Others · 1 building · 29 unitsRERA P51700053276

Mohan Samah

Deedo IDDP-THN-4Y31

Completion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 3% of its units are booked.

Navi Mumbai (M Corp.), Thane 400706 · by V M Constructions

DeliveryExtended 4 moPromised Dec 2027 · now due Apr 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales3% booked1 of 29 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2028

  • This projectRegistered 23 Oct 2023, completion promised 31 Dec 2027, revised to 30 Apr 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700053276
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170005327623 Oct 202331 Dec 202730 Apr 2028V M ConstructionsProject page
Documents118

1 document held by Deedo, 117 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardV M Constructions-Pancard.pdf · uploaded 24 Aug 2023Source

Legal

  • Declaration Form BForm B- Promoter(1).pdf · uploaded 25 Aug 2023Source
  • Legal Title reportPlot 11_Short Title_Mohan Samah_V M Construction_05102023 LH up.pdf · uploaded 21 Sep 2023Source
  • Legal Title reportMohan Samah_V M Construction_Plot No12_06102023 (1)_11zon.pdf · uploaded 21 Sep 2023Source
  • Other – LegalDeed of Assignment- Index II.pdf · uploaded 4 Oct 2023Source
  • Other – LegalTP_11zon.pdf · uploaded 4 Oct 2023Source

