Extended 9 mo6 floorsRERA P51700003251
Main building, Utsav
Deedo IDDP-THN-XK0J-UTSAVMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked33%4 of 12 · MahaRERA
Completion30 Nov 201828 Feb 2018 · revised
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 24.4 m² (263 sq.ft) | 4 | 2 |
| 1BHK | 26.5 m² (285 sq.ft) | 4 | 1 |
| 2BHK | 36.4 m² (392 sq.ft) | 4 | 1 |
As registered with MahaRERA
- RERA registration
- P51700003251 · registered 5 Aug 2017
- Promised completion
- 28 Feb 2018
- Revised completion
- 30 Nov 2018
- Sanctioned habitable floors
- 6
- Building
- UTSAV
- Sanctioned floors (incl. basement, stilt, podium)
- 6
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-THN-XK0J-UTSAV
Questions about Main building
When is Main building due for completion?
The MahaRERA registration promises 28 Feb 2018, revised to 30 Nov 2018.
How many floors does Main building have?
6 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology