Deedo IDDP-THN-X4HTCompletion was pushed back 4 months, to Apr 2032; no MahaRERA orders on record; 15% of its units are booked.
Nerul, Thane 400706 · by Paradise InfraCon Pvt Ltd
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2032
- This projectRegistered 26 May 2026, completion promised 30 Dec 2031, revised to 30 Apr 2032.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPR1330002600547
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PR1330002600547 | 26 May 2026 | 30 Dec 2031 | 30 Apr 2032 | Paradise Infracon Private Limited | Project page |
Documents61
1 document held by Deedo, 60 filings listed on MahaRERA's project page
Finance
- PAN CardPICPL.pdf · uploaded 17 Mar 2026Source
- GSTIN DocumentGST Paradise Infracon Pvt Ltd.pdf · uploaded 1 Apr 2026Source
- OthersDeclaration for Costing.pdf · uploaded 3 Apr 2026Source
- Others1705 Index II.pdf · uploaded 16 Apr 2026Source
- OthersMSEDCL Bill 1705.pdf · uploaded 17 Apr 2026Source
- OthersForm 3 Clarification.pdf · uploaded 20 Apr 2026Source
- Others1705.pdf · uploaded 20 Apr 2026Source
Show all 61 documentsShow fewer documents
Finance
Legal
- Declaration Form BForm B Revised.pdf · uploaded 13 Mar 2026Source
- Declaration Form BDA Kamdhenu CHS-1-45.pdf · uploaded 13 Mar 2026Source
- Declaration Form BDA Kamdhenu CHS-46-80.pdf · uploaded 13 Mar 2026Source
- Declaration Form BDA Kamdhenu CHS-81-115.pdf · uploaded 13 Mar 2026Source
- Declaration Form BDA Kamdhenu CHS-116-160.pdf · uploaded 13 Mar 2026Source
- Declaration Form BDA Kamdhenu CHS-161-205.pdf · uploaded 13 Mar 2026Source
- Declaration Form BDA Kamdhenu CHS-206-260.pdf · uploaded 13 Mar 2026Source
- Declaration Form BDA Kamdhenu CHS-261-300.pdf · uploaded 13 Mar 2026Source
- Declaration Form BDA New Pragati CHS-1-47.pdf · uploaded 13 Mar 2026Source
- Declaration Form BDA New Pragati CHS-48-90.pdf · uploaded 13 Mar 2026Source
- Declaration Form BDA New Pragati CHS-91-125.pdf · uploaded 13 Mar 2026Source
- Declaration Form BDA New Pragati CHS-126-165.pdf · uploaded 13 Mar 2026Source
- Declaration Form BDA New Pragati CHS-166-225.pdf · uploaded 13 Mar 2026Source
- Declaration Form BDA New Pragati CHS-226-278.pdf · uploaded 13 Mar 2026Source
- Declaration Form BSPV Title.pdf · uploaded 31 Mar 2026Source
Migrated
Technical
- OthersDeclaration for Commencement Certificate New.pdf · uploaded 13 Mar 2026Source
- OthersDisclosure of Interest-AMB.pdf · uploaded 13 Mar 2026Source
- OthersDisclosure of Interest-MBB.pdf · uploaded 13 Mar 2026Source
- OthersDisclosure of Interest-MMB.pdf · uploaded 13 Mar 2026Source
- OthersEncumbrance Certificate - Finance.pdf · uploaded 13 Mar 2026Source
- OthersNo Encubrance legal.pdf · uploaded 13 Mar 2026Source
- DocumentLOI Letter.pdf · uploaded 14 Mar 2026Source
- DocumentLOI Drawings 1.pdf · uploaded 14 Mar 2026Source
- DocumentLOI Drawings 2.pdf · uploaded 14 Mar 2026Source
- DocumentLOI Drawings 3.pdf · uploaded 14 Mar 2026Source
- DocumentLOI Drawings 4.pdf · uploaded 14 Mar 2026Source
- Document1.pdf · uploaded 14 Mar 2026Source
- Document2.pdf · uploaded 14 Mar 2026Source
- Document3.pdf · uploaded 14 Mar 2026Source
- Document4.pdf · uploaded 14 Mar 2026Source
- Document5.pdf · uploaded 14 Mar 2026Source
- Document6.pdf · uploaded 14 Mar 2026Source
- Document7.pdf · uploaded 14 Mar 2026Source
- Document8.pdf · uploaded 14 Mar 2026Source
- Document9.pdf · uploaded 14 Mar 2026Source
- Document10.pdf · uploaded 14 Mar 2026Source
- Document11.pdf · uploaded 14 Mar 2026Source
- Document12.pdf · uploaded 14 Mar 2026Source
- Document13.pdf · uploaded 14 Mar 2026Source
- DocumentRera Undertaking Annexure A.pdf · uploaded 14 Mar 2026Source
- DocumentRera Undertaking Annexure A.pdf · uploaded 1 Apr 2026Source
- DocumentSheet 4 Car Parking.pdf · uploaded 2 Apr 2026Source
- DocumentSheet 5 Car Parking.pdf · uploaded 2 Apr 2026Source
- OthersDeclaration regarding total number of Floors.pdf · uploaded 11 May 2026Source
- OthersDeclaration regarding total number of Floors.pdf · uploaded 12 May 2026Source
Technical (Architect)
- DocumentForm 1.pdf · uploaded 16 Jul 2026Source
Technical (Engineer)
- DocumentForm 2.pdf · uploaded 16 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Condominium Plot No 1, Condominium Plot No 2
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —47 units in all
- Address
- Sector 24 Nerul Road, NerulPIN 400706
- Village
- Nerul, Thane taluka
- Location
- 19.03168, 73.01094
- Land area for this project
- 4,721 sq m (50,811 sq ft)
- Permissible built-up area
- 33,796 sq m (3,63,773 sq ft)
- Sanctioned built-up area
- 28,188 sq m (3,03,415 sq ft)
- Recreational open space
- 668 sq m (7,190 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Condominium Plot No 1 and Condominium Plot No 2
Boundaries
- North
- 20 Mtr Wide DP Road
- South
- 15 Mtr Wide DP Road
- East
- Plot No 3
- West
- Plot No 7
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking47 units
47 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 47 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Engineer | Bharat Dave | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Nerul
- Sai World One CommercialRERA PC1330002601535
- Sai World One ResidentialRERA PR1330002601500
- Jewel Of PalmRERA PM1330002600412
- E.V.ParadiseRERA PR1330002600299
- Nova ArkRERA PC1330002600139
- Nova VistaRERA PR1330002600138
- La PalacioRERA PR1330002503064
- Matrix EstellaRERA PR1330002503040
All 58 projects in Nerul · Compare Sai Palm View (Incentive Tower) with another project