JVMs Equinox
Deedo IDDP-THN-JFRBCompletion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 5% of its units are booked.
Panchpakhadi, Thane 400604 · by Jvm Realty
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 11 Aug 2025, completion promised 31 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPC1330002500538
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PC1330002500538 | 11 Aug 2025 | 31 Dec 2028 | 30 Apr 2029 | JVM Realty | Project page |
Documents32
1 document held by Deedo, 31 filings listed on MahaRERA's project page
Finance
- PAN CardJVM Realty Pan Card.pdf · uploaded 3 Jul 2025Source
Legal
Show all 32 documentsShow fewer documents
Migrated
- Withdrawal Update Form 1Form 1 - JVMs Equinox as on March 2026.pdf · uploaded 14 May 2026Source
- Withdrawal Update Form 2Form 2 - JVMS Equinox as on Sept 2025.pdf · uploaded 14 May 2026Source
- Withdrawal Update Form 2Form 2 - JVMs Equinox as on Dec 2025.pdf · uploaded 14 May 2026Source
- Withdrawal Update Form 2Form 2 - JVMs Equinox as on March 2026.pdf · uploaded 14 May 2026Source
- Withdrawal Update Form 3Form 3 - JVMs EquinoX as on Sep 2025 (revised).pdf · uploaded 14 May 2026Source
- Withdrawal Update Form 3Form 3 - JVMs Equinox as on Dec 2025.pdf · uploaded 14 May 2026Source
- Withdrawal Update Form 3Form 3 - JVMs EquinoX as on 31-03-2026.pdf · uploaded 14 May 2026Source
- Withdrawal Update Form 1Jvms_Equinox_Form1_Q1_2026-27_21-07-2026_11-43.pdf · uploaded 21 Jul 2026Source
- Withdrawal Update Form 2Jvms_Equinox_Form2_Q1_2026-27_21-07-2026_11-43.pdf · uploaded 21 Jul 2026Source
- Withdrawal Update Form 3Jvms_Equinox_Form3_Q1_2026-27_20-07-2026_12-24_doc1.pdf · uploaded 21 Jul 2026Source
- Withdrawal Update Form 1Jvms_Equinox_Form1_Q1_2026-27_21-07-2026_11-43.pdf · uploaded 31 Aug 2026Source
- Withdrawal Update Form 2Jvms_Equinox_Form2_Q1_2026-27_21-07-2026_11-43.pdf · uploaded 31 Aug 2026Source
- Withdrawal Update Form 3Jvms_Equinox_Form3_Q1_2026-27_20-07-2026_12-24_doc1.pdf · uploaded 31 Aug 2026Source
- Withdrawal Update Form 1Jvms_Equinox_Form1_Q1_2026-27_21-07-2026_11-43.pdf · uploaded 10 Sep 2026Source
- Withdrawal Update Form 2Jvms_Equinox_Form2_Q1_2026-27_21-07-2026_11-43.pdf · uploaded 10 Sep 2026Source
- Withdrawal Update Form 3Jvms_Equinox_Form3_Q1_2026-27_20-07-2026_12-24_doc1.pdf · uploaded 10 Sep 2026Source
Technical
- DocumentLayout approval.pdf · uploaded 18 Jul 2025Source
- DocumentBuilding Plan Approval - 2.pdf · uploaded 18 Jul 2025Source
- DocumentBuilding Plan Approval - 3.pdf · uploaded 18 Jul 2025Source
- DocumentBuilding plan approval - 4.pdf · uploaded 18 Jul 2025Source
- OthersCC Verification (15).pdf · uploaded 22 Jul 2025Source
- DocumentOrder No 50.pdf · uploaded 28 Jul 2025Source
Technical (Architect)
- DocumentJvms_Equinox_Form1_Q1_2026-27_21-07-2026_11-43.pdf · uploaded 21 Jul 2026Source
Technical (Engineer)
- DocumentJvms_Equinox_Form2_Q1_2026-27_21-07-2026_11-43.pdf · uploaded 21 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Plot No A-289
As registered with MahaRERA and published on its project page
- Project type
- Commercial
- Status on MahaRERA
- Certificate Signed
- Unit types
- —137 units in all
- Address
- Wagle Industrial Area, PanchpakhadiPIN 400604
- Village
- Thane (M Corp.), Thane taluka
- Location
- 19.20146, 72.95377
- Land area for this project
- 1,431 sq m (15,403 sq ft)
- Permissible built-up area
- 9,639 sq m (1,03,748 sq ft)
- Sanctioned built-up area
- 8,639 sq m (92,984 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 17
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Plot No A-289
Boundaries
- North
- Plot No A-290
- South
- Plot No A-288
- East
- Plot No A-290
- West
- By Estate Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking137 units
137 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 137 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Dhruv Patel | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Panchpakhadi
- Milind MeeraRERA PM1330002602759
- Prayagtirth Co-operative Housing Society Ltd.RERA PM1330002602751
- Gurukul B Division CHSLRERA PM1330002602669
- Victoria OneRERA PC1330002602685
- Shree Pimpleshwar Mahadev CHSLRERA PM1330002602583
- Varsha Co-operative Housing Society LimitedRERA PR1330002602241
- Om Vaastu Sarika Co-Operative Housing Society LtdRERA PR1330002602166
- Nav Sulochana Co-Operative Housing Society LimitedRERA PR1330002601724
All 65 projects in Panchpakhadi · Compare JVMs Equinox with another project