Commercial · 1 building · 732 unitsRERA P51700025150

24 High

Deedo IDDP-THN-57A4

Its promised completion date, Apr 2026, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 73% of its units are booked.

Navi Mumbai (M Corp.), Thane 400706 · by Dream Apex Realties Limited

Delivery7 mo past duePromised Apr 2026 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales73% booked532 of 732 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Apr 2026, has passed and MahaRERA does not show it completed

  • This projectRegistered 19 Mar 2020, completion promised 5 Apr 2026, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700025150
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170002515019 Mar 20205 Apr 20265 Apr 2026Dream Apex Realties LimitedProject page
Documents105

1 document held by Deedo, 104 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Card13 dream apex pan card corrected.pdf · uploaded 9 Mar 2020Source

Legal

  • Legal Title report11 Title Report_compressed (1).pdf · uploaded 9 Mar 2020Source
  • Declaration Form BAffidavit and Declaration in Form B_compressed (1).pdf · uploaded 9 Mar 2020Source
  • Declaration Form BMIDC _ TRANSFER ORDER _ 225.pdf · uploaded 16 Mar 2026Source

Migrated

  • 1 PAN Card13 dream apex pan card corrected.pdf · uploaded 9 Mar 2020Source
  • 1 Copy of the legal title report11 Title Report_compressed (1).pdf · uploaded 9 Mar 2020Source
  • 1 Details of encumbrances4 NO EMCUMBRANCE.pdf · uploaded 9 Mar 2020Source
Show all 105 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted development8 Commencement Letter.pdf · uploaded 9 Mar 2020Source
  • 1 Declaration in FORM BAffidavit and Declaration in Form B_compressed (1).pdf · uploaded 9 Mar 2020Source
  • 1 Proforma of Allotment letterDream Apex Draft Allotment Letter.pdf · uploaded 9 Mar 2020Source
  • 1 Copy of Layout Approval (in case of layout)Layout compressed.pdf · uploaded 13 Mar 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentSanctioned plan 1.pdf · uploaded 13 Mar 2020Source
  • 2 Building Plan Approval / NA Order for plotted developmentSanctioned plan 2.pdf · uploaded 13 Mar 2020Source
  • 3 Building Plan Approval / NA Order for plotted developmentSanctioned plan 3.pdf · uploaded 13 Mar 2020Source
  • 4 Building Plan Approval / NA Order for plotted developmentSanctioned plan 4.pdf · uploaded 13 Mar 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Dram Apex Realties RERA CA Certificate.pdf · uploaded 13 Mar 2020Source
  • 2 Proforma of Allotment letterdeclaration of agreement.pdf · uploaded 13 Mar 2020Source
  • 5 Building Plan Approval / NA Order for plotted developmentRevised drawings Page 1-2.pdf · uploaded 4 Jan 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentRevised Approval D-225 D-226.pdf · uploaded 4 Jan 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 31-03-2021.pdf · uploaded 12 Apr 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 31-10-2021.pdf · uploaded 12 Apr 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 31-03-2022.pdf · uploaded 12 Apr 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 31-10-2022.pdf · uploaded 12 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5.pdf · uploaded 28 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5.pdf · uploaded 28 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5.pdf · uploaded 28 Apr 2023Source
  • 2 Details of encumbrancesEncumbrances.pdf · uploaded 7 Sep 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 - 24 High - FY 2022-23.pdf · uploaded 16 Feb 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-24 High.pdf · uploaded 17 Feb 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA Form 3 300623 Dream Apex.pdf · uploaded 17 Apr 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA Form 3 300923 Dream Apex.pdf · uploaded 17 Apr 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - Q1.pdf · uploaded 23 Apr 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - Q3.pdf · uploaded 23 Apr 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - Q2.pdf · uploaded 23 Apr 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 3 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 3 Jul 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 3 Jul 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 3 Jul 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 3 Jul 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 3 Jul 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 6 Jul 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 30062024.pdf · uploaded 7 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 02 30062024.pdf · uploaded 7 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1.pdf · uploaded 7 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2.pdf · uploaded 7 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1.pdf · uploaded 13 Mar 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1.pdf · uploaded 13 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 16 Apr 2025Source
  • 1 Copy of Layout Approval (in case of layout)1-7.pdf · uploaded 17 Apr 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentAnnexure A CC LATEST.pdf · uploaded 17 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A - 2019-20.pdf · uploaded 17 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A - 2020-21.pdf · uploaded 17 Apr 2025Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 17 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A - 2021-22.pdf · uploaded 17 Apr 2025Source
  • 1 Proforma of Agreement for saleFinal_Draft AFS.pdf · uploaded 17 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A - 2022-23.pdf · uploaded 17 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM-2A - 2023-24.pdf · uploaded 17 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 25 Apr 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 25 Apr 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 PDF DSC (1).pdf · uploaded 9 Jul 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1.pdf · uploaded 21 Jul 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 21 Jul 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2.pdf · uploaded 21 Jul 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1.pdf · uploaded 23 Jul 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2.pdf · uploaded 23 Jul 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3.pdf · uploaded 24 Jul 2025Source
  • Form 1Form 1 - 24 High as on Sep 2025.pdf · uploaded 20 Oct 2025Source
  • Form 2Form 2 - 24 High as on Sep 2025.pdf · uploaded 20 Oct 2025Source
  • Form 3Form 3 - 24 High as on Sep 2025.pdf · uploaded 20 Oct 2025Source
  • Disclosure of Sold and Booked InventoryCircular 29 - 24 High as on Sept 2025.pdf · uploaded 20 Oct 2025Source
  • Form 2A (FY 2024-2025)Form 2A-24 High -24-9-2025 FY 24-25.pdf · uploaded 24 Oct 2025Source
  • Withdrawal Update Form 1Form 1 - 24 High as on June 2025.pdf · uploaded 18 Nov 2025Source
  • Withdrawal Update Form 2Form 2 - 24 High as on June 2025.pdf · uploaded 18 Nov 2025Source
  • Withdrawal Update Form 3Form 3 - 24 High as on June 2025.pdf · uploaded 18 Nov 2025Source
  • Form 1Form 1 - 24 High as on March 2025.pdf · uploaded 20 Dec 2025Source
  • Form 2Form 2 - 24 High as on March 2025.pdf · uploaded 20 Dec 2025Source
  • Form 3Form 3-Q4-24-25 24.pdf · uploaded 20 Dec 2025Source
  • Disclosure of Sold and Booked InventoryCircular 29 - 24 High as on March 2025.pdf · uploaded 20 Dec 2025Source
  • Withdrawal Update Form 1Form 1 24 High.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 2Form 2 24 High.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 3Form 3 24 High_11zon.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 1Form 1 24 High.pdf · uploaded 14 Apr 2026Source
  • Withdrawal Update Form 2Form 2 24 High.pdf · uploaded 14 Apr 2026Source
  • Withdrawal Update Form 3Form 3 24 High_11zon.pdf · uploaded 14 Apr 2026Source

Technical

  • DocumentLayout compressed.pdf · uploaded 13 Mar 2020Source
  • DocumentSanctioned plan 1.pdf · uploaded 13 Mar 2020Source
  • DocumentSanctioned plan 2.pdf · uploaded 13 Mar 2020Source
  • DocumentSanctioned plan 3.pdf · uploaded 13 Mar 2020Source
  • DocumentSanctioned plan 4.pdf · uploaded 13 Mar 2020Source
  • DocumentRevised drawings Page 1-2.pdf · uploaded 4 Jan 2022Source
  • Document1-7.pdf · uploaded 17 Apr 2025Source
  • DocumentSanction Plan _ 05 March 2025 (3).pdf · uploaded 26 Nov 2025Source

Technical (Architect)

  • DocumentForm1.pdf · uploaded 7 Mar 2025Source
  • DocumentForm1.pdf · uploaded 13 Mar 2025Source
  • DocumentForm1.pdf · uploaded 13 Mar 2025Source
  • DocumentForm1.pdf · uploaded 21 Jul 2025Source
  • DocumentForm1.pdf · uploaded 23 Jul 2025Source
  • DocumentForm 1 24 High.pdf · uploaded 20 Jan 2026Source

Technical (Engineer)

  • DocumentFORM 02 30062024.pdf · uploaded 7 Feb 2025Source
  • DocumentForm2.pdf · uploaded 7 Mar 2025Source
  • DocumentForm 2.pdf · uploaded 16 Apr 2025Source
  • DocumentForm2.pdf · uploaded 21 Jul 2025Source
  • DocumentForm2.pdf · uploaded 23 Jul 2025Source
  • DocumentForm 2 24 High.pdf · uploaded 20 Jan 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel D-225, D-226

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Certificate Signed
Unit types
Office space, Shop732 units in all
Address
D-225 And D-226, Ttc Industrial Area, Opp Dy Patil StadiumPIN 400706
Village
Navi Mumbai (M Corp.), Thane taluka
Land area for this project
8,550 sq m (92,031 sq ft)
Permissible built-up area
31,297 sq m (3,36,883 sq ft)
Sanctioned built-up area
28,022 sq m (3,01,624 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

D-225D-226

Land as published on MahaRERA's project page

D-225 AND D-226

Boundaries

North
Plot No D 224
South
Plot No D 227
East
Forest Land
West
Road R W 20 Meters

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking732 units

532 of 732 units booked (73%), as the promoter reported to MahaRERA

Office space · 722 unitsShop · 10 units
TypeCarpet areaUnitsBooked
Office space27.32 sq m · 294 sq ft3836
Office space29.75 sq m · 320 sq ft7665
Office space31.27 sq m · 337 sq ft12084
Office space32.03 sq m · 345 sq ft3831
Office space33.91 sq m · 365 sq ft228151
Office space34.19 sq m · 368 sq ft3828
Office space34.47 sq m · 371 sq ft7661
Office space34.59 sq m · 372 sq ft3834
Show all 12 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Office space39.96 sq m · 430 sq ft3833
Office space42.84 sq m · 461 sq ft320
Shop58.35 sq m · 628 sq ft88
Shop76.25 sq m · 821 sq ft21

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSoyuz Talib Architects—
Chartered accountantChetan Joshi—
Chartered accountantNaina Jain—
EngineerAssociated Structural Consultants—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology