Sai Srushti

Completion date passed

Khadakpada, Thane 421301 |Promoter: Shakti Realty

6 Sep 2018Registered with MahaRERA
30 Jun 2022Promised completion
8 Apr 2024Revised completionPushed back 1 year and 10 months
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

MahaRERA's search listing gives this project's name, promoter and location only.

MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year and 10 months

The latest completion date on record passed 2 years and 6 months ago.

Registered
6 Sep 2018
Promised
30 Jun 2022
Revised
8 Apr 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000177006 Sep 201830 Jun 20228 Apr 2024Shakti RealtyProject page

Documents

2 documents held by Deedo

Registration certificate

Extension certificate

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Khadakpada

Survey, CTS, gat or plot numbers

41/1142/1A42/1B55/3

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology