Its promised completion date, Dec 2024, has passed and MahaRERA does not show it completed
- This projectRegistered 20 Apr 2022, completion promised 1 Dec 2024, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700034666
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700034666 | 20 Apr 2022 | 1 Dec 2024 | 1 Dec 2024 | Aai Enterprises | Project page |
Documents40
1 document held by Deedo, 39 filings listed on MahaRERA's project page
Finance
- PAN Card13 PAN card Aai Ent.pdf · uploaded 24 Mar 2022Source
Legal
Show all 40 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted development8 Commencement Certificate Compressed.pdf · uploaded 24 Mar 2022Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 25 Mar 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect Certificate Compressed.pdf · uploaded 25 Mar 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 Engineers Certificate Compressed.pdf · uploaded 25 Mar 2022Source
- 1 Proforma of Allotment letter5 Allotment Letter Compressed.pdf · uploaded 25 Mar 2022Source
- 1 Other21 Copy of CREDAI Certificate.pdf · uploaded 25 Mar 2022Source
- 1 Declaration in FORM B7 FORM B for Authorised Partner Compressed.pdf · uploaded 26 Mar 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200233467328_For_Asset_Based_Search_26_03_2022_13_33_38_993.pdf · uploaded 26 Mar 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_compressed.pdf · uploaded 26 Mar 2022Source
- 1 Copy of the legal title reportTitle Certificate.pdf · uploaded 11 Apr 2022Source
- 1 Building Plan Approval / NA Order for plotted development9 Approved Plan.pdf · uploaded 11 Apr 2022Source
- 2 Proforma of Allotment letter6 Draft Agreement for sale.pdf · uploaded 11 Apr 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate of work completion.pdf · uploaded 24 Aug 2022Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate pride compressed.pdf · uploaded 15 Mar 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate Pride.pdf · uploaded 15 Mar 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)aai ent - ekveera pride Form 2 31-03-2023_11zon.pdf · uploaded 27 Jun 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed Form 3_11zon.pdf · uploaded 27 Jun 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 as on 30-06-2023.pdf · uploaded 22 Sep 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 as on 30-06-2023.pdf · uploaded 22 Sep 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed Form 3.pdf · uploaded 22 Sep 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Signed Form 5 Aai Ent Ekveera Pride.pdf · uploaded 6 Dec 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 12 Mar 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 12 Mar 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 12 Mar 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 AAI ENT.pdf · uploaded 19 Jun 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)AAI ENT.pdf · uploaded 19 Jun 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 AAI ENT.pdf · uploaded 19 Jun 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5 aai enterprises SIGNED.pdf · uploaded 14 Jan 2025Source
Technical
Technical (Architect)
- DocumentForm 1 AAI ENT.pdf · uploaded 19 Jun 2024Source
Technical (Engineer)
- DocumentAAI ENT.pdf · uploaded 19 Jun 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel GUT NO 55 PLOT NO 26 CTS NO 9171
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Shop26 units in all
- Address
- Gut No 55 Plot No 26 Cts No 9171, B Cabin Road, MorivaliPIN 421501
- Village
- Ambarnath(M Cl), Ambarnath taluka
- Land area for this project
- 410 sq m (4,410 sq ft)
- Permissible built-up area
- 1,125 sq m (12,111 sq ft)
- Sanctioned built-up area
- 1,125 sq m (12,111 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
GUT NO 55 PLOT NO 26 CTS NO 9171
Boundaries
- North
- P No 25
- South
- P No 27
- East
- 9-00 Mw Road
- West
- G No 56
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking26 units
6 of 26 units booked (23%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 31.37 sq m · 338 sq ft | 6 | 1 |
| 1BHK | 32.87 sq m · 354 sq ft | 6 | 2 |
| 2BHK | 45.25 sq m · 487 sq ft | 12 | 3 |
| Shop | 17.71 sq m · 191 sq ft | 2 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Pramod V Patil & Associates | — |
| Chartered accountant | VRP & Associates | — |
| Engineer | Atul Kudtarkar & Associates | — |
Source: MahaRERA project page. Contact details are not shown.