Completion was pushed back 4 months, to Jul 2027; no MahaRERA orders on record; 63% of its units are booked.

Sanpada, Thane 400705 · by Kamdhenu Lifespaces

DeliveryExtended 4 moPromised Mar 2027 · now due Jul 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales63% booked82 of 131 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jul 2027

  • This projectRegistered 10 May 2022, completion promised 31 Mar 2027, revised to 31 Jul 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700035135
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170003513510 May 202231 Mar 202731 Jul 2027M/S Kamdhenu LifespacesProject page
Documents154

2 documents held by Deedo, 152 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardLifespaces Pan Card.pdf · uploaded 29 Apr 2022Source
  • Other – FinanceReceipt(pavti).pdf · uploaded 15 Oct 2022Source

Legal

  • OtherDeclaration For Phase 2.pdf · uploaded 29 Apr 2022Source
  • OtherFire NOC.pdf · uploaded 29 Apr 2022Source
  • OtherEC SEIAA_SIA_MH_MIS_239721_2021.pdf · uploaded 29 Apr 2022Source
  • Legal Title reportTitle Certificate.pdf · uploaded 29 Apr 2022Source
Show all 154 documentsShow fewer documents

Legal

  • Declaration Form BForm B Affidavit.pdf · uploaded 29 Apr 2022Source
  • OtherBAnm Certificate.pdf · uploaded 6 May 2022Source
  • Legal Title reportUpdated Legal Title Report.pdf · uploaded 15 Oct 2022Source

Migrated

  • 1 PAN CardLifespaces Pan Card.pdf · uploaded 29 Apr 2022Source
  • 1 Copy of the legal title reportTitle Certificate.pdf · uploaded 29 Apr 2022Source
  • 1 Details of encumbrancesEncumbrances Cert.pdf · uploaded 29 Apr 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 29 Apr 2022Source
  • 1 Declaration in FORM BForm B Affidavit.pdf · uploaded 29 Apr 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Certificate.pdf · uploaded 29 Apr 2022Source
  • 1 CERSAI detailsEncumbrances Cert.pdf · uploaded 29 Apr 2022Source
  • 1 Proforma of Allotment letterAFS-Kamdhenu- Lifespace.pdf · uploaded 29 Apr 2022Source
  • 1 OtherDeclaration For Phase 2.pdf · uploaded 29 Apr 2022Source
  • 2 OtherFire NOC.pdf · uploaded 29 Apr 2022Source
  • 3 OtherEC SEIAA_SIA_MH_MIS_239721_2021.pdf · uploaded 29 Apr 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 30 Apr 2022Source
  • 2 Proforma of Allotment letterAllotment Letter.pdf · uploaded 30 Apr 2022Source
  • 1 Copy of Layout Approval (in case of layout)01_11zon.pdf · uploaded 3 May 2022Source
  • 2 Copy of Layout Approval (in case of layout)02.pdf · uploaded 3 May 2022Source
  • 3 Copy of Layout Approval (in case of layout)03.pdf · uploaded 3 May 2022Source
  • 4 Copy of Layout Approval (in case of layout)04.pdf · uploaded 3 May 2022Source
  • 5 Copy of Layout Approval (in case of layout)05.pdf · uploaded 3 May 2022Source
  • 6 Copy of Layout Approval (in case of layout)06.pdf · uploaded 3 May 2022Source
  • 1 Building Plan Approval / NA Order for plotted development01_11zon.pdf · uploaded 3 May 2022Source
  • 2 Building Plan Approval / NA Order for plotted development02.pdf · uploaded 3 May 2022Source
  • 3 Building Plan Approval / NA Order for plotted development03.pdf · uploaded 3 May 2022Source
  • 4 Building Plan Approval / NA Order for plotted development04.pdf · uploaded 3 May 2022Source
  • 5 Building Plan Approval / NA Order for plotted development05.pdf · uploaded 3 May 2022Source
  • 6 Building Plan Approval / NA Order for plotted development06.pdf · uploaded 3 May 2022Source
  • 1 Declaration about Commencement CertificateForm D.pdf · uploaded 6 May 2022Source
  • 2 CERSAI detailsCERSAI_Search_Report_200236725131_For_Asset_Based_Search_06_05_2022_11_34_32_490.pdf · uploaded 6 May 2022Source
  • 4 OtherBAnm Certificate.pdf · uploaded 6 May 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Arch Certificate.pdf · uploaded 23 Jun 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Certificate Form 1.pdf · uploaded 20 Jul 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Certificate (2).pdf · uploaded 20 Jul 2022Source
  • 1 Disclosure of sold/ booked inventorySold Inventory.pdf · uploaded 20 Jul 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Form 3.pdf · uploaded 20 Jul 2022Source
  • 2 Copy of the legal title reportUpdated Legal Title Report.pdf · uploaded 15 Oct 2022Source
  • 1 b Details of encumbrances concerned to Legal1B.pdf · uploaded 15 Oct 2022Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Certificate.pdf · uploaded 15 Oct 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Certificate.pdf · uploaded 15 Oct 2022Source
  • 1 Other – FinanceReceipt(pavti).pdf · uploaded 15 Oct 2022Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Cert.pdf · uploaded 19 Oct 2022Source
  • 3 Proforma of Allotment letterDraft AFS.pdf · uploaded 19 Oct 2022Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 (From Architect).pdf · uploaded 14 Jan 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Certificate.pdf · uploaded 14 Jan 2023Source
  • 2 Disclosure of sold/ booked inventorySold Inventory (2).pdf · uploaded 14 Jan 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 19 Jan 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Vogue CA Certificate Form3_Dec22.pdf · uploaded 25 Jan 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Jan'23 to Mar'23.pdf · uploaded 12 Apr 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate_Mar 23.pdf · uploaded 12 Apr 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 14 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A.pdf · uploaded 22 Apr 2023Source
  • 3 Disclosure of sold/ booked inventorySold Unsold Unit.pdf · uploaded 22 Apr 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 (Chartered Accountant).pdf · uploaded 14 Jun 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)05-FORM 1 (From Architect)_April'23 to June'23 (1).pdf · uploaded 19 Jul 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 19 Jul 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form - 3 ( CA Certificate).pdf · uploaded 19 Jul 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form - 2 (Engineer's Certificate).pdf · uploaded 28 Jul 2023Source
  • 7 Building Plan Approval / NA Order for plotted developmentNEW CC PLANS UPTO 30TH FLOOR-1.pdf · uploaded 12 Aug 2023Source
  • 8 Building Plan Approval / NA Order for plotted developmentNEW CC PLANS UPTO 30TH FLOOR-2.pdf · uploaded 12 Aug 2023Source
  • 9 Building Plan Approval / NA Order for plotted developmentNEW CC PLANS UPTO 30TH FLOOR-3.pdf · uploaded 12 Aug 2023Source
  • 10 Building Plan Approval / NA Order for plotted developmentNEW CC PLANS UPTO 30TH FLOOR-4.pdf · uploaded 12 Aug 2023Source
  • 11 Building Plan Approval / NA Order for plotted developmentNEW CC PLANS UPTO 30TH FLOOR-5.pdf · uploaded 12 Aug 2023Source
  • 12 Building Plan Approval / NA Order for plotted developmentNEW CC PLANS UPTO 30TH FLOOR-6.pdf · uploaded 12 Aug 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentNEW UPDATED CC UPTO 30TH FLOOR.pdf · uploaded 12 Aug 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCH CERTIFICATE.pdf · uploaded 12 Aug 2023Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG CERIFICATE FORM 2.pdf · uploaded 12 Aug 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Form-3.pdf · uploaded 20 Aug 2023Source
  • 1 Proforma of Agreement for saleNew Draft of AFS.pdf · uploaded 20 Aug 2023Source
  • 4 Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 21 Sep 2023Source
  • 7 Copy of Layout Approval (in case of layout)Plans 1-2.pdf · uploaded 12 Oct 2023Source
  • 13 Building Plan Approval / NA Order for plotted developmentPlans 1-2.pdf · uploaded 12 Oct 2023Source
  • 14 Building Plan Approval / NA Order for plotted developmentPlans 3-4.pdf · uploaded 12 Oct 2023Source
  • 15 Building Plan Approval / NA Order for plotted developmentPlans 5-6.pdf · uploaded 12 Oct 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 12 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 12 Oct 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 27 Oct 2023Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 27 Oct 2023Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 27 Oct 2023Source
  • 16 Building Plan Approval / NA Order for plotted developmentFINAL CC PLANS UPTO 36TH FLOOR 1.pdf · uploaded 30 Dec 2023Source
  • 17 Building Plan Approval / NA Order for plotted developmentFINAL CC PLANS UPTO 36TH FLOOR 2.pdf · uploaded 30 Dec 2023Source
  • 18 Building Plan Approval / NA Order for plotted developmentFINAL CC PLANS UPTO 36TH FLOOR 3.pdf · uploaded 30 Dec 2023Source
  • 19 Building Plan Approval / NA Order for plotted developmentFINAL CC PLANS UPTO 36TH FLOOR 4.pdf · uploaded 30 Dec 2023Source
  • 20 Building Plan Approval / NA Order for plotted developmentFINAL CC PLANS UPTO 36TH FLOOR 5.pdf · uploaded 30 Dec 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 30 Dec 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form - 1_compressed.pdf · uploaded 8 Jan 2024Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 8 Jan 2024Source
  • 5 Disclosure of sold/ booked inventorySOLD UNSOLD_compressed.pdf · uploaded 8 Jan 2024Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form - 3_compressed (1).pdf · uploaded 8 Jan 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)08-Form1 (From Architect).pdf · uploaded 15 Apr 2024Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 vogue_0001.pdf · uploaded 20 May 2024Source
  • 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form - 3_compressed.pdf · uploaded 20 May 2024Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)From 1.pdf · uploaded 27 Jul 2024Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 27 Jul 2024Source
  • 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 27 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)10 Form 1 (From Architect).pdf · uploaded 12 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 sept.pdf · uploaded 12 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 KL VOGUE SEPT_0001 (2).pdf · uploaded 12 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1.pdf · uploaded 27 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 (4).pdf · uploaded 27 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 (3).pdf · uploaded 27 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Scan_0142.pdf · uploaded 8 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)F 1 Kamdhenu Vogue.pdf · uploaded 3 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Kamdhenu Vogue Form 2.pdf · uploaded 3 May 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)V F 2A Quality Assuarance.pdf · uploaded 3 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 KAMDHENU VOGUE March 2025_compressed.pdf · uploaded 13 May 2025Source
  • Form 112-FORM 1 (From Architect)_Kamdhenu Vogue_Dt.pdf · uploaded 2 Feb 2026Source
  • Form 2FORM 2 VOGUE 15042025.pdf · uploaded 2 Feb 2026Source
  • Form 3FORM 3 KAMDHENU VOGUE 31032025.pdf · uploaded 2 Feb 2026Source
  • Disclosure of Sold and Booked InventorySoldUnsold Vogue.pdf · uploaded 2 Feb 2026View
  • OthersKamdhenu Vogue OC Plans Verification.pdf · uploaded 2 Feb 2026Source

Technical

  • Document01_11zon.pdf · uploaded 3 May 2022Source
  • Document02.pdf · uploaded 3 May 2022Source
  • Document03.pdf · uploaded 3 May 2022Source
  • Document04.pdf · uploaded 3 May 2022Source
  • Document05.pdf · uploaded 3 May 2022Source
  • Document06.pdf · uploaded 3 May 2022Source
  • Document01_11zon.pdf · uploaded 3 May 2022Source
  • Document02.pdf · uploaded 3 May 2022Source
  • Document03.pdf · uploaded 3 May 2022Source
  • Document04.pdf · uploaded 3 May 2022Source
  • Document05.pdf · uploaded 3 May 2022Source
  • Document06.pdf · uploaded 3 May 2022Source
  • DocumentNEW CC PLANS UPTO 30TH FLOOR-1.pdf · uploaded 12 Aug 2023Source
  • DocumentNEW CC PLANS UPTO 30TH FLOOR-2.pdf · uploaded 12 Aug 2023Source
  • DocumentNEW CC PLANS UPTO 30TH FLOOR-3.pdf · uploaded 12 Aug 2023Source
  • DocumentNEW CC PLANS UPTO 30TH FLOOR-4.pdf · uploaded 12 Aug 2023Source
  • DocumentNEW CC PLANS UPTO 30TH FLOOR-5.pdf · uploaded 12 Aug 2023Source
  • DocumentNEW CC PLANS UPTO 30TH FLOOR-6.pdf · uploaded 12 Aug 2023Source
  • DocumentPlans 1-2.pdf · uploaded 12 Oct 2023Source
  • DocumentPlans 1-2.pdf · uploaded 12 Oct 2023Source
  • DocumentPlans 3-4.pdf · uploaded 12 Oct 2023Source
  • DocumentPlans 5-6.pdf · uploaded 12 Oct 2023Source
  • DocumentFINAL CC PLANS UPTO 36TH FLOOR 1.pdf · uploaded 30 Dec 2023Source
  • DocumentFINAL CC PLANS UPTO 36TH FLOOR 2.pdf · uploaded 30 Dec 2023Source
  • DocumentFINAL CC PLANS UPTO 36TH FLOOR 3.pdf · uploaded 30 Dec 2023Source
  • DocumentFINAL CC PLANS UPTO 36TH FLOOR 4.pdf · uploaded 30 Dec 2023Source
  • DocumentFINAL CC PLANS UPTO 36TH FLOOR 5.pdf · uploaded 30 Dec 2023Source

Technical (Architect)

  • DocumentFrom 1.pdf · uploaded 27 Jul 2024Source
  • Document10 Form 1 (From Architect).pdf · uploaded 12 Nov 2024Source
  • DocumentForm1.pdf · uploaded 27 Jan 2025Source
  • DocumentF 1 Kamdhenu Vogue.pdf · uploaded 3 May 2025Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 27 Jul 2024Source
  • Documentform 2 KL VOGUE SEPT_0001 (2).pdf · uploaded 12 Nov 2024Source
  • Documentform 2 (3).pdf · uploaded 27 Jan 2025Source
  • DocumentKamdhenu Vogue Form 2.pdf · uploaded 3 May 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 20 plus 21

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK, Office space131 units in all
Address
20 plus 21, Sector 08, SanpadaPIN 400705
Village
Navi Mumbai (M Corp.), Thane taluka
Land area for this project
3,000 sq m (32,294 sq ft)
Permissible built-up area
14,476 sq m (1,55,815 sq ft)
Sanctioned built-up area
14,471 sq m (1,55,767 sq ft)
Recreational open space
1,098 sq m (11,822 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

20 plus 21

Land as published on MahaRERA's project page

20 plus 21

Boundaries

North
Plot no 22 plus 23
South
15 Mtr wide road
East
Plot no 19U
West
Prop 15 Mtr wide road - Existing 11 Mtr wide road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking131 units

82 of 131 units booked (63%), as the promoter reported to MahaRERA

2BHK · 60 units3BHK · 59 unitsOffice space · 12 units
TypeCarpet areaUnitsBooked
2BHK64.48 sq m · 694 sq ft6042
3BHK91.09 sq m · 980 sq ft5940
Office space24.08 sq m · 259 sq ft20
Office space26.19 sq m · 282 sq ft20
Office space28.94 sq m · 312 sq ft20
Office space35.09 sq m · 378 sq ft20
Office space36.85 sq m · 397 sq ft20
Office space42.08 sq m · 453 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Other projects in Sanpada

All 11 projects in Sanpada · Compare Kamdhenu Vogue with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology