Sara Realty

Company or firm · 3 projects · 3 MahaRERA registrations

Also appears as M/S Sara Realty

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
KshipraP51700015011Navi Mumbai (M Corp.)2018Certificate Signed30 Dec 202230 Dec 2022On date
UnioneP51900028411Mumbai City2021Certificate Signed30 Jun 202530 Jun 2025On date
AntalyaP51700046637Navi Mumbai (M Corp.)2022Certificate Signed30 Jun 202730 Oct 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • KshipraOn date
  • UnioneOn date
  • Antalya+4 mo

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Antalya (P51700046637).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology