY 2021-22).pdf · uploaded 31 Mar 2023Source
- 1 Certificates of CA (Form 3)Kshipra - Form 3 - Final.pdf · uploaded 30 Jan 2025Source
Technical
Technical (Architect)
- DocumentForm 01 25012021(Architect Certificate)_compressed.pdf · uploaded 27 Feb 2021Source
Technical (Engineer)
- DocumentForm No 02 Engineer Certificate 25012021.pdf · uploaded 27 Feb 2021Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 16
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1 BHK, 1BHK, 2 BHK, Shops90 units in all
- Address
- 16, Plot No 16 Sector 8, SanpadaPIN 400705
- Village
- Navi Mumbai (M Corp.), Thane taluka
- Location
- 19.05747, 73.01101
- Land area for this project
- 2,560 sq m (27,554 sq ft)
- Permissible built-up area
- 3,837 sq m (41,305 sq ft)
- Sanctioned built-up area
- 3,837 sq m (41,305 sq ft)
- Recreational open space
- 2,560 sq m (27,554 sq ft)
- Designated bank account
- 154
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
16
Boundaries
- North
- Plot No 17
- South
- Plot No 15
- East
- Plot No 12
- West
- 15 Mtr Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking90 units
90 of 90 units booked (100%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 29.12 sq m · 313 sq ft | 10 | 10 |
| 1BHK | 26.29 sq m · 283 sq ft | 10 | 10 |
| 2 BHK | 40.49 sq m · 436 sq ft | 30 | 30 |
| 2 BHK | 45.24 sq m · 487 sq ft | 30 | 30 |
| Shops | 35.98 sq m · 387 sq ft | 8 | 8 |
| Shops | 36.04 sq m · 388 sq ft | 2 | 2 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Rajesh R C | — |
| Engineer | Rajesh Shah | — |
| Other | Marvellous Constructions | — |
Source: MahaRERA project page. Contact details are not shown.