Migrated

  • 1 PAN CardV M Constructions-Pancard.pdf · uploaded 24 Aug 2023Source
Show all 118 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)VM- NMMC.pdf · uploaded 24 Aug 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan.pdf · uploaded 24 Aug 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 24 Aug 2023Source
  • 1 Declaration about Commencement CertificateFinal Format D.pdf · uploaded 25 Aug 2023Source
  • 1 Declaration in FORM BForm B- Promoter(1).pdf · uploaded 25 Aug 2023Source
  • 1 CERSAI detailsDeclaration on CERSAI.pdf · uploaded 25 Aug 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 25 Aug 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report-AL.pdf · uploaded 25 Aug 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report- AFS.pdf · uploaded 25 Aug 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FINALFirst Form 3 of Mohan Samah - V M Constructions.pdf · uploaded 14 Sep 2023Source
  • 1 Copy of the legal title reportPlot 11_Short Title_Mohan Samah_V M Construction_05102023 LH up.pdf · uploaded 21 Sep 2023Source
  • 2 Copy of the legal title reportMohan Samah_V M Construction_Plot No12_06102023 (1)_11zon.pdf · uploaded 21 Sep 2023Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Letter- Finance.pdf · uploaded 21 Sep 2023Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Letter- Legal.pdf · uploaded 21 Sep 2023Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Letter- Finance.pdf · uploaded 21 Sep 2023Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Letter- Legal.pdf · uploaded 21 Sep 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentV M Construction- CC verification mail.pdf · uploaded 21 Sep 2023Source
  • 1 Proforma of Allotment letterAllotment letter.pdf · uploaded 21 Sep 2023Source
  • 1 Proforma of Agreement for saleAFS_Mohan Samah_V M Construction.pdf · uploaded 21 Sep 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 21 Sep 2023Source
  • 1 Other – TechnicalV M Construction- CC verification mail.pdf · uploaded 21 Sep 2023Source
  • 1 Other – LegalDeed of Assignment- Index II.pdf · uploaded 4 Oct 2023Source
  • 2 Other – LegalTP_11zon.pdf · uploaded 4 Oct 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Mohan Samah as on Dec 2023.pdf · uploaded 26 Apr 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Mohan Samah as on March 2024.pdf · uploaded 26 Apr 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Mohan Samah as on Dec 2023.pdf · uploaded 26 Apr 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Mohan Samah as on March 2024.pdf · uploaded 26 Apr 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Mohan Samah as on March 2024.pdf · uploaded 27 Apr 2024Source
  • 2 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 28 May 2024Source
  • 1 Disclosure of sold/ booked inventoryCircular 29 - Mohan Samah as on March 2024.pdf · uploaded 6 Jun 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Mohan Samah as on June 2024.pdf · uploaded 19 Jul 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Mohan Samah - V M Constructions as on 30-06-2024.pdf · uploaded 19 Jul 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Mohan Samah as on 30-09-2024.pdf · uploaded 19 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Mohan Samah as on 30-09-2024.pdf · uploaded 19 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 7 Nov 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Revised Form 3.pdf · uploaded 7 Nov 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 7 Nov 2024Source
  • 1 Disclosure of sold/ booked inventoryRevised Circular 29.pdf · uploaded 7 Nov 2024Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 7 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Mohan Samah As on 31-03-2024.pdf · uploaded 7 Nov 2024Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 FY 2023-24.pdf · uploaded 7 Nov 2024Source
  • 1 Copy of Layout Approval (in case of layout)Plan.pdf · uploaded 12 Nov 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 12 Nov 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan.pdf · uploaded 12 Nov 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Signed.pdf · uploaded 14 Nov 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 2 Dec 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)mohan1 SCAN.pdf · uploaded 20 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Mohan Samah as on 31-12-2024.pdf · uploaded 20 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)3 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 20 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Mohan Samah as on 20-02-2025.pdf · uploaded 20 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1_31-12-2024.pdf · uploaded 5 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Dec 2024_11zon.pdf · uploaded 5 Apr 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Feb 2025_11zon.pdf · uploaded 5 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Dec 2024.pdf · uploaded 5 Apr 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Feb 2025.pdf · uploaded 5 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryCircular 29.pdf · uploaded 5 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Mohan Samah as on 31-03-2025.pdf · uploaded 20 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Mohan Samah as on March 2025.pdf · uploaded 20 Apr 2025Source
  • Form 1Form 1 - Mohan Samah as on June 2025.pdf · uploaded 5 Jan 2026Source
  • Form 2Form 2 - Mohan Samah as on June 2025.pdf · uploaded 5 Jan 2026Source
  • Form 3Form 3 - Mohan Samah as on June 2025.pdf · uploaded 5 Jan 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Mohan Samah as on June 2025.pdf · uploaded 5 Jan 2026Source
  • Form 1Form 1 - Mohan Samah as on Sep 2025.pdf · uploaded 5 Jan 2026Source
  • Form 2Form 2 - Mohan Samah as on Sep 2025.pdf · uploaded 5 Jan 2026Source
  • Form 3Form 3 - Mohan Samah as on Sep 2025.pdf · uploaded 5 Jan 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Mohan Samah as on Sep 2025.pdf · uploaded 5 Jan 2026Source
  • Form 1Form 1 - Mohan Samah as on June 2025.pdf · uploaded 11 Feb 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Mohan Samah as on June 2025.pdf · uploaded 11 Feb 2026Source
  • Form 2Form 2 - Mohan Samah as on March 2025.pdf · uploaded 11 Feb 2026Source
  • Form 3Form 3 of Mohan Samah as on 31-03-2025.pdf · uploaded 11 Feb 2026Source
  • OthersACC Letter.pdf · uploaded 11 Feb 2026Source
  • Form 1Form 1 - Mohan Samah as on June 2025.pdf · uploaded 11 Feb 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Mohan Samah as on June 2025.pdf · uploaded 11 Feb 2026Source
  • Form 2Form 2 Mohan Samah as on 31-12-2024.pdf · uploaded 11 Feb 2026Source
  • Form 3Form 3 Mohan Samah as on 31-12-2024.pdf · uploaded 11 Feb 2026Source
  • OthersACC Drawing.pdf · uploaded 11 Feb 2026Source
  • Form 1Form 1 - Mohan Samah as on Dec 2025.pdf · uploaded 20 Feb 2026Source
  • Form 2Form 2 - Mohan Samah as on Dec 2025.pdf · uploaded 20 Feb 2026Source
  • Form 3Form 3 - Mohan Samah as on Dec 2025.pdf · uploaded 20 Feb 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Mohan Samah as on Dec 2025.pdf · uploaded 20 Feb 2026Source
  • Form 1Form 1 - Mohan Samah as on March 2026.pdf · uploaded 28 Apr 2026Source
  • Form 2Form 2 of Mohan Samah as on 31-03-2026.pdf · uploaded 28 Apr 2026Source
  • Form 3Form 3 of Mohan Samah as on 31-03-2026.pdf · uploaded 28 Apr 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Mohan Samah as on 31-03-2026.pdf · uploaded 28 Apr 2026Source
  • Form 1Form 1 - Mohan Samah as on March 2026.pdf · uploaded 5 May 2026Source
  • Form 2Form 2 of Mohan Samah as on 31-03-2026.pdf · uploaded 5 May 2026Source
  • Form 3Form 3 of Mohan Samah as on 31-03-2026.pdf · uploaded 5 May 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Mohan Samah as on 31-03-2026.pdf · uploaded 5 May 2026Source
  • OthersDRAFT AGREEMENT(FINAL UPLOAD).pdf · uploaded 5 May 2026Source
  • Form 1FORM1_MOHAN SAMAH-30-06-2026.pdf · uploaded 23 Jul 2026Source
  • Form 2Mohan_Samah_Form2_Q1_2026-27_23-07-2026_11-47.pdf · uploaded 23 Jul 2026Source
  • Form 3Mohan_Samah_Form3_Q1_2026-27_22-07-2026_13-01_doc1.pdf · uploaded 23 Jul 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Mohan Samah as on june 2026.pdf · uploaded 23 Jul 2026Source

Technical

  • DocumentVM- NMMC.pdf · uploaded 24 Aug 2023Source
  • DocumentPlan.pdf · uploaded 24 Aug 2023Source
  • Other – TechnicalV M Construction- CC verification mail.pdf · uploaded 21 Sep 2023Source
  • DocumentPlan.pdf · uploaded 12 Nov 2024Source
  • DocumentPlan.pdf · uploaded 12 Nov 2024Source

Technical (Architect)

  • DocumentForm 1 - Mohan Samah as on March 2024.pdf · uploaded 27 Apr 2024Source
  • DocumentForm 1.pdf · uploaded 7 Nov 2024Source
  • DocumentForm 1 - Signed.pdf · uploaded 14 Nov 2024Source
  • Document3 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 20 Mar 2025Source
  • DocumentForm-1_31-12-2024.pdf · uploaded 5 Apr 2025Source

Technical (Engineer)

  • DocumentForm 2 Mohan Samah as on June 2024.pdf · uploaded 19 Jul 2024Source
  • DocumentForm 2 Mohan Samah as on 30-09-2024.pdf · uploaded 19 Oct 2024Source
  • DocumentForm 2.pdf · uploaded 7 Nov 2024Source
  • DocumentForm 2 Mohan Samah as on 31-12-2024.pdf · uploaded 20 Jan 2025Source
  • DocumentForm 2 - Dec 2024.pdf · uploaded 5 Apr 2025Source
  • DocumentForm 2 - Feb 2025.pdf · uploaded 5 Apr 2025Source
  • DocumentForm 2 - Mohan Samah as on March 2025.pdf · uploaded 20 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 11, 12

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 2nd Floor, 3BHK, Office space, Shop29 units in all
Address
Plot No-10, 11 and 12, Sector- 6, Sector No- 6, Sarsole, NerulPIN 400706
Village
Navi Mumbai (M Corp.), Thane taluka
Land area for this project
1,499 sq m (16,130 sq ft)
Permissible built-up area
5,700 sq m (61,354 sq ft)
Sanctioned built-up area
2,058 sq m (22,157 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
109
Developed in phases
No

Survey, CTS, gat or plot numbers

1112Plot No10Sector 6

Land as published on MahaRERA's project page

Plot No-10, 11 and 12, Sector- 6

Boundaries

North
35 meter wide road
South
6 meter wide road
East
Plot no- 11
West
Plot No-13

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking29 units

1 of 29 units booked (3%), as the promoter reported to MahaRERA

2BHK · 4 units2nd Floor · 1 unit3BHK · 2 unitsOffice space · 11 unitsShop · 11 units
TypeCarpet areaUnitsBooked
2BHK61.39 sq m · 661 sq ft20
2BHK61.47 sq m · 662 sq ft21
2nd Floor419.19 sq m · 4,512 sq ft10
3BHK93.16 sq m · 1,003 sq ft20
Office space14.49 sq m · 156 sq ft20
Office space15 sq m · 161 sq ft10
Office space16.01 sq m · 172 sq ft20
Office space16.51 sq m · 178 sq ft20
Show all 18 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Office space16.64 sq m · 179 sq ft20
Office space20.05 sq m · 216 sq ft10
Office space29.53 sq m · 318 sq ft10
Shop20.66 sq m · 222 sq ft20
Shop21.39 sq m · 230 sq ft10
Shop21.75 sq m · 234 sq ft10
Shop22.84 sq m · 246 sq ft20
Shop23.56 sq m · 254 sq ft20
Shop23.74 sq m · 256 sq ft20
Shop37.79 sq m · 407 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology