Completion was pushed back 4 months, to Apr 2031; no MahaRERA orders on record; 20% of its units are booked.

Navi Mumbai (M Corp.), Thane 400706 · by Mm Breeze Realty LLP

DeliveryExtended 4 moPromised Dec 2030 · now due Apr 2031RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales20% booked19 of 95 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2031

  • This projectRegistered 26 Dec 2025, completion promised 31 Dec 2030, revised to 30 Apr 2031.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPM1330002501894
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM133000250189426 Dec 202531 Dec 203030 Apr 2031Mm Breeze Realty LLPProject page
Documents26

1 document held by Deedo, 25 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan Card.pdf · uploaded 8 Oct 2025Source

Legal

  • OthersAnnexure A Mubark Khan.pdf · uploaded 12 Nov 2025Source
  • OthersAnnexure- A-Anand Pardeshi.pdf · uploaded 12 Nov 2025Source
  • OthersAnnexure-A Mohd Bilal Khan.pdf · uploaded 12 Nov 2025Source
  • Declaration Form BForm B.pdf · uploaded 12 Nov 2025Source
  • Declaration Form BALLOTEMENT.pdf · uploaded 12 Nov 2025Source
  • Declaration Form BFinal Search Title Report.pdf · uploaded 4 Dec 2025Source
Show all 26 documentsShow fewer documents

Legal

  • Declaration Form BAgreement to Lease M M Breeze Realty.pdf · uploaded 5 Dec 2025Source

Migrated

  • Withdrawal Update Form 1From 1.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 1From 1.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 2From 2.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 2From 2.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 3From 3.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 3From 3.pdf · uploaded 28 Apr 2026Source
  • Withdrawal Update Form 1From 1.pdf · uploaded 28 Sep 2026Source
  • Withdrawal Update Form 2From 2.pdf · uploaded 28 Sep 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 28 Sep 2026Source

Planning Authority

  • DocumentNMMCB_7005_2025_0048_AutoDCR.pdf · uploaded 4 Dec 2025Source
  • Document19935_signed.pdf · uploaded 4 Dec 2025Source
  • DocumentPlotArea.pdf · uploaded 4 Dec 2025Source
  • Document17718__Supervision1_signed.pdf · uploaded 4 Dec 2025Source

Technical

  • DocumentCC Drawing.pdf · uploaded 8 Oct 2025Source
  • DocumentAdobe Scan Nov 20, 2025 (1).pdf · uploaded 26 Nov 2025Source

Technical (Architect)

  • DocumentFrom 1.pdf · uploaded 28 Sep 2026Source

Technical (Engineer)

  • DocumentFrom 2.pdf · uploaded 28 Sep 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel P_No.8, SECTOR-29

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Unit types
—95 units in all
Address
Plot no 8 Sector 29, Nerul Navi MumbaiPIN 400706
Village
Navi Mumbai (M Corp.), Thane taluka
Land area for this project
1,286 sq m (13,842 sq ft)
Permissible built-up area
6,207 sq m (66,807 sq ft)
Sanctioned built-up area
6,207 sq m (66,807 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
159
Developed in phases
No

Survey, CTS, gat or plot numbers

P_No.8SECTOR-29

Land as published on MahaRERA's project page

P_No.8, SECTOR-29, NERUL CTS_No.NA Sur_No.NA

Boundaries

North
buildibg
South
building
East
building
West
road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking95 units

95 units registered

— · 95 units
TypeCarpet areaUnits
——95

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
EngineerVilas Agharkar—

Source: MahaRERA project page. Contact details are not shown.