Completion was pushed back 4 months, to Jul 2028; no MahaRERA orders on record; 0% of its units are booked.

Naupada, Thane 400602 · by Skg Moreshwara Realty Pvt Ltd

DeliveryExtended 4 moPromised Mar 2028 · now due Jul 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 30 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jul 2028

  • This projectRegistered 6 Apr 2026, completion promised 31 Mar 2028, revised to 31 Jul 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPM1330002600029
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM13300026000296 Apr 202631 Mar 202831 Jul 2028Skg Moreshwara Realty Pvt LtdProject page
Documents39

1 document held by Deedo, 38 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan Card SKG Moreshwara.pdf · uploaded 24 Dec 2025Source
  • Othersvaibility declaration.pdf · uploaded 25 Dec 2025Source
  • OthersDeclaration of not opening rera account.pdf · uploaded 26 Dec 2025Source
  • OthersViability Letter.pdf · uploaded 2 Mar 2026Source
  • Othersformat a (2).pdf · uploaded 12 Mar 2026Source

Legal

  • OthersDOI PRIYANSH PHATAK.pdf · uploaded 25 Dec 2025Source
  • OthersDOI BHAGWANDAS PATEL.pdf · uploaded 25 Dec 2025Source
Show all 39 documentsShow fewer documents

Legal

  • OthersDOI NARSHI PATEL.pdf · uploaded 25 Dec 2025Source
  • OthersDOI SUNDEEP JAGASIA.pdf · uploaded 25 Dec 2025Source
  • Declaration Form BSKG FORM B PROMOTER.pdf · uploaded 25 Dec 2025Source
  • Declaration Form Bownership documents property card 712.pdf · uploaded 25 Dec 2025Source
  • Declaration Form BTITLE REPORT.pdf · uploaded 12 Jan 2026Source
  • OthersDA PART -1_compressed.pdf · uploaded 26 Feb 2026Source
  • OthersDA PART -2_compressed.pdf · uploaded 26 Feb 2026Source
  • OthersDA PART -3_compressed.pdf · uploaded 26 Feb 2026Source
  • OthersDA PART -4_compressed.pdf · uploaded 26 Feb 2026Source
  • OthersDA PART -5_compressed.pdf · uploaded 26 Feb 2026Source
  • OthersDA PART -6_compressed.pdf · uploaded 26 Feb 2026Source
  • OthersDA PART -7_compressed (1).pdf · uploaded 26 Feb 2026Source
  • OthersDA PART -8_compressed (1).pdf · uploaded 26 Feb 2026Source
  • OthersDA PART -9_compressed.pdf · uploaded 26 Feb 2026Source
  • OthersDA PART -10_compressed.pdf · uploaded 26 Feb 2026Source

Planning Authority

  • Documentd5U3DPQ4771_2_3_4_5_merged.pdf · uploaded 27 Feb 2026Source
  • Documentd5U3DPQ477Permission_and_CC_Certificate.pdf · uploaded 27 Feb 2026Source
  • Documentd5U3DPQ477Scrutiny_report.pdf · uploaded 27 Feb 2026Source
  • Documentt9tchBeztSPR_Card.pdf · uploaded 27 Feb 2026Source
  • DocumentCert_RB_543718_407oRa3XSign.pdf · uploaded 27 Feb 2026Source
  • Document1755760896_TMCB-25-ENTRY-83287_R1.html · uploaded 27 Feb 2026Source
  • Document1755760896_TMCB-25-ENTRY-83287_R1.pdf_8_43DSE_Sign.pdfSign.pdf · uploaded 27 Feb 2026Source

Technical

  • DocumentSANCTION DAWING TMCB-25-ENTRY-83287_R1.pdf · uploaded 24 Dec 2025Source
  • DocumentSANCTION DAWING TMCB-25-ENTRY-83287_R1.pdf · uploaded 24 Dec 2025Source
  • DocumentANNEXURE A.pdf · uploaded 26 Dec 2025Source
  • Otherscc declration.pdf · uploaded 26 Dec 2025Source
  • Otherspast exprience.pdf · uploaded 26 Feb 2026Source
  • OthersNew Thana CHS NOC for office P 5and non allotment of units P 2 Highlighted.pdf · uploaded 27 Mar 2026Source
  • OthersNilesh joshi NOC for non allotment of unit 1704.pdf · uploaded 27 Mar 2026Source
  • OthersAbhishek Thoke NOC for non allotment of unit 2304.pdf · uploaded 27 Mar 2026Source
  • OthersVeena Vinayak Divakar NOC for non allotment of unit 1104.pdf · uploaded 27 Mar 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 374 TIKKA NO.10 final_plot_no - sector_no 2 mauje NAUPADA, plot_no - city_survey_gut_no C..TS. NO. 348

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Unit types
—59 units in all
Address
Ram Mandir Road, Bhaskar Colony NaupadaPIN 400602
Village
Naupada, Thane taluka
Land area for this project
1,916 sq m (20,619 sq ft)
Permissible built-up area
7,350 sq m (79,115 sq ft)
Sanctioned built-up area
7,350 sq m (79,115 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
17
Developed in phases
No

Survey, CTS, gat or plot numbers

374 TIKKA NO.10 final_plot_no - sector_no 2 mauje NAUPADAplot_no - city_survey_gut_no C..TS. NO. 348

Land as published on MahaRERA's project page

plot_no - city_survey_gut_no C..TS. NO. 348, 374 TIKKA NO.10 final_plot_no - sector_no 2 mauje NAUPADA road_street 15.00 MT. WIDE ROAD society YES

Boundaries

North
Property of Sahastrabudhhe
South
Property of Vardhaman Society
East
Property of Tirupati Society
West
Municipal Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking59 units

59 units registered

— · 59 units
TypeCarpet areaUnits
——59

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAnil Jagwani—
Chartered accountantRaj Paresh Sheth—
EngineerAshish Patel—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology