Skip to content
Residential / Group Housing · 2 buildingsRERA P51700009826

walchand nagar - 2

Deedo IDDP-THN-VGEY

MahaRERA shows it completed; no MahaRERA orders on record.

Mira Bhayandar (M Corp.), Thane 401101 · by Prakash Hamirmal Jain

DeliveryCompletedAs MahaRERA showsRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 22 Aug 2017, completion promised 30 Apr 2018.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700009826
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170000982622 Aug 201730 Apr 2018—Prakash Hamirmal JainProject page
Documents37

16 documents held by Deedo, 21 filings listed on MahaRERA's project page

Title report

Encumbrance details

Commencement certificate

Form B

Form 1

Form 2

Registration certificate

Form 5

Show all 37 documentsShow fewer documents

Form 4

Occupancy / completion certificate

  • Occupancy / completion certificate22 Oct 2019ViewSource

Other (3)

Layout plan

Building plan

Allotment letter

Document library

  • Copy of the legal title reporttitle.pdf · uploaded 31 Jul 2017View
  • Details of encumbrancessearch.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letteragreement as per rera declaration.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)plan approval.pdf · uploaded 31 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentcc (2).pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)architect.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)iod.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM Baffidavit.pdf · uploaded 31 Jul 2017View
  • Otherilovepdf_merged (5).pdf · uploaded 6 Dec 2017View
  • OtherC and D wing.pdf · uploaded 24 Sep 2018View
  • Certificates of CA (Form 5)CERTIFICATE.pdf · uploaded 15 Nov 2018View
  • Certificates of Architect (Form 4)FORM 4 A B C D.pdf · uploaded 8 Jun 2019View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentoc WN2 ABCD.pdf · uploaded 22 Oct 2019View

Promoter documents

  • Legal Title reporttitle.pdf · uploaded 31 Jul 2017View
  • Declaration Form Baffidavit.pdf · uploaded 31 Jul 2017View

Technical documents

  • Building Plan Approvaliod.pdfView
  • Layout Approvalplan approval.pdfView

Other legal documents

  • Otherilovepdf_merged (5).pdfView
  • OtherC and D wing.pdfView

Proforma allotment letter

  • Proforma allotment letteragreement as per rera declaration.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsSurvey 4, old s no 220 new s no 4

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Address
old s no 220 new s no 4PIN 401101
Village
Mira-Bhayandar (M Corp.), Thane taluka
Land area for this project
5,360 sq m (57,695 sq ft)
Permissible built-up area
4,337 sq m (46,680 sq ft)
Sanctioned built-up area
4,337 sq m (46,680 sq ft)
Recreational open space
804 sq m (8,654 sq ft)
Designated bank account
Icici Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

4old s no 220 new s no 4old s no 220 new s no 4

Land as published on MahaRERA's project page

old s no 220 new s no 4

Boundaries

North
s no 221
South
s no 218
East
s no 219
West
road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking42 parking spaces

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
walchand nagar 2 - A and B wingClosed/Covered000010
walchand nagar 2 - A and B wingOpen Space000012
walchan nagar 2 - C and D wingClosed/Covered00008
walchan nagar 2 - C and D wingOpen Space000012

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress3 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

walchand nagar 2 - A and B wing

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

walchan nagar 2 - C and D wing

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure60%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & Footpaths.0%
  • Water Supply.0%
  • Sewerage (Chamber, Lines, Septic Tank , STP).50%
  • Storm Water Drains.0%
  • Landscaping & Tree Planting.25%
  • Street Lighting.50%
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvesting.100%
  • Energy managemcnt.0%
  • Fire protection and fire safety requirements.25%
  • Electrical meter room, sub-station, receiving station.25%
  • Aggregate area of recreational Open Space.5%
  • Open Parking.100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Architectdinesh narottam patel—
Othervalu rathod—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Mira Bhayandar (M Corp.)

All 106 projects in Mira Bhayandar (M Corp.) · Compare walchand nagar - 2 with another project

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology