Residential / Group Housing · 19 buildings · 665 unitsRERA P51700011629 +1

Palava Milano

Deedo IDDP-THN-785S

MahaRERA shows it completed; no MahaRERA orders on record; 72% of its units are booked.

Khoni, Thane 421202 · by Palava Dwellers Private Limited · 92% of its projects kept the RERA date

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales72% booked481 of 665 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • P51700011629Registered 31 Aug 2017, completion promised 30 Mar 2023.
  • P51700015016Registered 22 Jan 2018, completion promised 30 Oct 2023.

No extension certificate on record.

2 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

19 buildings

Open a building to see every flat, floor by floor.

Show all 19 buildingsShow fewer buildings

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations2
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170001162931 Aug 201730 Mar 202330 Mar 2023Palava Dwellers Private LimitedProject page
P5170001501622 Jan 201830 Oct 202330 Oct 2023Palava Dwellers Private LimitedProject page
Documents161

4 documents held by Deedo, 157 filings listed on MahaRERA's project page

Registration certificate (2)

  • Registration certificateP51700011629 · 9 Sep 2021ViewSource
  • Registration certificateP51700015016 · 9 Sep 2021ViewSource

Other (2)

  • OtherP51700011629 · Date not statedView
  • OtherP51700015016 · Date not statedView

Finance

  • PAN CardP51700011629 · Microtec Pan Card.pdf · uploaded 11 Aug 2017Source
  • PAN CardP51700015016 · Microtec Pan Card.pdf · uploaded 18 Jan 2018Source

Legal

  • Legal Title reportP51700011629 · Milano Title Report dated.pdf · uploaded 11 Aug 2017Source
  • Legal Title reportP51700011629 · First Supplemental_Milano.pdf · uploaded 11 Aug 2017Source
Show all 161 documentsShow fewer documents

Legal

  • Declaration Form BP51700011629 · Milano E F.pdf · uploaded 14 Aug 2017Source
  • Legal Title reportP51700015016 · Title Report1.pdf · uploaded 17 Jan 2018Source
  • Legal Title reportP51700015016 · Title Report2.pdf · uploaded 17 Jan 2018Source
  • Legal Title reportP51700015016 · Second Supplemental Report on Title 17 January 2018.pdf · uploaded 17 Jan 2018Source
  • Declaration Form BP51700015016 · FORM B MILANO.pdf · uploaded 18 Jan 2018Source
  • Legal Title reportP51700011629 · MILANO MERGED pdf.pdf · uploaded 17 May 2018Source
  • Legal Title reportP51700015016 · MILANO MERGED pdf.pdf · uploaded 17 May 2018Source

Migrated

  • 1 PAN CardP51700011629 · Microtec Pan Card.pdf · uploaded 11 Aug 2017Source
  • 1 Copy of the legal title reportP51700011629 · Milano Title Report dated.pdf · uploaded 11 Aug 2017Source
  • 2 Copy of the legal title reportP51700011629 · First Supplemental_Milano.pdf · uploaded 11 Aug 2017Source
  • 1 Certificates of CA (Form 3)P51700011629 · Palava Milano E F.pdf · uploaded 11 Aug 2017Source
  • 1 Proforma of Allotment letterP51700011629 · ATS Amenities and allotment.pdf · uploaded 11 Aug 2017Source
  • 1 Details of encumbrancesP51700011629 · Milano E F.pdf · uploaded 14 Aug 2017Source
  • 1 Copy of Layout Approval (in case of layout)P51700011629 · Layout for upload.pdf · uploaded 14 Aug 2017Source
  • 1 Building Plan Approval (IOD)P51700011629 · Final Building Plan - Upload.pdf · uploaded 14 Aug 2017Source
  • 2 Building Plan Approval (IOD)P51700011629 · Final Building - Upload.pdf · uploaded 14 Aug 2017Source
  • 1 Declaration in FORM BP51700011629 · Milano E F.pdf · uploaded 14 Aug 2017Source
  • 1 Copy of Layout Approval (in case of layout)P51700015016 · Layout Plan.pdf · uploaded 16 Jan 2018Source
  • 1 Copy of the legal title reportP51700015016 · Title Report1.pdf · uploaded 17 Jan 2018Source
  • 2 Copy of the legal title reportP51700015016 · Title Report2.pdf · uploaded 17 Jan 2018Source
  • 3 Copy of the legal title reportP51700015016 · Second Supplemental Report on Title 17 January 2018.pdf · uploaded 17 Jan 2018Source
  • 1 Certificates of CA (Form 3)P51700015016 · form 3 milano.pdf · uploaded 17 Jan 2018Source
  • 1 Proforma of Allotment letterP51700015016 · ATS and Alottment Letter Milano.pdf · uploaded 17 Jan 2018Source
  • 1 PAN CardP51700015016 · Microtec Pan Card.pdf · uploaded 18 Jan 2018Source
  • 1 Details of encumbrancesP51700015016 · ENCUMBRANCES MILANO.pdf · uploaded 18 Jan 2018Source
  • 1 Building Plan Approval (IOD)P51700015016 · 39 F1.pdf · uploaded 18 Jan 2018Source
  • 2 Building Plan Approval (IOD)P51700015016 · 40 F1.pdf · uploaded 18 Jan 2018Source
  • 3 Building Plan Approval (IOD)P51700015016 · 57 F2.pdf · uploaded 18 Jan 2018Source
  • 4 Building Plan Approval (IOD)P51700015016 · 58 F3.pdf · uploaded 18 Jan 2018Source
  • 5 Building Plan Approval (IOD)P51700015016 · 59 F3.pdf · uploaded 18 Jan 2018Source
  • 6 Building Plan Approval (IOD)P51700015016 · 67 D3.pdf · uploaded 18 Jan 2018Source
  • 7 Building Plan Approval (IOD)P51700015016 · 68 D3.pdf · uploaded 18 Jan 2018Source
  • 8 Building Plan Approval (IOD)P51700015016 · 69 D3.pdf · uploaded 18 Jan 2018Source
  • 9 Building Plan Approval (IOD)P51700015016 · 70 D3.pdf · uploaded 18 Jan 2018Source
  • 10 Building Plan Approval (IOD)P51700015016 · For Approval 1.pdf · uploaded 18 Jan 2018Source
  • 11 Building Plan Approval (IOD)P51700015016 · For Approval 2.pdf · uploaded 18 Jan 2018Source
  • 12 Building Plan Approval (IOD)P51700015016 · For Approval 1.pdf · uploaded 18 Jan 2018Source
  • 13 Building Plan Approval (IOD)P51700015016 · For Approval 2.pdf · uploaded 18 Jan 2018Source
  • 1 Declaration in FORM BP51700015016 · FORM B MILANO.pdf · uploaded 18 Jan 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700011629 · PALAVA MILANO E F.pdf · uploaded 19 Feb 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700011629 · PALAVA MILANO - E F.pdf · uploaded 26 Feb 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentP51700011629 · 14 Mar 2018 A.pdf · uploaded 26 Mar 2018Source
  • 2 Commencement Certificates / NA Order for plotted developmentP51700011629 · 14 Mar 2018 B.pdf · uploaded 26 Mar 2018Source
  • 3 Commencement Certificates / NA Order for plotted developmentP51700011629 · 14 Mar 2018 C.pdf · uploaded 26 Mar 2018Source
  • 4 Commencement Certificates / NA Order for plotted developmentP51700011629 · 14 Mar 2018 D.pdf · uploaded 26 Mar 2018Source
  • 5 Commencement Certificates / NA Order for plotted developmentP51700011629 · 14 Mar 2018 E.pdf · uploaded 26 Mar 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentP51700015016 · 14 Mar 2018 A.pdf · uploaded 26 Mar 2018Source
  • 2 Commencement Certificates / NA Order for plotted developmentP51700015016 · 14 Mar 2018 B.pdf · uploaded 26 Mar 2018Source
  • 3 Commencement Certificates / NA Order for plotted developmentP51700015016 · 14 Mar 2018 C.pdf · uploaded 26 Mar 2018Source
  • 4 Commencement Certificates / NA Order for plotted developmentP51700015016 · 14 Mar 2018 D.pdf · uploaded 26 Mar 2018Source
  • 5 Commencement Certificates / NA Order for plotted developmentP51700015016 · 14 Mar 2018 E.pdf · uploaded 26 Mar 2018Source
  • 2 Details of encumbrancesP51700011629 · MILANO E F.pdf · uploaded 30 Mar 2018Source
  • 3 Copy of the legal title reportP51700011629 · MILANO MERGED pdf.pdf · uploaded 17 May 2018Source
  • 4 Copy of the legal title reportP51700015016 · MILANO MERGED pdf.pdf · uploaded 17 May 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700015016 · PALAVA MILANO A B C H I J.pdf · uploaded 9 Jul 2018Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700015016 · PALAVA MILANO A B C H I J.pdf · uploaded 9 Jul 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700015016 · PALAVA MILANO A B C H I J.pdf · uploaded 9 Jul 2018Source
  • 3 Details of encumbrancesP51700011629 · Milano E F.pdf · uploaded 13 Aug 2018Source
  • 2 Details of encumbrancesP51700015016 · Milano A B C H I J.pdf · uploaded 13 Aug 2018Source
  • 1 Certificates of CA (Form 5)P51700011629 · Palava Milano E,F.pdf · uploaded 1 Oct 2018Source
  • 1 Certificates of CA (Form 5)P51700015016 · Palava Milano A B C H I J.pdf · uploaded 1 Oct 2018Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)P51700011629 · casa milano.pdf · uploaded 13 Nov 2018Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)P51700015016 · casa milano.pdf · uploaded 13 Nov 2018Source
  • 4 Details of encumbrancesP51700011629 · Milano E F.pdf · uploaded 16 Nov 2018Source
  • 3 Details of encumbrancesP51700015016 · Milano A B C H I J.pdf · uploaded 16 Nov 2018Source
  • 3 Building Plan Approval (IOD)P51700011629 · C46.pdf · uploaded 19 Nov 2018Source
  • 4 Building Plan Approval (IOD)P51700011629 · C47.pdf · uploaded 19 Nov 2018Source
  • 5 Building Plan Approval (IOD)P51700011629 · C48.pdf · uploaded 19 Nov 2018Source
  • 6 Building Plan Approval (IOD)P51700011629 · C49.pdf · uploaded 19 Nov 2018Source
  • 14 Building Plan Approval (IOD)P51700015016 · C36.pdf · uploaded 19 Nov 2018Source
  • 15 Building Plan Approval (IOD)P51700015016 · C37.pdf · uploaded 19 Nov 2018Source
  • 16 Building Plan Approval (IOD)P51700015016 · C38.pdf · uploaded 19 Nov 2018Source
  • 17 Building Plan Approval (IOD)P51700015016 · C39.pdf · uploaded 19 Nov 2018Source
  • 5 Details of encumbrancesP51700011629 · PALAVA MILANO E F.pdf · uploaded 25 Feb 2019Source
  • 4 Details of encumbrancesP51700015016 · PALAVA MILANO A B C H I J.pdf · uploaded 25 Feb 2019Source
  • 1 Form 2AP51700011629 · MILANO E F.pdf · uploaded 17 Jun 2019Source
  • 1 Form 2AP51700015016 · MILANO A B C H I J.pdf · uploaded 17 Jun 2019Source
  • 2 Certificates of CA (Form 5)P51700011629 · Palava Mila E F.pdf · uploaded 30 Sep 2019Source
  • 2 Certificates of CA (Form 5)P51700015016 · Palava Milano AB CHI J.pdf · uploaded 30 Sep 2019Source
  • 2 Form 2AP51700011629 · Palava Milano E F.pdf · uploaded 27 Aug 2020Source
  • 2 Form 2AP51700015016 · Palava Milano A B C H I J.pdf · uploaded 27 Aug 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P51700011629 · 39 Palava Milano E F.pdf · uploaded 27 Oct 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P51700015016 · 42 Palava Milano A B C H I J.pdf · uploaded 27 Oct 2020Source
  • 3 Form 2AP51700011629 · P51700011629.pdf · uploaded 13 Aug 2021Source
  • 3 Form 2AP51700015016 · P51700015016.pdf · uploaded 13 Aug 2021Source
  • 2 Certificates of CA (Form 3)P51700011629 · 3 PALAVA - MILANO E,F.pdf · uploaded 9 Oct 2021Source
  • 2 Certificates of CA (Form 3)P51700015016 · 7 PALAVA - MILANO A,B,C,H,I,J.pdf · uploaded 9 Oct 2021Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700011629 · 14 PALAVA - MILANO E,F.pdf · uploaded 14 Oct 2021Source
  • 1 Disclosure of sold/ booked inventoryP51700011629 · P51700011629.pdf · uploaded 14 Oct 2021Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700015016 · 27 PALAVA MILANO A,B,C,H,I,J.pdf · uploaded 14 Oct 2021Source
  • 1 Disclosure of sold/ booked inventoryP51700015016 · P51700015016.pdf · uploaded 14 Oct 2021Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700011629 · 13_Milano E-F.pdf · uploaded 15 Oct 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P51700011629 · 38 Palava - Milano E,F.pdf · uploaded 15 Oct 2021Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700015016 · 26_MILANO A,B,C,H,I,J.pdf · uploaded 15 Oct 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P51700015016 · 41 Palava - Milano A,B,C,H,I,J.pdf · uploaded 15 Oct 2021Source
  • 4 Form 2AP51700011629 · 30 PALAVA - MILANO E,F.pdf · uploaded 18 Nov 2021Source
  • 4 Form 2AP51700015016 · 54 PALAVA MILANO A,B,C,H,I,J.pdf · uploaded 18 Nov 2021Source
  • 3 Certificates of CA (Form 3)P51700011629 · 3 PALAVA - MILANO E,F.pdf · uploaded 15 Dec 2021Source
  • 3 Certificates of CA (Form 3)P51700015016 · 7 PALAVA - MILANO A,B,C,H,I,J.pdf · uploaded 15 Dec 2021Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700011629 · 14 PALAVA - MILANO E,F.pdf · uploaded 16 Dec 2021Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700015016 · 27 PALAVA MILANO A,B,C,H,I,J.pdf · uploaded 16 Dec 2021Source
  • 2 Disclosure of sold/ booked inventoryP51700011629 · PALAVA - MILANO E,F.pdf · uploaded 27 Dec 2021Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700015016 · 7 PALAVA - MILANO A,B,C,H,I,J.pdf · uploaded 29 Jun 2022Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700011629 · PALAVA - MILANO E,F.pdf · uploaded 30 Jun 2022Source
  • 6 Details of encumbrancesP51700011629 · PALAVA - MILANO E,F.pdf · uploaded 30 Jul 2022Source
  • 5 Details of encumbrancesP51700015016 · PALAVA MILANO A,B,C,H,I,J.pdf · uploaded 30 Jul 2022Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700011629 · 3 PALAVA - MILANO E,F.pdf · uploaded 4 Aug 2022Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700015016 · 7 PALAVA - MILANO A,B,C,H,I,J.pdf · uploaded 4 Aug 2022Source
  • 4 Certificates of CA (Form 3)P51700011629 · 3 PALAVA - MILANO E,F.pdf · uploaded 5 Aug 2022Source
  • 4 Certificates of CA (Form 3)P51700015016 · 7 PALAVA - MILANO A,B,C,H,I,J.pdf · uploaded 5 Aug 2022Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP51700011629 · Palava OC Sept 2022.pdf · uploaded 23 Sep 2022Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)P51700011629 · PALAVA - MILANO E,F.pdf · uploaded 29 Sep 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P51700011629 · 3 PALAVA - MILANO E,F.pdf · uploaded 12 Nov 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P51700015016 · 7 PALAVA - MILANO A,B,C,H,I,J.pdf · uploaded 12 Nov 2022Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP51700015016 · Palava OC Dec 2022.pdf · uploaded 27 Mar 2023Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP51700015016 · Palava OC Mar 23.pdf · uploaded 27 Mar 2023Source
  • 2 Disclosure of sold/ booked inventoryP51700015016 · MILANO A,B,C,H,I,J.pdf · uploaded 31 Mar 2023Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)P51700015016 · Milano A B.pdf · uploaded 5 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P51700011629 · Palava - Milano E,F.pdf · uploaded 16 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P51700015016 · Palava - Milano A,B,C,H,I,J.pdf · uploaded 16 Oct 2023Source
  • 3 Disclosure of sold/ booked inventoryP51700011629 · Milano E, F - P51700011629.pdf · uploaded 30 Nov 2023Source
  • 3 Disclosure of sold/ booked inventoryP51700015016 · Palava Milano A,B,C,H,I,J - P51700015016.pdf · uploaded 30 Nov 2023Source
  • 4 Disclosure of sold/ booked inventoryP51700011629 · Sold Unsold - PALAVA - MILANO E,F - P51700011629 - March 24.pdf · uploaded 28 May 2024View
  • 4 Disclosure of sold/ booked inventoryP51700015016 · Sold Unsold - PALAVA MILANO A,B,C,H,I,J - P51700015016 - March 24.pdf · uploaded 6 Jun 2024View

Technical

  • DocumentP51700011629 · Layout for upload.pdf · uploaded 14 Aug 2017Source
  • DocumentP51700011629 · Final Building Plan - Upload.pdf · uploaded 14 Aug 2017Source
  • DocumentP51700011629 · Final Building - Upload.pdf · uploaded 14 Aug 2017Source
  • DocumentP51700015016 · Layout Plan.pdf · uploaded 16 Jan 2018Source
  • DocumentP51700015016 · 39 F1.pdf · uploaded 18 Jan 2018Source
  • DocumentP51700015016 · 40 F1.pdf · uploaded 18 Jan 2018Source
  • DocumentP51700015016 · 57 F2.pdf · uploaded 18 Jan 2018Source
  • DocumentP51700015016 · 58 F3.pdf · uploaded 18 Jan 2018Source
  • DocumentP51700015016 · 59 F3.pdf · uploaded 18 Jan 2018Source
  • DocumentP51700015016 · 67 D3.pdf · uploaded 18 Jan 2018Source
  • DocumentP51700015016 · 68 D3.pdf · uploaded 18 Jan 2018Source
  • DocumentP51700015016 · 69 D3.pdf · uploaded 18 Jan 2018Source
  • DocumentP51700015016 · 70 D3.pdf · uploaded 18 Jan 2018Source
  • DocumentP51700015016 · For Approval 1.pdf · uploaded 18 Jan 2018Source
  • DocumentP51700015016 · For Approval 2.pdf · uploaded 18 Jan 2018Source
  • DocumentP51700015016 · For Approval 1.pdf · uploaded 18 Jan 2018Source
  • DocumentP51700015016 · For Approval 2.pdf · uploaded 18 Jan 2018Source
  • DocumentP51700011629 · C46.pdf · uploaded 19 Nov 2018Source
  • DocumentP51700011629 · C47.pdf · uploaded 19 Nov 2018Source
  • DocumentP51700011629 · C48.pdf · uploaded 19 Nov 2018Source
  • DocumentP51700011629 · C49.pdf · uploaded 19 Nov 2018Source
  • DocumentP51700015016 · C36.pdf · uploaded 19 Nov 2018Source
  • DocumentP51700015016 · C37.pdf · uploaded 19 Nov 2018Source
  • DocumentP51700015016 · C38.pdf · uploaded 19 Nov 2018Source
  • DocumentP51700015016 · C39.pdf · uploaded 19 Nov 2018Source

Technical (Architect)

  • DocumentP51700015016 · 7 PALAVA - MILANO A,B,C,H,I,J.pdf · uploaded 29 Jun 2022Source
  • DocumentP51700011629 · PALAVA - MILANO E,F.pdf · uploaded 30 Jun 2022Source

Technical (Engineer)

  • DocumentP51700011629 · 3 PALAVA - MILANO E,F.pdf · uploaded 4 Aug 2022Source
  • DocumentP51700015016 · 7 PALAVA - MILANO A,B,C,H,I,J.pdf · uploaded 4 Aug 2022Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 141/3 pt, 29/5pt

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Phases
2
Unit types
1 BHK, 1BHK, 2BHK, 2 BHK ULTIMA, 2BHK Ultima, 3 BHK OPTIMA, 2 BHK Ultima, 2BHKOptima, 2BHKUltima, 3BHK, 2BHK ultima665 units in all
Address
36/2 pt, 141/3 pt, 36/3 pt, 36/5 ptPIN 421202
Village
Khoni, Kalyan taluka
Land area for this project
2,657 sq m (28,600 sq ft)
Permissible built-up area
14,658 sq m (1,57,779 sq ft)
Sanctioned built-up area
13,325 sq m (1,43,431 sq ft)
Recreational open space
1,781 sq m (19,175 sq ft)
Designated bank account
229
Developed in phases
Yes
Also registered as
Palava Milano E, F, Palava Milano A, B, C, H, I, J

Survey, CTS, gat or plot numbers

141/3 pt29/5pt29/6pt36/1pt36/2 pt36/3 pt36/5 pt36/6pt

Land as published on MahaRERA's project page

36/2 pt, 141/3 pt, 36/3 pt, 36/5 pt

Boundaries

North
36 by 2 pt
South
36 by 3 pt 36 by 5 pt
East
141 by 3 pt 141 by 4 pt
West
Residetial Bldg

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking665 units

481 of 665 units booked (72%), as the promoter reported to MahaRERA

1 BHK · 76 units1BHK · 200 units2BHK · 71 units2 BHK ULTIMA · 120 units2BHK Ultima · 32 units3 BHK OPTIMA · 41 units2 BHK Ultima · 65 units2BHKOptima · 2 units2BHKUltima · 31 units3BHK · 2 units2BHK ultima · 25 units
RERABuildingTypeCarpet areaUnitsBooked
P51700015016Milano A1 BHK37.07 sq m · 399 sq ft5856
P51700015016Milano A1 BHK39.68 sq m · 427 sq ft11
P51700015016Milano A1 BHK47.19 sq m · 508 sq ft20
P51700015016Milano A1BHK37 sq m · 398 sq ft66
P51700015016Milano A1BHK39.76 sq m · 428 sq ft11
P51700015016Milano A2BHK52.86 sq m · 569 sq ft11
P51700015016Milano A2 BHK ULTIMA50.14 sq m · 540 sq ft22
P51700015016Milano A2 BHK ULTIMA52.82 sq m · 569 sq ft11
Show all 59 unit rowsShow fewer unit rows
RERABuildingTypeCarpet areaUnitsBooked
P51700015016Milano A2BHK Ultima50.17 sq m · 540 sq ft3221
P51700015016Milano A3 BHK OPTIMA59.64 sq m · 642 sq ft11
P51700015016Milano B1 BHK39.48 sq m · 425 sq ft20
P51700015016Milano B2 BHK Ultima49.05 sq m · 528 sq ft3217
P51700015016Milano B2 BHK Ultima50.17 sq m · 540 sq ft10
P51700015016Milano B3 BHK OPTIMA59.74 sq m · 643 sq ft3513
P51700015016Milano C1 BHK39.76 sq m · 428 sq ft22
P51700015016Milano C1 BHK47.19 sq m · 508 sq ft20
P51700015016Milano C1BHK37.07 sq m · 399 sq ft6462
P51700015016Milano C2 BHK ULTIMA50.17 sq m · 540 sq ft3418
P51700015016Milano C2 BHK ULTIMA52.82 sq m · 569 sq ft21
P51700015016Milano C3 BHK OPTIMA59.64 sq m · 642 sq ft11
P51700011629Milano E2BHK45.52 sq m · 490 sq ft10
P51700011629Milano E2BHK48.64 sq m · 524 sq ft10
P51700011629Milano E2BHK48.67 sq m · 524 sq ft10
P51700011629Milano E2BHK50.35 sq m · 542 sq ft130
P51700011629Milano E2BHK51.95 sq m · 559 sq ft160
P51700011629Milano E2BHK53.11 sq m · 572 sq ft130
P51700011629Milano E2BHK53.93 sq m · 580 sq ft10
P51700011629Milano E2BHK54.72 sq m · 589 sq ft11
P51700011629Milano E2BHK56.39 sq m · 607 sq ft11
P51700011629Milano E2BHK57.3 sq m · 617 sq ft30
P51700011629Milano E2BHK57.6 sq m · 620 sq ft11
P51700011629Milano E2BHK57.69 sq m · 621 sq ft1818
P51700011629Milano E2BHKOptima54.64 sq m · 588 sq ft22
P51700011629Milano E2BHKUltima53.08 sq m · 571 sq ft11
P51700011629Milano E2BHKUltima57.64 sq m · 620 sq ft2828
P51700011629Milano E2BHKUltima61.5 sq m · 662 sq ft22
P51700011629Milano E3BHK73.62 sq m · 792 sq ft20
P51700015016Milano H1 BHK39.76 sq m · 428 sq ft22
P51700015016Milano H1 BHK47.19 sq m · 508 sq ft20
P51700015016Milano H1BHK37.07 sq m · 399 sq ft6463
P51700015016Milano H2 BHK ULTIMA50.17 sq m · 540 sq ft3411
P51700015016Milano H2 BHK ULTIMA52.86 sq m · 569 sq ft20
P51700015016Milano H3 BHK OPTIMA59.64 sq m · 642 sq ft11
P51700015016Milano I1 BHK39.48 sq m · 425 sq ft22
P51700015016Milano I2 BHK Ultima55.18 sq m · 594 sq ft11
P51700015016Milano I2 BHK ULTIMA48.96 sq m · 527 sq ft77
P51700015016Milano I2 BHK ULTIMA59.74 sq m · 643 sq ft3325
P51700015016Milano I2BHK ultima49.05 sq m · 528 sq ft2518
P51700015016Milano I3 BHK OPTIMA59.66 sq m · 642 sq ft11
P51700015016Milano I3 BHK OPTIMA59.72 sq m · 643 sq ft11
P51700015016Milano J1 BHK39.68 sq m · 427 sq ft11
P51700015016Milano J1 BHK47.19 sq m · 508 sq ft20
P51700015016Milano J1BHK37 sq m · 398 sq ft88
P51700015016Milano J1BHK37.07 sq m · 399 sq ft5655
P51700015016Milano J1BHK39.76 sq m · 428 sq ft11
P51700015016Milano J2 BHK Ultima50.17 sq m · 540 sq ft3122
P51700015016Milano J2 BHK ULTIMA50.14 sq m · 540 sq ft33
P51700015016Milano J2 BHK ULTIMA52.86 sq m · 569 sq ft20
P51700015016Milano J3 BHK OPTIMA59.64 sq m · 642 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.