Skip to content
Others · 1 building · 137 unitsRERA P51700028361

Aroma

Deedo IDDP-THN-9YE6

MahaRERA shows it completed; no MahaRERA orders on record; 90% of its units are booked.

Kavesar, Thane 400615 · by Sagar Enterprise · 75% of its projects kept the RERA date

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales90% booked123 of 137 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 22 Feb 2021, completion promised 30 Nov 2026.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700028361
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170002836122 Feb 202130 Nov 202630 Nov 2026Sagar EnterpriseProject page
Documents152

2 documents held by Deedo, 150 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN CardSagar Ent- NEW PAN.pdf · uploaded 27 Jan 2021Source

Legal

  • Other7 12.pdf · uploaded 2 Feb 2021Source
  • Legal Title reportRevised Title Certificate.pdf · uploaded 6 Feb 2021Source
  • Declaration Form BB Form.pdf · uploaded 10 Feb 2021Source
  • Declaration Form BForm B.pdf · uploaded 11 Oct 2024Source
  • Declaration Form BAffidavit cum Declaration.pdf · uploaded 15 Nov 2024Source
Show all 152 documentsShow fewer documents

Legal

  • Declaration Form BFORM -B 30-10-2024.pdf · uploaded 18 Nov 2024Source
  • Declaration Form BFORM -B (6).pdf · uploaded 6 Feb 2025Source

Migrated

  • 1 PAN CardSagar Ent- NEW PAN.pdf · uploaded 27 Jan 2021Source
  • 1 Details of encumbrancesNo Encumbrances Letter.pdf · uploaded 27 Jan 2021Source
  • 1 Copy of Layout Approval (in case of layout)PLAN 1.pdf · uploaded 27 Jan 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentPLAN 2.pdf · uploaded 27 Jan 2021Source
  • 2 Building Plan Approval / NA Order for plotted developmentPLAN 3.pdf · uploaded 27 Jan 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentC C Copy.pdf · uploaded 27 Jan 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 27 Jan 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Draft 2.pdf · uploaded 27 Jan 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 RCC Certificate.pdf · uploaded 27 Jan 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 27 Jan 2021Source
  • 1 Proforma of Allotment letterAGREEMENT FOR SALE.pdf · uploaded 27 Jan 2021Source
  • 1 Other7 12.pdf · uploaded 2 Feb 2021Source
  • 1 Copy of the legal title reportRevised Title Certificate.pdf · uploaded 6 Feb 2021Source
  • 1 Declaration in FORM BB Form.pdf · uploaded 10 Feb 2021Source
  • 2 Proforma of Allotment letterAllotment Letter_Sagar Enterprises.pdf · uploaded 17 Feb 2021Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 24 Aug 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 24 Aug 2021Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM III1.pdf · uploaded 24 Aug 2021Source
  • 2 Details of encumbrancesEncumbrances certificate.pdf · uploaded 7 Jan 2022Source
  • 2 Copy of Layout Approval (in case of layout)Plan 1.pdf · uploaded 7 Jan 2022Source
  • 3 Copy of Layout Approval (in case of layout)Plan 2.pdf · uploaded 7 Jan 2022Source
  • 4 Copy of Layout Approval (in case of layout)Plan 3.pdf · uploaded 7 Jan 2022Source
  • 5 Copy of Layout Approval (in case of layout)Plan 4.pdf · uploaded 7 Jan 2022Source
  • 3 Building Plan Approval / NA Order for plotted developmentPlan 2.pdf · uploaded 7 Jan 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentRevised CC.pdf · uploaded 7 Jan 2022Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM I.pdf · uploaded 7 Jan 2022Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form II.pdf · uploaded 7 Jan 2022Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 7 Jan 2022Source
  • 1 CERSAI detailsAroma.pdf · uploaded 29 Dec 2022Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 1 Feb 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 RCC.pdf · uploaded 1 Feb 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 (1)_compressed.pdf · uploaded 1 Feb 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Aroma.pdf · uploaded 7 Apr 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 24 Apr 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Aroma as on 31-03-2023.pdf · uploaded 24 Apr 2023Source
  • 1 Disclosure of sold/ booked inventoryCircular 29 for Aroma.pdf · uploaded 25 May 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Aroma as on 30-09-2022.pdf · uploaded 22 Jun 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Aroma as on 31-12-2022.pdf · uploaded 22 Jun 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Aroma as on 30-09-2022.pdf · uploaded 22 Jun 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Aroma as on 31-12-2022.pdf · uploaded 22 Jun 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Aroma (1).pdf · uploaded 25 Jul 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Aroma as on June 2023.pdf · uploaded 26 Jul 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Aroma as on 30-06-2023.pdf · uploaded 26 Jul 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 AROMA as on Sep 2023.pdf · uploaded 5 Oct 2023Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Aroma as on Sep 2023.pdf · uploaded 11 Oct 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Aroma as on 30-09-2023.pdf · uploaded 11 Oct 2023Source
  • 3 Details of encumbrancesENCUMBRANCES CERTIFICATE.pdf · uploaded 29 Dec 2023Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Aroma as on Dec 2023.pdf · uploaded 5 Jan 2024Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Aroma as on Dec 2023.pdf · uploaded 11 Jan 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Aroma as on Dec 2023.pdf · uploaded 12 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 - Aroma FY 21-22.pdf · uploaded 14 Feb 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 - Aroma FY 22-23.pdf · uploaded 14 Feb 2024Source
  • 2 Disclosure of sold/ booked inventoryAroma.pdf · uploaded 23 Feb 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5-Aroma 20-21.pdf · uploaded 2 Mar 2024Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Aroma as on March 2024.pdf · uploaded 18 Jun 2024Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Aroma as on March 2024.pdf · uploaded 18 Jun 2024Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Aroma as on March 2024.pdf · uploaded 18 Jun 2024Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 20 Jul 2024Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)11 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf · uploaded 20 Jul 2024Source
  • 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)xxxxxxxxxx.pdf · uploaded 20 Jul 2024Source
  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Aroma as on June 2024.pdf · uploaded 27 Jul 2024Source
  • 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Aroma as on 30-06-2024.pdf · uploaded 27 Jul 2024Source
  • 2 Declaration in FORM BForm B.pdf · uploaded 11 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 11 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 11 Oct 2024Source
  • 1 Disclosure of sold/ booked inventoryCIRCULAR 29.pdf · uploaded 11 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 21-22.pdf · uploaded 11 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 22-23.pdf · uploaded 11 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)20-21 (1).pdf · uploaded 24 Oct 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Declaration Aroma.pdf · uploaded 24 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)21-22 (1).pdf · uploaded 24 Oct 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest Aroma.pdf · uploaded 24 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)22-23.pdf · uploaded 24 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)23-24.pdf · uploaded 24 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)form 5 -20-21.pdf · uploaded 25 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM I AROMA.pdf · uploaded 11 Nov 2024Source
  • 3 Declaration in FORM BAffidavit cum Declaration.pdf · uploaded 15 Nov 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentAROMA OC.pdf · uploaded 15 Nov 2024Source
  • 4 Declaration in FORM BFORM -B 30-10-2024.pdf · uploaded 18 Nov 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Aroma as on 30-09-2024.pdf · uploaded 22 Nov 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)ARCHITECT'S CERTIFICATE (2).pdf · uploaded 2 Jan 2025Source
  • 1 Declaration in FORM BFORM -B (6).pdf · uploaded 6 Feb 2025Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)ARCHITECT'S CERTIFICATE (2).pdf · uploaded 6 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)12 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 17 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)15 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf · uploaded 17 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)14 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 17 Feb 2025Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmenthdnhn.pdf · uploaded 27 Mar 2025Source
  • Withdrawal Update Form 1Form 1 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 1Form 1 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 1Form 1 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 1Form 1 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 1Form 1 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 1Form 1 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 2Form 2 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 2Form 2 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 2Form 2 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 2Form 2 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 2Form 2 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 2Form 2 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source
  • Form 2A (FY 2024-2025)Form 2A(FY 2024-25).pdf · uploaded 27 Jul 2026Source
  • Form 2A (FY 2025-2026)Form 2A(FY 2024-25).pdf · uploaded 27 Jul 2026Source
  • Form 2A (FY 2020-2021)Form 2A_FY_2020-21.pdf · uploaded 18 Aug 2026Source
  • Form 2A (FY 2021-2022)Fom 2A_FY_2021-22.pdf · uploaded 18 Aug 2026Source
  • Form 2A (FY 2022-2023)Form 2A_FY_2022-23.pdf · uploaded 18 Aug 2026Source
  • Form 2A (FY 2023-2024)Form 2A_FY_2023-24.pdf · uploaded 18 Aug 2026Source
  • Form 2A (FY 2026-2027)Form 2A_FY_2024-25.pdf · uploaded 18 Aug 2026Source
  • Form 5 (FY 2025-2026)Form 5_FY_2022-23.pdf · uploaded 18 Aug 2026Source
  • Occupational CertificateOccupancy Certificate.pdf · uploaded 18 Aug 2026Source
  • Occupational CertificateCommencement Certificate.pdf · uploaded 18 Aug 2026Source
  • Occupational CertificateCC Plan 1.pdf · uploaded 18 Aug 2026Source
  • Occupational CertificateCC Plan 2.pdf · uploaded 18 Aug 2026Source
  • Occupational CertificateCC Plan 3.pdf · uploaded 18 Aug 2026Source
  • Occupational CertificateCC Plan 4.pdf · uploaded 18 Aug 2026Source
  • Occupational CertificateOC Verification Mail Screenshot.pdf · uploaded 18 Aug 2026Source

Planning Authority

  • Document9kdg695HquSAAT_BARA.pdf · uploaded 28 Jul 2026Source
  • Document1EzsMQOONZSANCTIONED_PLANS.pdf · uploaded 28 Jul 2026Source
  • DocumentCert_FO_429041_407O9KQ9Sign.pdf · uploaded 28 Jul 2026Source
  • Document1EzsMQOONZPERMISSION_CC.pdf · uploaded 28 Jul 2026Source

Technical

  • DocumentPLAN 1.pdf · uploaded 27 Jan 2021Source
  • DocumentPLAN 2.pdf · uploaded 27 Jan 2021Source
  • DocumentPLAN 3.pdf · uploaded 27 Jan 2021Source
  • DocumentPlan 1.pdf · uploaded 7 Jan 2022Source
  • DocumentPlan 2.pdf · uploaded 7 Jan 2022Source
  • DocumentPlan 3.pdf · uploaded 7 Jan 2022Source
  • DocumentPlan 4.pdf · uploaded 7 Jan 2022Source
  • DocumentPlan 2.pdf · uploaded 7 Jan 2022Source
  • DocumentCC Plan 1.pdf · uploaded 27 Jul 2026Source
  • DocumentCC Plan 2.pdf · uploaded 27 Jul 2026Source
  • DocumentCC Plan 3.pdf · uploaded 27 Jul 2026Source
  • DocumentCC Plan 4.pdf · uploaded 27 Jul 2026Source

Technical (Architect)

  • DocumentFORM I AROMA.pdf · uploaded 11 Nov 2024Source
  • Document12 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 17 Feb 2025Source
  • DocumentForm 1 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 11 Oct 2024Source
  • Document14 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 17 Feb 2025Source
  • DocumentForm 2 - Aroma as on June 2026.pdf · uploaded 27 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel H.NO.4, Sector_no 6

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, Landowner Units, Shop137 units in all
Address
Survey No 3 Hissa No 4, Ghodbunder Road, KavesarPIN 400615
Village
Kavesar, Thane taluka
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

H.NO.4Sector_no 6S. NO.3

Boundaries

North
40 Mtr Wide Road
South
Survey No 3 Hissa No 8
East
30 Mtr Wide Road
West
Survey No 265

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking137 units

123 of 137 units booked (90%), as the promoter reported to MahaRERA

1BHK · 120 unitsLandowner Units · 12 unitsShop · 5 units
TypeCarpet areaUnitsBooked
1BHK25.9 sq m · 279 sq ft3433
1BHK26.92 sq m · 290 sq ft2320
1BHK26.93 sq m · 290 sq ft4233
1BHK29.91 sq m · 322 sq ft2120
Landowner Units25.9 sq m · 279 sq ft66
Landowner Units26.93 sq m · 290 sq ft44
Landowner Units29.91 sq m · 322 sq ft22
Shop15.44 sq m · 166 sq ft11
Show all 12 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop16.04 sq m · 173 sq ft11
Shop17.9 sq m · 193 sq ft11
Shop20.13 sq m · 217 sq ft11
Shop20.44 sq m · 220 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
EngineerSarvesh Patil—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology