Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.

Sai, Thane 421501 · by Shivam Construction Co

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 30 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 22 Dec 2022, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700048248
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170004824822 Dec 202231 Dec 202630 Apr 2027Shivam Construction CoProject page
Documents41

1 document held by Deedo, 40 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardshivam constructions scanned copy.pdf · uploaded 16 Oct 2022Source

Legal

  • Legal Title reportLegal Report.pdf · uploaded 9 Nov 2022Source
  • Declaration Form BForm B.pdf · uploaded 9 Nov 2022Source

Migrated

  • 1 PAN Cardshivam constructions scanned copy.pdf · uploaded 16 Oct 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentmarathi com shivam.pdf · uploaded 16 Oct 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentmarathi com shivam.pdf · uploaded 16 Oct 2022Source
  • 1 CERSAI detailscersai shivam.pdf · uploaded 16 Oct 2022Source
Show all 41 documentsShow fewer documents

Migrated

  • 1 Proforma of Allotment lettershivam allotment.pdf · uploaded 16 Oct 2022Source
  • 1 Deviation Report with respect to Allotment lettershivam deviation allotment.pdf · uploaded 16 Oct 2022Source
  • 1 Deviation Report with respect to model copy of Agreementdeviation shivam agreement.pdf · uploaded 16 Oct 2022Source
  • 1 Copy of the legal title reportLegal Report.pdf · uploaded 9 Nov 2022Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 9 Nov 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT’S CERTIFICATE.pdf · uploaded 9 Nov 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate.pdf · uploaded 9 Nov 2022Source
  • 1 Proforma of Agreement for saleAgreement for sale.pdf · uploaded 9 Nov 2022Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrances Legal.pdf · uploaded 10 Nov 2022Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrances.pdf · uploaded 10 Nov 2022Source
  • 1 b Details of encumbrances concerned to LegalEncumbrances Legal.pdf · uploaded 10 Nov 2022Source
  • 2 b Details of encumbrances concerned to LegalEncumbrances.pdf · uploaded 10 Nov 2022Source
  • 1 Declaration about Commencement CertificateDeclaration About Commencment Certificate.pdf · uploaded 10 Nov 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDECLARATION OF SEPARATE BANK ACCOUNT.pdf · uploaded 10 Nov 2022Source
  • 1 Copy of Layout Approval (in case of layout)layout plan.pdf · uploaded 29 Nov 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)SHIVAM3.pdf · uploaded 12 Dec 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE (2) ELENZZ.pdf · uploaded 2 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FROM 05ANNUAL REPORT.pdf · uploaded 2 Nov 2023Source
  • Form 2A (FY 2022-2023)Form 2A - 2022-23.pdf · uploaded 16 Sep 2025Source
  • Form 2A (FY 2023-2024)FORM 2A (2023-24).pdf · uploaded 16 Sep 2025Source
  • Form 2A (FY 2024-2025)FORM 2A (2024-25).pdf · uploaded 16 Sep 2025Source
  • Form 5 (FY 2022-2023)form 5 - 2022-23.pdf · uploaded 16 Sep 2025Source
  • Form 5 (FY 2023-2024)FORM 5 2023-2024.pdf · uploaded 16 Sep 2025Source
  • Form 5 (FY 2024-2025)Form 5 2024-2025.pdf · uploaded 16 Sep 2025Source
  • Form 1FORM 1 - 30-06-2025.pdf · uploaded 25 Sep 2025Source
  • Form 2FORM 2 - 30-06-2025.pdf · uploaded 25 Sep 2025Source
  • Form 3FORM 3 - 30-06-2025.pdf · uploaded 25 Sep 2025Source
  • Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLD - UNSOLD INVENTORY - 30-06-2025.pdf · uploaded 25 Sep 2025Source

Technical

  • Documentmarathi com shivam.pdf · uploaded 16 Oct 2022Source
  • Documentlayout plan.pdf · uploaded 29 Nov 2022Source
  • Documentupdated plan.pdf · uploaded 27 Sep 2025Source

Technical (Architect)

  • DocumentARCHITECT CERTIFICATE (2) ELENZZ.pdf · uploaded 2 Nov 2023Source

Technical (Engineer)

  • DocumentEngineers Certificate.pdf · uploaded 9 Nov 2022Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel CTS NO 7315

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK30 units in all
Address
CTS NO 7315, Sai Section, AmbernathPIN 421501
Village
Sai, Ambarnath taluka
Land area for this project
536 sq m (5,772 sq ft)
Permissible built-up area
1,451 sq m (15,622 sq ft)
Sanctioned built-up area
1,451 sq m (15,622 sq ft)
Designated bank account
220
Developed in phases
No

Survey, CTS, gat or plot numbers

CTS NO 7315

Land as published on MahaRERA's project page

CTS NO 7315

Boundaries

North
Road
South
Road
East
Road
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking30 units

0 of 30 units booked (0%), as the promoter reported to MahaRERA

2BHK · 30 units
TypeCarpet areaUnitsBooked
2BHK36.2 sq m · 390 sq ft20
2BHK43.19 sq m · 465 sq ft280

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectJoglekar Associates—
Chartered accountantMala S Rajpal & CO—
EngineerPradeep Dubey—
EngineerRaj Consultants—

Source: MahaRERA project page. Contact details are not shown.